STOCK TITAN

Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
AI
Applied Digital (APLD) has secured two 15-year lease agreements with CoreWeave to provide 250MW of critical IT load for AI and HPC infrastructure at its Ellendale, North Dakota data center campus. The agreements are expected to generate approximately $7 billion in total revenue over the term. The first 100MW data center is scheduled for completion in Q4 2025, followed by a 150MW facility in mid-2026. CoreWeave also has an option for an additional 150MW, potentially expanding their presence at the facility. The Ellendale campus is designed to host 400MW of critical IT load with potential to scale up to 1 gigawatt, featuring advantages such as rapid deployment capabilities, strategic location, and access to low-cost energy.
Applied Digital (APLD) ha stipulato due contratti di locazione della durata di 15 anni con CoreWeave per fornire 250MW di carico IT critico destinato a infrastrutture di AI e HPC presso il campus del data center di Ellendale, nel Dakota del Nord. Si prevede che questi accordi genereranno circa 7 miliardi di dollari di ricavi totali durante il periodo contrattuale. Il primo data center da 100MW è previsto per il completamento nel quarto trimestre del 2025, seguito da una struttura da 150MW a metà del 2026. CoreWeave dispone inoltre di un'opzione per ulteriori 150MW, potenzialmente ampliando la propria presenza nella struttura. Il campus di Ellendale è progettato per ospitare 400MW di carico IT critico con la possibilità di scalare fino a 1 gigawatt, offrendo vantaggi come rapide capacità di implementazione, posizione strategica e accesso a energia a basso costo.
Applied Digital (APLD) ha asegurado dos contratos de arrendamiento de 15 años con CoreWeave para proporcionar 250MW de carga informática crítica para infraestructura de IA y HPC en su campus de centro de datos en Ellendale, Dakota del Norte. Se espera que los acuerdos generen aproximadamente 7 mil millones de dólares en ingresos totales durante el plazo. El primer centro de datos de 100MW está programado para completarse en el cuarto trimestre de 2025, seguido por una instalación de 150MW a mediados de 2026. CoreWeave también tiene una opción para 150MW adicionales, lo que podría ampliar su presencia en la instalación. El campus de Ellendale está diseñado para alojar 400MW de carga informática crítica con potencial para escalar hasta 1 gigavatio, con ventajas como capacidades de implementación rápida, ubicación estratégica y acceso a energía de bajo costo.
Applied Digital(APLD)는 노스다코타 Ellendale 데이터 센터 캠퍼스에서 AI 및 HPC 인프라를 위한 250MW의 중요한 IT 부하를 제공하기 위해 CoreWeave와 15년 임대 계약 두 건을 체결했습니다. 이 계약들은 계약 기간 동안 약 70억 달러의 총 수익을 창출할 것으로 예상됩니다. 첫 번째 100MW 데이터 센터는 2025년 4분기에 완공될 예정이며, 이어서 2026년 중반에 150MW 시설이 완공됩니다. CoreWeave는 추가로 150MW를 선택할 수 있는 옵션도 보유하고 있어 시설 내 입지를 확장할 가능성이 있습니다. Ellendale 캠퍼스는 400MW의 중요한 IT 부하를 수용할 수 있도록 설계되었으며 최대 1기가와트까지 확장할 수 있는 잠재력을 갖추고 있습니다. 신속한 배치 능력, 전략적 위치, 저비용 에너지 접근성 등의 장점이 있습니다.
Applied Digital (APLD) a conclu deux contrats de location de 15 ans avec CoreWeave pour fournir 250 MW de charge informatique critique destinée aux infrastructures d'IA et de HPC sur son campus de centre de données à Ellendale, dans le Dakota du Nord. Ces accords devraient générer environ 7 milliards de dollars de revenus totaux sur la durée. Le premier centre de données de 100 MW est prévu pour être achevé au quatrième trimestre 2025, suivi d'une installation de 150 MW à la mi-2026. CoreWeave dispose également d'une option pour 150 MW supplémentaires, ce qui pourrait étendre leur présence sur le site. Le campus d'Ellendale est conçu pour accueillir 400 MW de charge informatique critique avec un potentiel d'extension jusqu'à 1 gigawatt, offrant des avantages tels qu'une capacité de déploiement rapide, un emplacement stratégique et un accès à une énergie à faible coût.
Applied Digital (APLD) hat zwei 15-jährige Mietverträge mit CoreWeave abgeschlossen, um 250 MW kritische IT-Last für KI- und HPC-Infrastruktur auf dem Datenzentrumsgelände in Ellendale, North Dakota, bereitzustellen. Die Verträge sollen über die Laufzeit hinweg etwa 7 Milliarden US-Dollar Gesamterlöse generieren. Das erste 100-MW-Datenzentrum soll im vierten Quartal 2025 fertiggestellt werden, gefolgt von einer 150-MW-Anlage Mitte 2026. CoreWeave hat zudem eine Option für weitere 150 MW, was eine Erweiterung ihrer Präsenz auf dem Gelände ermöglichen könnte. Der Ellendale-Campus ist für eine kritische IT-Last von 400 MW ausgelegt und kann potenziell auf 1 Gigawatt skaliert werden. Zu den Vorteilen zählen schnelle Einsatzmöglichkeiten, eine strategische Lage und Zugang zu kostengünstiger Energie.
Positive
  • Secured approximately $7 billion in total revenue over 15-year lease agreements
  • CoreWeave retains option for additional 150MW expansion, showing growth potential
  • Strategic location with access to abundant, low-cost energy
  • Campus designed to scale up to 1 gigawatt over time
  • Energy-efficient climate enables rapid capacity deployment
Negative
  • Significant construction and development timeline extending into 2026-2027
  • Large capital investment required for infrastructure development
  • Heavy reliance on single customer (CoreWeave) for revenue

Insights

Applied Digital secures transformative $7B, 15-year deal with CoreWeave for 250MW AI data center capacity, significantly strengthening its competitive position in AI infrastructure.

Applied Digital's landmark agreement with CoreWeave represents a game-changing development in the AI infrastructure landscape. The $7 billion total revenue expected over the approximately 15-year term translates to roughly $467 million annually - a substantial recurring revenue stream that provides exceptional visibility into the company's long-term financial trajectory.

What makes this deal particularly compelling is the strategic positioning of the Ellendale campus. The facility's design addresses the critical bottlenecks in AI deployment: power capacity, deployment speed, and location efficiency. The campus's planned 1 gigawatt scale puts it among North America's most ambitious data center projects, with the current agreement securing utilization for a significant portion (250MW) of that capacity.

The implementation timeline is aggressive yet achievable - with the first 100MW expected online by Q4 2025 and the additional 150MW by mid-2026. CoreWeave's option for another 150MW further validates the facility's value proposition and provides a clear path to additional upside.

From an industry perspective, this deal represents a significant vote of confidence in Applied Digital's execution capabilities. CoreWeave, a specialized AI infrastructure provider, has selected Applied Digital for this massive deployment over numerous competing options. This partnership positions Applied Digital as a key enabler in the AI compute infrastructure ecosystem - a sector experiencing exponential growth as generative AI applications proliferate.

The strategic value of securing a purpose-built, high-density compute facility with access to abundant, low-cost energy cannot be overstated in today's AI landscape, where power consumption and cooling requirements have become critical constraints for large language model deployment.

This lease agreement represents a transformative financial development for Applied Digital. The $7 billion in anticipated revenue over the approximately 15-year term provides extraordinary visibility into the company's long-term financial trajectory and dramatically changes its business outlook.

To put this in perspective, this single agreement translates to an average of $467 million in annual revenue over the contract period. The long-term nature of these leases creates a stable, predictable revenue stream that significantly de-risks Applied Digital's business model and provides a solid foundation for future growth investments.

The phased implementation approach is financially prudent - with the first 100MW data center coming online in Q4 2025, followed by 150MW in mid-2026. This staged deployment allows for distributed capital expenditure while beginning to generate revenue within an 18-month timeframe.

CoreWeave's option for an additional 150MW represents meaningful potential upside not yet reflected in the announced $7 billion figure. If exercised, this option would increase the total contracted capacity by 60%, with corresponding revenue implications.

From a competitive positioning standpoint, this agreement establishes Applied Digital as a significant player in the AI infrastructure space. The company's ability to secure such a substantial commitment from CoreWeave demonstrates its capability to deliver mission-critical infrastructure at scale - a key differentiator in the increasingly competitive AI data center market.

The economics of this deal highlight the profound value creation potential in purpose-built AI infrastructure. The revenue per MW metrics implied by this agreement reflect the premium economics available to providers who can effectively address the specific requirements of AI compute workloads.

Ellendale, North Dakota data center campus

DALLAS, June 02, 2025 (GLOBE NEWSWIRE) -- Applied Digital Corporation (Nasdaq: APLD), a designer, builder and operator of next-generation digital infrastructure for HPC applications, has entered into two approximately 15-year lease agreements with CoreWeave, the AI Hyperscaler™.

Under the lease agreements, Applied Digital will deliver 250 megawatts (MW) of critical IT load to host CoreWeave's artificial intelligence (AI) and high-performance computing (HPC) infrastructure at its Ellendale, North Dakota data center campus. Over the approximately 15-year term, Applied Digital anticipates generating approximately $7 billion in total revenue from the leases.

Pursuant to the lease agreements, CoreWeave also retains the option to access an additional 150 MW of critical IT load at Ellendale, positioning the campus as a scalable hub for expanding AI and HPC workloads. “We believe these leases solidify Applied Digital’s position as an emerging provider of infrastructure critical to the next generation of artificial intelligence and high-performance computing,” said Wes Cummins, Chairman and CEO of Applied Digital. “As demand for AI accelerates exponentially, we believe that we are uniquely positioned to deliver substantial returns while supporting the evolving and dynamic needs of these rapidly evolving sectors. We view CoreWeave as an ideal partner as we accelerate our growth and innovation.”

Applied Digital’s Ellendale campus is believed to be one of the most ambitious data center developments currently underway in North America. Intended to be purpose-built for next-generation workloads, the facility combines large-scale power capacity with rapid deployment capabilities – both critical for AI and HPC clients.

The Ellendale campus was planned to be engineered for high-density compute and designed to scale up to 1 gigawatt over time. The two approximately 15-year lease agreements mark a foundational step in unlocking the campus’s full potential.

“We believe Ellendale is more than a development project — it’s a launchpad for the future of AI infrastructure,” added Cummins. “We intend for this platform to put us in a strong position to support early demand while continuing to grow alongside our customers. Through these newly signed long-term leases with CoreWeave, we are taking a step forward in our strategic expansion into advanced compute infrastructure.”

Applied Digital designed Ellendale for the speed and efficiency of deployment, prime location, AI innovative design, and access to abundant, low-cost energy. The energy-efficient climate is intended to further enable Applied Digital to meet the rapid capacity demands, positioning both the region and the company as emerging leaders in the AI data center ecosystem. Applied Digital expects the first 100 MW data center for CoreWeave to be ready for service in the fourth quarter of calendar 2025. The second building, which is expected to house a 150 MW data center, is currently under construction and is expected to be ready for service in the middle of 2026. Additionally, CoreWeave holds an option for the third 150 MW building, which is currently in the planning stages, anticipated to be ready for service in 2027.

Applied Digital’s Ellendale campus is designed to host 400 MW of critical IT load. Ellendale has 1+ gigawatts of power capacity currently under various stages of load study, allowing the campus to expand its power capacity to support additional AI and HPC data center infrastructure development.

About Applied Digital
Applied Digital (Nasdaq: APLD) develops, builds and operates next-generation data centers and infrastructure. Different by design, the Company’s purpose-built facilities are engineered to unleash the power of accelerated compute and deliver secure, scalable and sustainable digital hosting, enabling CSaaS and GPU-as-a-Service solutions. Backed by deep hyperscale expertise and a robust pipeline of available power, Applied Digital accommodates AI Factories and beyond to support AI/ML, blockchain and high-performance computing (HPC) workloads.

CAUTION ABOUT FORWARD-LOOKING STATEMENTS
This press release contains “forward-looking statements” as defined in the Private Securities Litigation Reform Act of 1995 regarding, among other things, future operating and financial performance, product development, market position, business strategy and objectives and future financing plans. These statements use words, and variations of words, such as “will,” “continue,” “build,” “future,” “increase,” “drive,” “believe,” “look,” “ahead,” “confident,” “deliver,” “outlook,” “expect,” “project” and “predict.” Other examples of forward-looking statements may include, but are not limited to, (i) statements that reflect perspectives and expectations regarding the lease agreements and campus development, (ii) statements about the HPC industry, (iii) statements of Company plans and objectives, including our evolving business model, or estimates or predictions of actions by suppliers, (iv) statements of future economic performance, and (v) statements of assumptions underlying other statements and statements about the Company or its business. You are cautioned not to rely on these forward-looking statements. These statements are based on current expectations of future events and thus are inherently subject to uncertainty. If underlying assumptions prove inaccurate or known or unknown risks or uncertainties materialize, actual results could vary materially from the Company’s expectations and projections. These risks, uncertainties, and other factors include: our ability to complete construction of the Ellendale HPC data centers; changes to AI and HPC infrastructure needs and their impact on future plans; risks associated with the leasing business, including those associated with counterparties; costs related to the HPC operations and strategy; our ability to timely deliver any services required in connection with completion of installation under the lease agreements; our ability to raise additional capital to fund ongoing and future data center construction and operations; our ability to obtain financing of the lease agreements on acceptable financing terms, or at all; our dependence on principal customers, including our ability to execute and perform our obligations under our leases with key customers, including without limitation, the lease agreements; our ability to timely and successfully build hosting facilities with the appropriate contractual margins and efficiencies; power or other supply disruptions and equipment failures; the inability to comply with regulations, developments and changes in regulations; cash flow and access to capital; availability of financing to continue to grow our business; decline in demand for our products and services; maintenance of third party relationships; and conditions in the debt and equity capital markets. A further list and description of these risks, uncertainties and other factors can be found in the company's most recently filed Annual Report on Form 10-K and Quarterly Report on Form 10-Q, including in the sections captioned “Forward-Looking Statements” and “Risk Factors,” and in the company's subsequent filings with the Securities and Exchange Commission. Copies of these filings are available online at www.sec.gov, on the Company’s website (www.applieddigital.com) under “Investors,” or on request from the Company. Information in this release is as of the dates and time periods indicated herein, and the Company does not undertake to update any of the information contained in these materials, except as required by law.

Media Contacts
Buffy Harakidas and Jo Albers
JSA (Jaymie Scotto & Associates)
jsa_applied@jsa.net

Investor Relations Contacts
Matt Glover or Ralf Esper
Gateway Group, Inc.
(949) 574-3860
APLD@gateway-grp.com

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/4bba31cc-5279-4ef8-9a82-1cb0b4a7069f


FAQ

What is the value of Applied Digital's (APLD) lease agreement with CoreWeave?

The lease agreements are expected to generate approximately $7 billion in total revenue over the 15-year term

When will Applied Digital's Ellendale data center be operational for CoreWeave?

The first 100MW data center will be ready in Q4 2025, with the second 150MW facility expected by mid-2026

What is the total power capacity of Applied Digital's Ellendale campus?

The campus is designed to host 400MW of critical IT load with potential to scale up to 1 gigawatt over time

Where is Applied Digital's (APLD) new AI data center located?

The data center campus is located in Ellendale, North Dakota

How long are the lease agreements between Applied Digital and CoreWeave?

The lease agreements are for approximately 15 years
Applied Digital

NASDAQ:APLD

APLD Rankings

APLD Latest News

APLD Stock Data

1.71B
174.79M
20.08%
67.51%
25.46%
Information Technology Services
Services-computer Processing & Data Preparation
Link
United States
DALLAS