Bunker Hill Shareholders Vote to Approve Business Combination With Silver47 Exploration Corp, as Company Completes Drawdowns of Ocean Partners and Teck Facilities Supporting Ramp-Up to Commercial Production by End Q4 2026
Concentrate shipments are underway, while final court and stock exchange approvals remain outstanding for the proposed combination.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Bunker Hill Mining (BHLL) shareholders approved resolutions supporting the proposed business combination with Silver47 Exploration, advancing the transaction toward closing. Silver47 shareholders also approved the deal. Bunker Hill anticipates closing on or about November 5, 2026, subject to final court and stock exchange approvals.
The Ocean Partners and Teck facilities are fully drawn, providing aggregate proceeds of US$20,000,000. Funding supports plant optimization, underground development and initial concentrate sales cycles. Zinc and lead-silver concentrates are being transported to market. Average plant throughput exceeds 1100t/day, excluding downtime, with lead and zinc recoveries averaging greater than 70%. The company expects commercial production by end Q4 2026 and plans a resource and reserve update and 2027 production guidance by year-end. A study is progressing on increasing production to 2500tpd from 2027.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Major pointFully drawn financing facilities provided aggregate proceeds of US$20,000,000 to support the mine ramp-up. 20% of market cap
- Moderate pointBunker Hill shareholders approved the combination-related resolutions; Silver47 shareholders also approved the transaction.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Commercial production remains the company's target for end Q4 2026.
- Moderate pointAverage plant throughput exceeds 1100t/day, excluding downtime, with lead and zinc recoveries averaging greater than 70%.
- Minor pointZinc and lead-silver concentrates are now being transported to market.
6 minor points
- Minor pointUnderground mining is meeting tonnage and grade requirements for the current ramp-up stage.
- Minor pointThe largest long-hole transverse stope blasted to date moved 7000t of ore.
- Minor pointThe operation has recorded 569 days since its last reportable injury.
- Minor point. Forward-looking: it has not happened yet and may not happen.A production expansion study is progressing toward 2500tpd from 2027, including a new portal and facility enhancements.
- Minor point. Forward-looking: it has not happened yet and may not happen.A resource and reserve update incorporating Cate-8 and other near-mine discoveries is planned by end 2026.
- Minor point. Forward-looking: it has not happened yet and may not happen.2027 production guidance is expected by end 2026, accounting for ramp-up, exploration, studies and mine planning.
Negative
- Minor pointTransaction closing remains subject to final court and stock exchange approvals; closing is anticipated around November 5, 2026.
- Minor pointThe US$10,000,000 Ocean Partners concentrate prepayment facility is fully drawn, committing future concentrate-related funding obligations.
- Minor pointThe Teck standby facility is fully drawn at US$10,000,000 aggregate principal, adding debt obligations.
AI-generated analysis. How Rhea-AI works. Not financial advice.
KELLOGG, Idaho and VANCOUVER, British Columbia, Oct. 28, 2026 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. ("Bunker Hill" or the "Company") (TSX: BNKR | OTCQB: BHLL) is pleased to announce that Bunker Hill stockholders approved all matters voted on at the special meeting of stockholders (the "Meeting") held today in Kellogg, Idaho, including the charter amendment and share issuance resolutions in connection with the proposed business combination (the “Transaction”) with Silver47 Exploration Corp. (TSXV: AGA | OTCQX: AAGAF | Frankfurt: QP2) (“Silver47”).
The Company is also pleased to announce that it remains on track to achieve commercial production by end Q4 2026, supported by the drawing down of the remaining amounts available under its concentrate prepayment facility (the "Ocean Partners Facility") with Ocean Partners UK Ltd. ("Ocean Partners"), and its existing standby facility (the "Standby Facility") provided by Teck Resources Limited, together with its affiliates ("Teck"). Together, the drawdowns provided aggregate proceeds of US
Sam Ash, President and CEO of Bunker Hill stated: "I wish to thank the combined Bunker Hill and Silver 47 shareholders for supporting this exciting transaction that will materially improve their exposure to US-based Silver and Critical Metals. This is a source of remarkable US-based investment value to be unlocked by the re-investment of cash flow generated by the Bunker Hill Mine, which remains on track to achieve commercial production by the end of 2026, supported by the drawdowns from the existing Teck and Ocean Partners facilities."
Special Meeting
A total of 27,295,759 shares of common stock (“Common Shares”) were represented in person or by proxy at the Meeting, representing approximately
All matters submitted to stockholders for approval as set out in the Company's proxy statement dated September 23, 2026 (the “Proxy Statement”), were approved by the requisite majorities of votes cast at the Meeting.
Of the votes cast at the Meeting: (i) 25,847,044 Common Shares, representing
In addition to the approval by Bunker Hill stockholders, the Silver47 shareholders approved the Transaction at its special meeting of shareholders held on October 27, 2026. Closing of the Transaction remains subject to satisfaction of certain customary conditions, including receipt of final court and stock exchange approvals. Subject to the satisfaction of these conditions, the Company anticipates that closing of the Transaction will occur on or about November 5, 2026. Further details regarding the Transaction, including the principal closing conditions and the anticipated benefits of the Transaction, can be found in the Proxy Statement, which can be found on the Company’s SEDAR+ profile at www.sedarplus.ca and on EDGAR at www.sec.gov.
Ramp-Up to Commercial Production

Fig 1: Zinc Concentrate being loaded into trucks for transport to Teck’s Trail Smelter
The operation is now transporting Zinc and Lead-Silver concentrates to market - the Zinc to Trail, British Columbia, and the Lead-Silver via Ocean Partners to various buyers. Other highlights include:
- The safety of the expanding Bunker Hill team remains the highest priority. It is now 569 days since the last reportable injury. The quality of front-line supervision and individual commitment to safety and operational improvement remains outstanding and reflective of the exceptional human mining talent available in the remarkable Silver Valley.
- The underground mining operation is meeting tonnage and grade requirements for this stage of ramp up through mining both UTZ on the 5-Level and part of the recently discovered Cate-8 on the 8-Level. It recently blasted its largest long hole-transverse stope to date: 7000t of ore moved from a 60ft long x 40ft wide x 50ft deep section, a breakthrough to a new level of efficiency and productivity.
- The average throughput in the plant is now above 1100t/day (excluding down time) with recoveries for both Lead and Zinc averaging >
70% , with plant availability targets improving as the maintenance systems evolve, training of the new team advances and mechanical optimization work is executed to plan. This places the plant on track to achieve its commercial targets by the end of 2026.
2027 Business Planning
The update to the Resource and Reserve Table is being worked on, to incorporate the Cate-8 and other near-mine discoveries. The Company plans to issue this update by the end of 2026.
Working with Ausenco and Tierra Group, the Bunker Hill technical team is progressing its study of a ramp up of production to 2500tpd from 2027, via the construction of a new 6000ft portal nearer to the processing plant, minor enhancements to the existing processing plant and enhancements to the on-site dry-stack tailings facility.
The Company currently expects to issue production guidance for 2027 taking account of the ramp-up to commercial production, exploration and study progress, and associated mine planning by the end of 2026.
Facility Drawdowns
The proceeds of the drawdowns will support the final phases of ramp-up to commercial production at the Bunker Hill Mine, including mechanical optimization in the plant, underground development, and general working capital through the first concentrate sales cycles.
Ocean Partners Concentrate Prepayment Facility
As previously announced on August 21, 2026, Bunker Hill entered into a concentrate prepayment agreement with Ocean Partners, a current shareholder of Bunker Hill, for a concentrate prepayment facility of up to US
Teck Standby Facility
The Company also announces that it has now drawn the remaining US
The Company continues to prudently manage its liquidity while focusing on safely increasing production, optimizing plant performance and generating sustainable cash flow.
As Teck and its affiliates have beneficial ownership of, or control or direction over, directly or indirectly, more than
About Bunker Hill Mining Corp.
Bunker Hill Mining Corp. is a U.S.-based exploration and development company focused on the restart of its flagship asset, the historic Bunker Hill Mine in northern Idaho’s prolific Silver Valley. One of North America’s most storied mining districts, the Bunker Hill Mine is being redeveloped as a modern producer of zinc, lead and silver concentrates through responsible mining practices and a disciplined approach to operational execution.
The Company's strategy is centered on creating long-term value through the efficient restart, optimization and expansion of this high-quality asset while maintaining strong environmental stewardship, safety performance and community engagement. Bunker Hill is committed to delivering sustainable growth and maximizing shareholder returns by successfully redeveloping a cornerstone mining operation in the United States.
Additional information is available at www.bunkerhillmining.com, on SEDAR+ and on EDGAR.
For further information, please contact:
Mark McBride
Vice President, Finance
T: 604.842.1384
E: mark.mcbride@bunkerhillmining.com
Neither the Toronto Stock Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this news release. No securities regulatory authority has reviewed or approved the contents of this news release.
Cautionary Statements Regarding Forward-Looking Statements
Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such forward-looking statements are within the meaning of that term in Section 27A of the U.S. Securities Act of 1933, as amended, and Section 21E of the U.S. Securities Exchange Act of 1934, as amended, as well as within the meaning of the phrase ‘forward-looking information’ in the Canadian Securities Administrators’ National Instrument 51-102 – Continuous Disclosure Obligations (collectively, “forward-looking statements”). Forward-looking statements are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company’s future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”, “may”, “could”, “would”, “will”, “plan” or variations of such words and phrases.
Forward-looking statements in this news release may include, without limitation: Bunker Hill's ability to receive sufficient project financing for the restart and development of the Bunker Hill Mine and the anticipated timing thereof, satisfaction of conditions to closing the Transaction, including receipt of final court and stock exchange approvals, and the timing of closing the Transaction; the anticipated use of proceeds from the Ocean Partners Facility and the Standby Facility and Bunker Hill's ramp-up at the Bunker Hill Mine. Estimates or expectations of future events or results are based upon certain assumptions, which may prove to be incorrect. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: Bunker Hill’s ability to receive sufficient project financing for the restart and ongoing development of the Bunker Hill Mine on acceptable terms or at all; the future price of metals; and the stability of the financial and capital markets. Factors that could cause actual results to differ materially from such forward-looking statements include, but are not limited to, those risks and uncertainties identified in public filings made by Bunker Hill with the U.S. Securities and Exchange Commission (the “SEC”) and with applicable Canadian securities regulatory authorities, and the following: the Company’s inability to raise additional capital for project activities, including through equity financings, concentrate offtake financings or otherwise; capital market conditions; restrictions on labor and its effects on international travel and supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to reserves; the preliminary nature of metallurgical test results; the Company’s ability to restart and develop the Bunker Hill Mine and the risks of not basing a production decision on a feasibility study of mineral reserves demonstrating economic and technical viability, resulting in increased uncertainty due to multiple technical and economic risks of failure which are associated with this production decision including, among others, areas that are analyzed in more detail in a feasibility study, such as applying economic analysis to resources and reserves, more detailed metallurgy and a number of specialized studies in areas such as mining and recovery methods, market analysis, and environmental and community impacts and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit, with no guarantee that production will begin as anticipated or at all or that anticipated production costs will be achieved; failure to commence production would have a material adverse impact on the Company’s ability to generate revenue and cash flow to fund operations; failure to achieve the anticipated production costs would have a material adverse impact on the Company’s cash flow and future profitability; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; political risks; changes in equity markets; uncertainties relating to the availability and costs of financing needed in the future; the inability of the Company to budget and manage its liquidity in light of the failure to obtain additional financing, including the ability of the Company to complete the payments pursuant to the terms of the agreement to acquire the Bunker Hill Mine complex; inflation; changes in exchange rates; fluctuations in commodity prices; delays in the development of projects; and capital, operating and reclamation costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry. Although the Company believes that the assumptions and factors used in preparing the forward-looking statements in this news release are reasonable, undue reliance should not be placed on such statements or information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all, including as to whether or when the Company will achieve its project finance initiatives, or as to the actual size or terms of those financing initiatives. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Readers are cautioned that the foregoing risks and uncertainties are not exhaustive. Additional information on these and other risk factors that could affect the Company’s operations or financial results are included in the Company’s annual report and may be accessed through the SEDAR+ website (www.sedarplus.ca) or through EDGAR on the SEC website (www.sec.gov).
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/f9938d92-24e1-4ff7-b648-6ac330dabbef
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
When is Bunker Hill's combination with Silver47 expected to close?
Bunker Hill anticipates closing on or about November 5, 2026, subject to final court and stock exchange approvals. Both companies' shareholders have approved the relevant transaction matters.
When does Bunker Hill expect commercial production?
Bunker Hill expects to achieve commercial production by end Q4 2026. Concentrate shipments are underway, and average plant throughput is above 1100t/day, excluding downtime, with lead and zinc recoveries averaging greater than 70%.
What infrastructure is Bunker Hill studying for its production expansion?
Bunker Hill is studying a new 6000ft portal nearer the processing plant, minor processing-plant enhancements and improvements to its on-site dry-stack tailings facility. The technical team is working with Ausenco and Tierra Group on the study of a ramp-up to 2500tpd from 2027.