Dakota Gold Intersects 5 g/t Gold over 24.9 Meters at Richmond Hill and Provides Silver Assay Update
Rhea-AI Summary
Dakota Gold (NYSE American: DC) reported 2025 drill results at the Richmond Hill oxide heap‑leach project and a silver assay update on February 5, 2026. Key intersections include 5.00 g/t Au over 24.9 m (RH25C‑310) and 2.46 g/t Au over 32.7 m (RH25C‑348).
The Project hosts reported resources of 3.65 Moz M&I gold, 2.61 Moz inferred gold, 38.1 Moz M&I silver, and 22.8 Moz inferred silver; results will feed a Pre‑Feasibility Study due H2 2026.
Positive
- High‑grade intercept RH25C‑310: 5.00 g/t Au over 24.9 m
- Large silver resource: 38.1 Moz M&I complements gold output
- Drill expansion: 2026 campaign started with 15,481 m in 109 holes
- Pre‑Feasibility Study scheduled for H2 2026 to support reserve reporting
Negative
- Average mined grade in prior mine plan is low: 0.566 g/t Au, implying scale dependence
- True thickness unknown for reported intervals, adding geological uncertainty
- 37 assays from 2025 remain pending, delaying full dataset integration
News Market Reaction
On the day this news was published, DC declined 6.54%, reflecting a notable negative market reaction. Argus tracked a trough of -6.5% from its starting point during tracking. Our momentum scanner triggered 3 alerts that day, indicating moderate trading interest and price volatility. This price movement removed approximately $50M from the company's valuation, bringing the market cap to $710M at that time.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Market Reality Check
Peers on Argus
DC was down 1.57% pre-news while several gold peers also traded lower (e.g., NFGC -2.68%, GAU -4.59%, CMCL -6.43%, GROY -4.61%), with ODV a notable gainer at +2.78%. No peers appeared in the momentum scanner.
Historical Context
| Date | Event | Sentiment | Move | Catalyst |
|---|---|---|---|---|
| Jan 13 | 2026 drill plans | Positive | -1.4% | Outlined 2026 Richmond Hill and Maitland drill programs supporting PFS and maiden resource. |
| Dec 23 | Expansion drilling | Positive | +0.5% | Reported Richmond Hill expansion holes extending mineralization and high-grade intercepts. |
| Dec 18 | Metallurgy update | Positive | +1.9% | Provided FS metallurgical plan, column test results, and NPV sensitivity context. |
| Dec 1 | High-grade step-out | Positive | -1.3% | Announced high-grade surface intercepts and a 150 m step-out north of resource. |
| Nov 19 | Expansion drilling | Positive | +2.5% | Released high-grade expansion and metallurgical drill results at Richmond Hill. |
Recent Richmond Hill updates have generally been positive operationally, with three prior news events seeing share price gains and two showing modest declines within 24 hours, indicating mixed short-term trading responses.
Over the past few months, Dakota Gold has repeatedly advanced the Richmond Hill oxide heap leach project through drilling, metallurgy, and study work. News on Nov 19, 2025 and Dec 1, 2025 highlighted high-grade expansion drilling and open mineralization. Subsequent updates on Dec 18, 2025 detailed metallurgical testing and Feasibility Study planning, while Dec 23, 2025 and Jan 13, 2026 emphasized additional high-grade intercepts and 2026 drill plans to support a PFS in H2 2026. Today’s release continues that Richmond Hill drill and resource narrative.
Regulatory & Risk Context
The company has an active Form S-3 shelf registration dated Jul 24, 2025, with at least one usage recorded via a 424B5 on Nov 13, 2025. An at-the-market equity program of up to $50,000,000 was established under this framework, allowing share sales at the company’s discretion, which can introduce potential dilution depending on future usage.
Market Pulse Summary
The stock moved -6.5% in the session following this news. A negative reaction despite strong drill grades and substantial resources would fit prior instances where positive Richmond Hill news was followed by short-term declines, such as the moves after Jan 13, 2026 and Dec 1, 2025. Investors may have focused on broader sector weakness or on existing equity issuance flexibility under the Form S-3 shelf and $50,000,000 at-the-market program. Past patterns show that one-day trading often diverged from the underlying operational progress described in these releases.
Key Terms
oxide heap leach technical
pre-feasibility study technical
measured and indicated technical
inferred technical
critical minerals list regulatory
initial assessment technical
mine plan technical
AI-generated analysis. Not financial advice.
Lead, South Dakota--(Newsfile Corp. - February 5, 2026) - Dakota Gold Corp. (NYSE American: DC) ("Dakota Gold" or the "Company") is pleased to report additional drill results from the Richmond Hill Oxide Heap Leach Gold Project ("Richmond Hill" or the "Project") and provide silver assay results received to date from the 2025 drill campaign. Richmond Hill hosts a large resource including 3.65 million ounces ("oz") of measured and indicated ("M&I") gold and 2.61 million oz of inferred gold, as well as 38.1 million oz of M&I silver and 22.8 million oz of inferred silver outlined in the S-K 1300 Initial Assessment published on February 6, 2025. Gold and silver assay results from the 2025 and 2026 drill campaigns at Richmond Hill will be incorporated into a Pre-Feasibility Study being published in the second half of 2026.
Highlights from this update include:
- Expansion drill hole RH25C-310 intersected 5.00 grams per tonne gold (g/t Au) and 28.64 g/t silver (Ag) over 24.9 meters (124 gram meters Au), including 60.82 g/t Au and 61.68 g/t Ag over 1.5 meters (89 gram meters Au) and RH25C-348 intersected 2.46 g/t Au and 19.16 g/t Ag over 32.7 meters (81 gram meters Au). RH25C-310 is a 194 meter (635 feet) north step-out and RH25C-348 is a 87 meter (285 feet) northwest step-out from the current measured and indicated resource boundary. The mineralization in the northeast is only limited by drilling and remains open in all directions. The 2025 northeast expansion drill program covered an area of 300 meters (980 ft) north - south and 535 meters (1,750 ft) east - west.
- Infill drill hole RH25C-328 intersected 2.49 g/t Au and 16.63 g/t Ag over 26.9 meters (67 gram meters Au), including 18.60 g/t Au and 41.20 g/t Ag over 1.8 meters (34 gram meters Au). Many higher-grade gold mineralization intersections encountered in the 2025 campaign including infill hole RH25C-328 exceed the average grade of 0.566 g/t Au published in the July 7, 2025, Initial Assessment with Cash Flow ("IACF") measured and indicated mine plan.
- Richmond Hill's heap leach gold resource is complimented by a large silver resource. Many high-grade silver assay results are shown in Table 2 from the 2025 drill campaign including:
- RH25C-164 intersected 1.94 g/t Au and 34.88 g/t Ag over 60.0 meters
- RH25C-169 intersected 2.78 g/t Au and 42.07 g/t Ag over 39.3 meters
- RH25C-209 intersected 1.40 g/t Au and 34.82 g/t Ag over 73.5 meters
- RH25C-166 intersected 2.25 g/t Au and 27.91 g/t Ag over 44.3 meters
- RH25C-236 intersected 8.17 g/t Au and 11.02 g/t Ag over 11.3 meters
- RH25C-171 intersected 1.50 g/t Au and 24.08 g/t Ag over 62.1 meters
- RH25C-215 intersected 1.72 g/t Au and 34.75 g/t Ag over 42.7 meters
Jack Henris, President and COO of Dakota Gold said, "I am pleased with the results received to date from the 2025 drill campaign at Richmond Hill which included 242 drill holes. Assays from 37 drill holes are pending release including many from northeast expansion drilling, which will be reported as they are received in the next few weeks. The Company has now begun its 2026 drill campaign at Richmond Hill including 15,481 meters of drilling in 109 holes to follow up on the success from 2025. Two drills are in operation and we expect to complete the 2026 campaign in the third quarter of this year." Shawn Campbell, Chief Financial Officer added, "We are pleased to be advancing a project that in addition to gold, hosts a considerable amount of silver. Silver was recently designated as a Critical Mineral in the United States, and the Richmond Hill project has the potential to support domestic supply and contribute to the nation's long-term mineral security. We look forward to incorporating the gold and silver results into the Pre-Feasibility Study. This work will enable the Company to report reserves in 2026, further de-risking the Project as it advances along its path to expected production in 2029."

Figure 1. Plan Map showing location of Dakota Gold Corp. Richmond Hill 2025 Drill Campaign drill results reported today in Table 1.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/8218/282757_006e75aca475abc0_002full.jpg
Table 1. Richmond Hill Drill Results (Metric / Imperial)1,2,3,4,5
| Hole # | From (m) | To (m) | Interval (m) | Grade Au (g/t) | g x m Au | Grade Ag (g/t) | g x m Ag | From (ft) | To (ft) | Interval (ft) | Grade Au (oz/ton) |
| RH25C-233 | 2.0 | 5.5 | 3.6 | 0.51 | 2 | 1.76 | 6 | 6.5 | 18.2 | 11.7 | 0.015 |
| 11.5 | 24.7 | 13.2 | 1.27 | 17 | 4.87 | 64 | 37.7 | 80.9 | 43.2 | 0.037 | |
| 47.0 | 53.8 | 6.8 | 0.64 | 4 | 15.02 | 103 | 154.2 | 176.6 | 22.4 | 0.019 | |
| 79.9 | 84.5 | 4.7 | 2.63 | 12 | 11.91 | 56 | 262.0 | 277.3 | 15.3 | 0.077 | |
| 110.1 | 116.2 | 6.2 | 0.87 | 5 | 11.01 | 68 | 361.1 | 381.3 | 20.2 | 0.025 | |
| RH25C-308 | 16.2 | 22.2 | 5.9 | 1.04 | 6 | 47.83 | 284 | 53.3 | 72.8 | 19.5 | 0.03 |
| 34.8 | 38.7 | 3.9 | 0.63 | 2 | 5.82 | 23 | 114.2 | 127.1 | 12.9 | 0.018 | |
| RH25C-310 | 78.3 | 103.2 | 24.9 | 5.00 | 124 | 28.64 | 712 | 257.0 | 338.6 | 81.6 | 0.146 |
| inc. | 95.1 | 96.6 | 1.5 | 60.82 | 89 | 61.68 | 90 | 312.0 | 316.8 | 4.8 | 1.774 |
| RH25C-326 | 37.6 | 40.8 | 3.1 | 1.50 | 5 | 1.34 | 4 | 123.5 | 133.8 | 10.3 | 0.044 |
| 94.4 | 105.4 | 11.0 | 0.83 | 9 | 5.33 | 59 | 309.6 | 345.7 | 36.1 | 0.024 | |
| 108.8 | 113.1 | 4.3 | 0.74 | 3 | 44.61 | 192 | 357.0 | 371.1 | 14.1 | 0.021 | |
| 126.5 | 131.3 | 4.8 | 3.07 | 15 | 107.90 | 523 | 414.9 | 430.8 | 15.9 | 0.09 | |
| RH25C-327 | 77.9 | 93.0 | 15.1 | 1.36 | 20 | 22.45 | 338 | 255.7 | 305.1 | 49.4 | 0.039 |
| RH25C-328 | 91.9 | 118.8 | 26.9 | 2.49 | 67 | 16.63 | 448 | 301.6 | 389.9 | 88.3 | 0.073 |
| inc. | 96.6 | 98.4 | 1.8 | 18.60 | 34 | 41.20 | 75 | 316.8 | 322.8 | 6.0 | 0.543 |
| RH25C-329 | 48.3 | 84.0 | 35.7 | 1.00 | 36 | 10.23 | 365 | 158.4 | 275.6 | 117.2 | 0.029 |
| RH25C-330 | 75.3 | 85.7 | 10.4 | 1.03 | 11 | 17.86 | 186 | 247.0 | 281.2 | 34.2 | 0.03 |
| RH25C-332 | 62.1 | 68.0 | 5.9 | 0.76 | 4 | 68.78 | 405 | 203.7 | 223.0 | 19.3 | 0.022 |
| RH25C-333 | 20.1 | 28.3 | 8.1 | 2.92 | 24 | 6.56 | 53 | 66.1 | 92.8 | 26.7 | 0.085 |
| 47.1 | 52.7 | 5.6 | 0.83 | 5 | 9.30 | 52 | 154.5 | 173.0 | 18.5 | 0.024 | |
| 69.5 | 73.6 | 4.1 | 1.26 | 5 | 45.22 | 185 | 228.1 | 241.5 | 13.4 | 0.037 | |
| 78.2 | 83.2 | 5.0 | 1.69 | 8 | 25.67 | 128 | 256.6 | 272.9 | 16.3 | 0.049 | |
| RH25C-334 | 56.4 | 61.6 | 5.2 | 0.63 | 3 | 2.30 | 12 | 185.0 | 202.2 | 17.2 | 0.018 |
| 70.8 | 75.5 | 4.7 | 0.61 | 3 | 63.16 | 295 | 232.4 | 247.7 | 15.3 | 0.018 | |
| RH25C-335 | 36.0 | 46.0 | 10.1 | 0.64 | 6 | 9.05 | 91 | 118.0 | 151.0 | 33.0 | 0.019 |
| 53.3 | 58.8 | 5.5 | 1.73 | 9 | 200.96 | 1105 | 175.0 | 193.0 | 18.0 | 0.05 | |
| RH25C-336 | 52.7 | 71.3 | 18.6 | 1.15 | 21 | 23.18 | 431 | 173.0 | 234.0 | 61.0 | 0.034 |
| RH25C-337 | 109.7 | 112.8 | 3.0 | 0.63 | 2 | 2.44 | 7 | 360.0 | 370.0 | 10.0 | 0.018 |
| RH25C-339 | No Significant Results | ||||||||||
| RH25C-346 | 57.2 | 60.8 | 3.6 | 1.08 | 4 | 6.31 | 23 | 187.7 | 199.5 | 11.8 | 0.032 |
| 71.3 | 79.1 | 7.8 | 0.61 | 5 | 22.40 | 175 | 234.0 | 259.6 | 25.6 | 0.018 | |
| RH25C-348 | 57.8 | 90.5 | 32.7 | 2.46 | 81 | 19.16 | 627 | 189.6 | 297.0 | 107.4 | 0.072 |
| RH25C-351 | 57.1 | 65.2 | 8.1 | 0.68 | 6 | 1.87 | 15 | 187.3 | 214.0 | 26.7 | 0.02 |
| 71.3 | 77.9 | 6.6 | 0.73 | 5 | 26.78 | 176 | 234.0 | 255.5 | 21.5 | 0.021 | |
| RH25C-352 | 82.7 | 94.2 | 11.5 | 0.86 | 10 | 52.20 | 601 | 271.3 | 309.1 | 37.8 | 0.025 |
| RH25C-357 | 55.2 | 61.0 | 5.8 | 0.91 | 5 | 3.85 | 22 | 181.0 | 200.0 | 19.0 | 0.027 |
| BG-GW-09A | 10.7 | 25.9 | 15.2 | 0.83 | 13 | 28.82 | 439 | 35.0 | 85.0 | 50.0 | 0.024 |
The table may contain rounding errors.
- Abbreviations in the table include ounces per ton ("oz/ton"); grams per tonne ("g/t"); feet ("ft"); meter ("m"); gram meters ("g x m").
- True thickness unknown.
- Intervals calculated based on 0.5 g/t Au cut-off and maximum dilution of 3.05 meters.
- The July 7, 2025, Initial Assessment with Cash Flow has an open pit designed with 12.2m (40 ft) benches. The average grade for the Measured and Indicated mine plan is 0.566 g/t Au (0.017 oz/ton). A gram meter of 7 and above has been highlighted in Table 1 based on the bench height and average grade.
- The following monitoring water well hole drilled outside of the resource area for permitting has confirmed no significant gold mineralization: BG-GW-07; BG-GW-03
Silver Assay Results Update
Silver's addition to the Department of the Interior, U.S. Geological Survey Critical Minerals list in November 20251 underscores growing federal recognition of its importance to the U.S. economy and national security. With industrial demand rising rapidly—driven by solar, AI data centers, electric vehicles, and next-generation electronics—domestic supply remains limited. This designation highlights silver as a strategically important metal and reinforces the value of projects like Richmond Hill, which has the potential to contribute to U.S.-based silver production.
On July 7th, 2025, the Company published an IACF for Richmond Hill using a base case silver price of
Table 2. Richmond Hill table of zones for the initial 5 phases of mining with gold and silver assays for select highlight holes from the 2025 drill campaign (Metric / Imperial)1,2,3
| Hole # | From (m) | To (m) | Interval (m) | Grade Au (g/t) | g x m Au | Grade Ag (g/t) | g x m Ag | From (ft) | To (ft) | Interval (ft) | Grade Au (oz/ton) |
| MW3 Main | |||||||||||
| RH25C-164 | 7.1 | 67.1 | 60.0 | 1.94 | 116 | 34.88 | 2093 | 23.3 | 220.0 | 196.7 | 0.057 |
| RH25C-169 | 20.1 | 59.4 | 39.3 | 2.78 | 109 | 42.07 | 1652 | 66.0 | 194.8 | 128.8 | 0.081 |
| RH25C-166 | 10.5 | 54.9 | 44.3 | 2.25 | 100 | 27.91 | 1236 | 34.6 | 180.0 | 145.4 | 0.066 |
| RH25C-171 | 16.5 | 78.6 | 62.1 | 1.50 | 93 | 24.08 | 1496 | 54.2 | 258.0 | 203.8 | 0.044 |
| RH25C-200 | 22.8 | 56.2 | 33.4 | 2.25 | 75 | 26.19 | 876 | 74.7 | 184.4 | 109.7 | 0.065 |
| RH25C-167 | 17.5 | 51.8 | 34.3 | 2.10 | 72 | 28.04 | 962 | 57.4 | 170.0 | 112.6 | 0.061 |
| RH25C-170 | 19.0 | 59.0 | 40.1 | 1.23 | 49 | 24.26 | 973 | 62.3 | 193.7 | 131.4 | 0.036 |
| MW3 East | |||||||||||
| RH25C-162 | 39.6 | 83.1 | 43.4 | 1.85 | 80 | 25.39 | 1102 | 129.8 | 272.8 | 143.0 | 0.054 |
| RH25C-234 | 34.3 | 62.6 | 28.3 | 1.88 | 53 | 27.92 | 790 | 112.5 | 205.3 | 92.8 | 0.055 |
| RH25C-156 | 40.0 | 70.2 | 30.2 | 1.24 | 37 | 16.74 | 506 | 131.2 | 230.3 | 99.1 | 0.036 |
| RH25C-160 | 32.8 | 61.1 | 28.3 | 1.30 | 37 | 24.71 | 699 | 107.6 | 200.3 | 92.7 | 0.038 |
| Chism Gulch | |||||||||||
| RH25C-310 | 78.3 | 103.2 | 24.9 | 5.00 | 124 | 28.64 | 712 | 257.0 | 338.6 | 81.6 | 0.146 |
| inc. | 95.1 | 96.6 | 1.5 | 60.82 | 89 | 61.68 | 90 | 312.0 | 316.8 | 4.8 | 1.774 |
| RH25C-348 | 57.8 | 90.5 | 32.7 | 2.46 | 81 | 19.16 | 627 | 189.6 | 297.0 | 107.4 | 0.072 |
| RH25C-303 | 101.1 | 116.3 | 15.2 | 4.52 | 69 | 15.39 | 235 | 331.6 | 381.6 | 50.0 | 0.132 |
| inc. | 111.4 | 113.2 | 1.8 | 31.90 | 57 | 37.90 | 68 | 365.5 | 371.4 | 5.9 | 0.930 |
| RH25C-323 | 110.3 | 141.5 | 31.1 | 2.19 | 68 | 4.27 | 133 | 362.0 | 464.1 | 102.1 | 0.064 |
| inc. | 134.8 | 136.3 | 1.5 | 17.35 | 26 | 13.95 | 21 | 442.3 | 447.2 | 4.9 | 0.506 |
| RH25C-328 | 91.9 | 118.8 | 26.9 | 2.49 | 67 | 16.63 | 448 | 301.6 | 389.9 | 88.3 | 0.073 |
| inc. | 96.6 | 98.4 | 1.8 | 18.60 | 34 | 41.20 | 86 | 316.8 | 322.8 | 6.0 | 0.543 |
| RH25C-270 | 30.5 | 59.7 | 29.2 | 2.26 | 66 | 18.17 | 531 | 100.1 | 196.0 | 95.9 | 0.066 |
| RH25C-295 | 5.5 | 35.4 | 30.0 | 2.15 | 65 | 20.99 | 630 | 17.9 | 116.3 | 98.4 | 0.063 |
| RH25C-288 | 87.7 | 102.2 | 14.5 | 4.15 | 60 | 16.61 | 242 | 287.7 | 335.4 | 47.7 | 0.121 |
| inc. | 92.2 | 93.5 | 1.2 | 29.20 | 36 | 48.90 | 60 | 302.6 | 306.6 | 4.0 | 0.852 |
| RH25C-319 | 33.5 | 81.1 | 47.6 | 1.18 | 56 | 4.47 | 213 | 109.9 | 266.0 | 156.1 | 0.034 |
| RH25C-261 | 37.0 | 54.3 | 17.3 | 2.87 | 50 | 18.41 | 318 | 121.4 | 178.0 | 56.6 | 0.084 |
| RH25C-256 | 36.4 | 48.9 | 12.5 | 3.76 | 47 | 26.66 | 332 | 119.5 | 160.4 | 40.9 | 0.110 |
| inc. | 36.4 | 38.0 | 1.6 | 23.20 | 37 | 29.90 | 47 | 119.5 | 124.7 | 5.2 | 0.677 |
| RH25C-313 | 20.0 | 45.7 | 25.7 | 1.74 | 45 | 22.89 | 589 | 65.6 | 150.0 | 84.4 | 0.051 |
| RH25C-307 | 102.7 | 132.9 | 30.2 | 1.43 | 43 | 17.26 | 521 | 337.0 | 436.0 | 99.0 | 0.042 |
| Cole Creek | |||||||||||
| RH25C-209 | 14.3 | 87.5 | 73.5 | 1.40 | 103 | 34.82 | 2558 | 47.0 | 287.0 | 241.0 | 0.041 |
| RH25C-211 | 16.2 | 68.5 | 52.3 | 1.55 | 81 | 16.83 | 881 | 53.0 | 224.7 | 171.7 | 0.045 |
| RH25C-204 | 20.6 | 83.1 | 62.5 | 1.22 | 76 | 15.35 | 959 | 67.5 | 272.5 | 205.0 | 0.036 |
| RH25C-241 | 177.3 | 197.8 | 20.5 | 3.72 | 76 | 10.88 | 223 | 581.8 | 649.1 | 67.3 | 0.109 |
| inc. | 191.8 | 193.2 | 1.5 | 28.20 | 41 | 43.00 | 63 | 629.2 | 634.0 | 4.8 | 0.823 |
| RH25C-215 | 28.3 | 71.0 | 42.7 | 1.72 | 74 | 34.75 | 1483 | 93.0 | 233.0 | 140.0 | 0.050 |
| RH25C-207 | 15.1 | 48.6 | 33.5 | 1.31 | 44 | 13.68 | 459 | 49.4 | 159.4 | 110.0 | 0.038 |
| RH25C-190 | 140.7 | 155.2 | 14.5 | 2.96 | 43 | 16.34 | 237 | 461.5 | 509.1 | 47.6 | 0.086 |
| RH25C-195 | 108.2 | 140.3 | 32.1 | 1.21 | 39 | 21.02 | 675 | 355.0 | 460.4 | 105.4 | 0.035 |
| Twin Tunnels | |||||||||||
| RH25C-236 | 0.0 | 11.3 | 11.3 | 8.17 | 93 | 11.02 | 125 | 0.0 | 37.2 | 37.2 | 0.238 |
| RH25C-230 | 20.3 | 82.3 | 62.0 | 0.67 | 42 | 9.37 | 581 | 66.6 | 270.0 | 203.4 | 0.020 |
| RH25C-222 | 27.9 | 59.1 | 31.2 | 0.96 | 30 | 8.54 | 267 | 91.6 | 194.0 | 102.4 | 0.028 |
The table may contain rounding errors.
- Abbreviations in the table include ounces per ton ("oz/ton"); grams per tonne ("g/t"); feet ("ft"); meter ("m"); gram meters ("g x m").
- True thickness unknown.
- Intervals calculated based on 0.5 g/t Au cut-off and maximum dilution of 3.05 meters.
About Dakota Gold Corp.
Dakota Gold is expanding the legacy of the 145-year-old Homestake Gold Mining District by advancing the Richmond Hill Oxide Heap Leach Gold Project to commercial production as soon as 2029, and outlining a Tertiary maiden resource as well as a high-grade underground gold resource at the Maitland Gold Project, both located on private land in South Dakota.
Subscribe to Dakota Gold's e-mail list at www.dakotagoldcorp.com to receive the latest news and other Company updates.
Shareholder and Investor Inquiries
For more information, please contact:
Jack Henris
President and COO
Tel: +1 605-717-2540
Shawn Campbell
Chief Financial Officer
Tel: +1 778-655-9638
Carling Gaze
VP of Investor Relations and Corporate Communications
Tel: +1 605-679-7429
Email: info@dakotagoldcorp.com
Qualified Person and S-K 1300 Disclosure
James M. Berry, a Registered Member of SME and Vice President of Exploration of Dakota Gold Corp., is the Company's designated qualified person (as defined in Subpart 1300 of Regulation S-K) for this news release and has reviewed and approved its scientific and technical content.
Quality Assurance/Quality Control consists of regular insertion of certified reference materials, duplicate samples, and blanks into the sample stream. Samples are submitted to the ALS Geochemistry sample preparation facility in Winnipeg, Manitoba. Gold and multi-element analyses are performed at the ALS Geochemistry laboratory in Vancouver, British Columbia. ALS Minerals is an ISO/IEC 17025:2017 accredited lab. Check samples are submitted to Bureau Veritas, Vancouver B.C. as an umpire laboratory. Assay results are reviewed, and discrepancies are investigated prior to incorporation into the Company database.
Forward-Looking Statements
This communication contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. When used in this communication, the words "plan," "target," "anticipate," "believe," "estimate," "intend," "potential," "will" and "expect" and similar expressions are intended to identify such forward-looking statements. Any express or implied statements contained in this communication that are not statements of historical fact may be deemed to be forward-looking statements, including, without limitation: our expectations regarding additional drilling, metallurgy and modeling; our expectations for the improvement and growth of the mineral resources and potential for conversion of mineral resources into reserves; completion of a pre-feasibility study, a feasibility study, and/or permitting; our expectations regarding free cash flow and future financing, and our overall expectation for the possibility of near-term production at the Richmond Hill project. These forward-looking statements are based on assumptions and expectations that may not be realized and are inherently subject to numerous risks and uncertainties, which could cause actual results to differ materially from these statements. These risks and uncertainties include, among others: the execution and timing of our planned exploration activities; our use and evaluation of historic data; our ability to achieve our strategic goals; the state of the economy and financial markets generally and the effect on our industry; and the market for our common stock. The foregoing list is not exhaustive. For additional information regarding factors that may cause actual results to differ materially from those indicated in our forward-looking statements, we refer you to the risk factors included in Item 1A of the Company's Annual Report on Form 10-K for the fiscal year ended December 31, 2024, as updated by annual, quarterly and current reports that we file with the SEC, which are available at www.sec.gov. We caution investors not to place undue reliance on the forward-looking statements contained in this communication. These statements speak only as of the date of this communication, and we undertake no obligation to update or revise these statements, whether as a result of new information, future events or otherwise, except as may be required by law. We do not give any assurance that we will achieve our expectations.
All references to "$" in this communication are to U.S. dollars unless otherwise stated.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/282757