STOCK TITAN

Eldorado Gold Announces Four Tailings Filter Presses Operational at Skouries; Updated Technical Report to be Filed Q1 2027

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Eldorado Gold (EGO) has four tailings filter presses operational at its Skouries mine in northern Greece, meeting the filtration requirement for commercial production on sulphide ore. Five presses are needed to reach designed processing capacity. Eldorado expects commercial production late this quarter.

The company expects the remaining two presses to be operational in early December and to file an updated Skouries technical report in Q1 2027.

Loading...
Loading translation...
4 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 1 point

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate pointFour operational filter presses meet Skouries’ filtration requirement for commercial production on sulphide ore
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Commercial production at Skouries is expected late this quarter
  • Minor point. Forward-looking: it has not happened yet and may not happen.Two remaining filter presses are expected to be operational in early December
  • Minor pointInstalled spare press allows maintenance without reducing processing throughput

Negative

  • Moderate pointDesigned processing capacity requires five operational filter presses; four are currently operational

News Explained

Four presses are operational at Skouries.

Key Figures

Operational filter presses: 4 presses Presses required for commercial production: 4 presses Presses required for nameplate throughput: 5 presses +3 more
Operational filter presses
4 presses
Now operational at Skouries
Presses required for commercial production
4 presses
On sulphide ore
Presses required for nameplate throughput
5 presses
Skouries tailings filtration
Remaining presses expected operational
2 presses
Expected in early December
Updated Technical Report filing
Q1 2027
Expected filing for Skouries
Commercial production expectation
Late this quarter
Skouries ramp-up

Historical Context

1 past event · Latest: Oct 26
1 event
  1. Oct 26

    Filter-press activation

    24h Move
    +7.8%

    First two Skouries tailings filter presses became operational during commissioning.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

filter presses, sulphide ore, nameplate throughput, tailings filtration facility
4 terms
filter presses technical
"Four tailings filter presses are now operational at its Skouries mine"
Filter presses are mechanical devices used to separate solids from liquids by forcing slurry through a series of cloth- or mesh-lined plates that trap solids as a compacted cake while allowing clear liquid (filtrate) to pass out. Slurry is pumped into the press and pressure—created by a pump, hydraulic system, or gravity—compresses the solids between plates; the trapped solids must be removed and disposed or further processed, and operation involves periodic stopping and cleaning rather than continuous separation. They are commonly used where high dewatering efficiency and a relatively dry solid cake are required, but they are batch-oriented and can be slower or more labor-intensive than continuous separators like centrifuges or belt presses.
sulphide ore technical
"required to support commercial production on sulphide ore"
A sulphide ore is a rock that contains metal-bearing sulphide minerals (compounds of sulfur with metals) in concentrations high enough to be mined and processed for the contained metal. These ores are typically treated by concentrating the sulphide minerals (often using flotation) and then smelting or roasting to separate the metal; their chemistry and processing methods differ from oxide ores because the metal is chemically bound to sulfur rather than oxygen, which affects metallurgy, recovery techniques and certain environmental controls.
nameplate throughput technical
"five required to achieve nameplate throughput"
The maximum continuous production rate a piece of equipment, plant or production line is designed to achieve under ideal operating conditions, usually expressed as units per time (e.g., barrels per day, tonnes per year). Nameplate throughput is a design specification rather than a guaranteed performance figure; actual throughput typically differs because of scheduled downtime, maintenance, feedstock quality, regulatory limits or operational constraints.
tailings filtration facility technical
"The Skouries tailings filtration facility comprises six Metso filter presses"
A tailings filtration facility is the plant and equipment at a mine that separates water from ore-processing waste (tailings) to produce a drier, stackable solid and recover process water. It typically uses thickeners and mechanical filters (for example pressure, vacuum or belt filters) to turn slurry into a filtered “cake,” plus conveyors, storage areas and water-recycling systems; the result is reduced liquid volume compared with a wet tailings pond and easier handling and storage of the solids. The facility’s performance affects how tailings are stored and how much water is reclaimed, but it does not itself change the chemical composition of the waste.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Four operational filter presses achieve a key filtration requirement toward commercial production

VANCOUVER, British Columbia, Nov. 23, 2026 (GLOBE NEWSWIRE) -- Eldorado Gold Corporation (TSX: ELD, NYSE: EGO) (“Eldorado” or the “Company”) is pleased to announce that four tailings filter presses are now operational at its Skouries mine in northern Greece, marking another important milestone in the commissioning and ramp-up of the operation.

“With four filter presses now operational, we have achieved another important milestone in the ramp-up of Skouries,” said Christian Milau, President and Chief Executive Officer. “With this additional filtration capacity now online, we are well positioned to advance throughput and build momentum across the operation. We remain focused on progressing the ramp-up toward commercial production, which we expect late this quarter.”

Four operating filter presses are required to support commercial production on sulphide ore, with five required to achieve nameplate throughput. The Skouries tailings filtration facility comprises six Metso filter presses, including five operating units and one installed spare. The sixth unit provides operational flexibility and enables maintenance activities with no loss of throughput. The remaining two filter presses are expected to be operational in early December.

Technical Report

Eldorado expects to file an updated Technical Report for Skouries in the first quarter of 2027, incorporating an updated resource model and metal price assumptions, together with updated production, operating cost and capital estimates reflecting the transition of Skouries from development into operations.

About Eldorado Gold

Eldorado is a gold, copper and base metals producer with mining, development and exploration operations in Canada, Türkiye, and Greece. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio of high-quality assets, and long-term partnerships with local communities. Eldorado’s common shares trade on the Toronto Stock Exchange (TSX: ELD) and the New York Stock Exchange (NYSE: EGO).

Contact

Investor Relations
Lynette Gould, VP, Investor Relations, Communications & External Affairs
647 271 2827 or 1 888 353 8166
lynette.gould@eldoradogold.com

Media
Chad Pederson, Director, Communications and Public Affairs
236 885 6251 or 1 888 353 8166
chad.pederson@eldoradogold.com 

Cautionary Note about Forward-looking Statements and Information
Certain of the statements made and information provided in this news release are forward-looking statements or information within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Often, these forward-looking statements and forward-looking information can be identified by the use of words such as “anticipate”, “believe”, “budget”, “continue”, “commitment”, “confident”, “estimate”, “expect”, “focus”, “forecast”, “foresee”, “future”, “goal”, “guidance”, “intend”, “opportunity”, “outlook”, “plan”, “potential”, “project”, “prospective”, “schedule”, “strive”, “target”, “underway”, “working” or the negatives thereof or variations of such words and phrases or similar words or statements that certain actions, events or results “can”, “could”, “likely”, “may”, “might”, “will” or “would” be taken, occur or be achieved.

Forward-looking statements or information contained in this news release include, but are not limited to, statements or information with respect to: the commissioning and ramp-up of Skouries, including the expected performance of the tailings filtration facility; the continued advancement of plant throughput and progress toward commercial production, including the expected timing thereof; the filtration capacity required to support commercial production and nameplate throughput; the expected operational timing of the remaining filter presses; the expected benefits of the installed spare filter press; the expected filing and contents of an updated Technical Report for Skouries; and generally our strategy, plans and goals, including our proposed exploration, development, construction, permitting, financing and operating potential, plans and priorities and related timelines and schedules.

Forward-looking statements and forward-looking information by their nature are based on a number of assumptions that management considers reasonable. However, if such assumptions prove to be inaccurate, then actual results, activities, performance, or achievements may be materially different from those described in the forward-looking statements or information. These include assumptions concerning, among other things: timing, costs and results of our construction and development activities, improvements and exploration, including at the Skouries mine, the McIlvenna Bay mine and our other operating mines and development projects; the current or future price of gold, copper and other commodities; the availability of financing for our exploration, development and operating activities and our ability to access existing project funding and remain in compliance with all covenants and contractual commitments related thereto; the geopolitical, economic, permitting and legal climate that we operate in, including the effects of any disruptions to shipping operations in the Strait of Hormuz and Red Sea and any related shipping delays, shipping price increases, or impacts on the global energy market; availability of labour resources, including for construction, development and improvement activities; our ability to integrate the assets of Foran Mining Corporation, advance its exploration and development assets and to realize anticipated synergies and benefits therefrom; general business and economic conditions, including interest rates, inflation, commodity and power prices, credit and financial market conditions and the impact of foreign exchange rates and tax rates and related frameworks; anticipated values, costs, expenses and working capital requirements; production and metallurgical recoveries; Mineral Reserves and Mineral Resources; our ability to develop, finalize and execute on our updated five-year strategic plan through 2030; acts of governments and the outcome of any legal or regulatory proceedings or other disputes that we may be involved in; our ability to continue to make purchases under our normal course issuer bid and to pay dividends; the impact of acquisitions, dispositions, suspensions or delays on our business; our ability to manage and mitigate the risks associated with our use of technology and artificial intelligence; the expected vesting and redemption outcomes under our compensation securities; our ability to address the negative impacts of climate change and adverse weather; consistency of agglomeration and our ability to optimize it in the future; the cost of, and extent to which we use, essential consumables; the impact and effectiveness of productivity initiatives; the time and cost necessary for anticipated overhauls of equipment; expected by-product grades; the effectiveness of our hedging programs; and our ongoing relations with regulators, communities, and our partners.

More specifically, with respect to the Skouries mine and updates, we have made additional assumptions regarding: our ability to continue executing our plans relating to the Skouries mine on the estimated existing project timeline and consistent with the current planned project scope; the performance and availability of the filter presses and associated tailings handling infrastructure at the required capacity, including the timely commissioning of the remaining filter presses; successful completion of commissioning and ramp-up activities within the expected timelines, including the achievement of commercial production in late Q4 2026; achievement of the anticipated filtration and water recovery performance; our ability to progressively increase plant throughput and achieve and maintain stable production; our ability to continue to deliver copper-gold concentrate under our offtake arrangements, including to EU-based smelters, in the quantities and on the timelines and terms expected; the continued availability of trucking and other logistics for the delivery of Skouries concentrate; the continued designation of Skouries as a Strategic Project under the EU Critical Raw Materials Act; labour productivity, rates, and expected hours; inflation rates; the timeliness of shipping for important or critical items; our ability to continue accessing our project funding and remain in compliance with all covenants and contractual commitments related thereto; our ability to obtain and maintain all required approvals and permits, both overall and in a timely manner; the absence of further previously unidentified archaeological discoveries which would delay construction of various portions of the project; the future price of gold, copper, and other commodities; our ability to complete the updated resource model and the updated production, operating cost and capital estimates, and to file the updated Technical Report, within the expected timeline; and the broader community engagement and social climate in respect of the Skouries mine.

In addition, except where otherwise stated, we have assumed a continuation of existing business operations on substantially the same basis as exists at the time of this news release. Even though we believe that the assumptions and expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statements or information will prove to be accurate. Many assumptions may be difficult to predict and are beyond our control.

Forward-looking statements or information contained in this news release are subject to a variety of known and unknown risks, uncertainties and other factors which could cause actual events or results to differ from those expressed or implied by the forward-looking statements or information, including, but not limited to: commodity price risk; construction and development risks at the Skouries mine, the McIlvenna Bay mine and our other construction and development projects; changing political, economic and social conditions, including changes in governments, political systems or political dynamics, ongoing market uncertainty and global or regional geopolitical events, conflicts or disruptions; risks relating to our operations in foreign jurisdictions; risks relating to production and processing; risks relating to our improvement projects; risks relating to our ability to integrate the assets of Foran Mining Corporation, advance its exploration and development assets and realize anticipated synergies and benefits therefrom on the timelines expected or at all; delays and risks relating to surface construction, commissioning activities, ramp-up, and commercial production at McIlvenna Bay; our ability to obtain reliable supplies of power and water at a reasonable cost; risks relating to prices of commodities and consumables; our reliance on significant amounts of critical equipment; our reliance on infrastructure, commodities and consumables, including risks from volatility and inflationary pressures as a result of the ongoing international conflict in Iran; inflation risk; risks relating to fluctuations in the currency markets, including the Euro, Turkish lira, Canadian dollar and United States dollar; risks relating to community relations, social license and our ability to obtain or maintain required permits; risks relating to environmental matters and environmental monitoring and reporting; geotechnical and hydrogeological structures, conditions or failures, including our ability to completely understand such structures, to deal with pre-existing mineralogical, topographical or predecessor activities on or near our sites and to mitigate such conditions or failures at a reasonable cost or at all; regulatory requirements as they relate to mine plan approvals; compliance with the Extractive Sector Transparency Measures Act (Canada); waste disposal; mineral tenure; risks relating to permits, licenses and other authorizations, including our ability to obtain, maintain, and comply with the terms and conditions of such permits, licenses and other authorizations; risks relating to non-governmental organizations; reputational issues; risks relating to climate change, including risks relating to forest fires and water management; water collection, treatment and disposal operations at our mines, including the ability to manage unexpectedly large quantities of water; risk of spills or failure from our tailings operations (including circumstances beyond our control such as extreme weather, seismic events, prolonged droughts or heavy rainfall); environmental risks from our heap leaching operations, including hazardous materials management of our use of cyanide; risks relating to a change of control or actions of activist shareholders; estimation of Mineral Reserves and Mineral Resources; risks relating to replacement of Mineral Reserves; regulatory reviews and different standards used to prepare and report Mineral Reserves and Mineral Resources; risks relating to any pandemic, epidemic, endemic or similar public health threats; risks relating to our use of regulated substances; risks relating to acquisitions, including integration risks, and dispositions; risks relating to co-ownership of our properties; risks relating to volatility, volume fluctuations, and dilution risk in respect of our shares; competition risks; reliance on a limited number of smelters, refiners and off-takers, including risks related to accessibility, availability, proximity, and capacity of smelters, refiners and off-takers; risks relating to the performance of our offtake arrangements and of smelters, refiners, traders and other counterparties thereto, including changes in treatment and refining charges and other commercial terms; risks relating to concentrate quality, including penalty elements and the ability to meet smelter specifications; risks relating to the transportation of concentrate, including road conditions, trucking availability, cross-border logistics and related delays or costs; risks relating to changes in European Union policy, including the EU Critical Raw Materials Act, and to the maintenance of the designation of Skouries as a Strategic Project and any benefits associated therewith; information and operational technology systems; liquidity and financing risks; indebtedness, including current and future operating restrictions, implications of a change of control, ability to meet debt service obligations, the implications of defaulting on obligations and changes in credit ratings; risks relating to total cash costs per ounce and all in sustaining costs, including in relation to the market price of gold and the Company’s profitability; interest rate risk; credit risk; tax matters; financial reporting, including relating to the carrying value of our assets and changes in reporting standards; the global economic environment; labour risks (including availability of labour resources, including for construction, development and improvement activities, and labour productivity); risks relating to employee/union relations, employee and contractor misconduct, key personnel, skilled workforce, expatriates and contractors, reclamation and long-term obligations; turnover and attrition rates of labour, and related impacts thereof; the unavailability of insurance; risks relating to title and surface rights; risks relating to environmental, sustainability, health and safety, and governance matters; technology and cybersecurity risks; corruption, bribery, and sanctions; litigation and contracts, including counterparty risk; conflicts of interest; compliance with applicable laws, regulations, stock exchange rules and permitting requirements and the consequences of non-compliance, including suspension, substantial alteration or termination of our development activities or operations, monetary penalties or criminal proceedings in various jurisdictions; risks relating to tariffs and other trade barriers; and those risk factors discussed in the section titled “Risk Factors in Our Business” in the Company’s most recent Annual Information Form and Form 40-F. The reader is directed to carefully review our most recent Annual Information Form, Form 40-F and other regulatory filings filed on SEDAR+ and EDGAR under our Company name for a fuller understanding of the risks and uncertainties that affect the Company’s business and operations.

With respect to the Skouries mine, these risks, uncertainties and other factors may cause further delays in the completion of the construction and commissioning at the Skouries mine which in turn may cause delays in the commencement of production, the achievement of commercial production and further increases to the costs of the Skouries mine. The specific risks, uncertainties and other factors include, among others: our ability to efficiently manage the transitions from construction to commissioning to operations (including EPCM performance and owner team turnover); our ability to progressively increase plant throughput and achieve and maintain stable production; our ability to increase productivity by, among other things, adding or modifying labour shifts; rising labour costs or costs of key inputs such as materials, power and fuel; risks related to any unanticipated critical equipment defects or failures during the commissioning and ramp-up of operations; risks related to the performance of the tailings filtration facility and the ramp-up of operations, including the timing of commercial production and nameplate throughput; risks related to third-party contractors, including reduced control over aspects of the Company’s operations, and/or the ability of contractors to perform at required levels and according to baseline schedules, costs of any engineering rework and any commercial disputes that may arise from a contractor’s failure to meet these requirements; the ability of key suppliers to meet key contractual commitments in terms of schedules, amount of product delivered, cost, or quality and the impact of any vendor data errors; impacts to overhead costs related to the schedule; our ability to construct key infrastructure within the required timelines, including the process plant, filter plant, substation, waste management facilities, embankments, tailings conveyors, and water management infrastructure; the timely receipt of necessary permits and authorizations and our ability to comply with the terms of existing and future permits and authorizations; differences between projected and actual degree of pre-strip required in the open pit; variability in metallurgical recoveries and concentrate quality due to factors such as extent and intensity of oxidation or presence of transition minerals; presence of additional structural features impacting hydrological and geotechnical considerations; variability in minerals or presence of substances that may have an impact on filtered tails performance and resulting bulk density of stockpiles or filtered tails; distribution of sulphides that may dilute concentrate and change the characteristics of tailings; unexpected disruptions to operations including protests, non-routine regulatory inspections, road conditions, on site or labour unrest; unexpected inclement weather and climate events, including wildfires, short and long duration rainfall and floods and other extreme weather events and our site’s ability to respond to those events; our ability to meet pre-commercial producing mining or underground development targets; unexpected results from underground stopes; new archaeological discoveries requiring the completion of a regulatory process; changes in support from local communities; our ability to meet the expectations of communities, governments, and stakeholders related to the Skouries mine; risks relating to changes in treatment and refining charges and other commercial terms; risks relating to concentrate quality, including penalty elements and the ability to meet smelter specifications; risks relating to the transportation of concentrate, including road conditions, trucking availability, cross-border logistics and related delays or costs; risks relating to changes in European Union policy, including the EU Critical Raw Materials Act, and to the maintenance of the designation of Skouries as a Strategic Project and any benefits associated therewith; and that the updated Technical Report may not be filed within the expected timeline, or that the updated resource model, metal price assumptions, and production, operating cost and capital estimates may differ materially from current estimates. Our project capital and accelerated operational capital costs at Skouries are incurred primarily in Euros but are reported in US dollars and are therefore sensitive to fluctuations in the EUR/USD exchange rate.

The inclusion of forward-looking statements and information is designed to help you understand management’s current views of our near- and longer-term prospects, and it may not be appropriate for other purposes. There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Except as required by law, we do not expect to update forward-looking statements and information continually as conditions change and you are referred to the full discussion of the Company’s business contained in the Company’s reports filed with the securities regulatory authorities in Canada and the United States. Accordingly, you should not place undue reliance on the forward-looking statements or information contained herein.


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

When does Eldorado Gold expect commercial production at Skouries?

Eldorado Gold expects Skouries to reach commercial production late this quarter. The four filter presses now operational meet the filtration requirement for commercial production on sulphide ore.

When will Eldorado Gold file its updated Skouries technical report, and what will it include?

Eldorado Gold expects to file the updated Skouries technical report in the first quarter of 2027. It will update the resource model and metal price assumptions, along with production, operating cost and capital estimates that reflect the mine’s transition into operations.

Why does Eldorado Gold have a sixth filter press at Skouries?

The sixth press is an installed spare that allows maintenance without reducing the amount of material the facility can process.

Keep reading