Entergy Louisiana to power Meta's data center in Richland Parish
Rhea-AI Summary
Entergy Louisiana announces plans to support Meta's $10 billion data center project in Richland Parish with significant infrastructure investments. The facility, set to be Meta's largest at over 4-million square feet, will be built on the 1,400-acre Franklin Farm mega site.
The infrastructure development includes building three combined-cycle combustion turbines with 2,260 megawatts capacity, two Entergy-owned substations, six customer-owned substations, and nearly 100 miles of transmission lines. The project will create 1,500-1,800 construction jobs for generation units and 3,500-5,000 jobs for transmission investments, plus 44 permanent positions.
Meta will share infrastructure costs and contribute $1 million to Entergy's Power to Care program. The new generators, expected online between 2028-2029, will support 30% hydrogen co-firing initially, with potential for 100% hydrogen transition and carbon capture capabilities.
Positive
- Meta's $10 billion investment in data center construction
- Creation of up to 6,800 construction jobs and 44 permanent positions
- Meta's cost-sharing agreement expected to reduce existing customer costs by over $300 million
- $1 million contribution to The Power to Care program
- Significant infrastructure expansion with 2,260 megawatts of new generation capacity
Negative
- Substantial capital expenditure required for infrastructure development
- Long implementation timeline with generators coming online only by 2028-2029
News Market Reaction 1 Alert
On the day this news was published, ETR gained 1.37%, reflecting a mild positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
Investment in new infrastructure will transform
This transformative project promises to revitalize
"Today marks a turning point for
Just as Entergy's founder, Harvey Couch, pioneered new power solutions nearly a century ago, Entergy Louisiana is building on its legacy of innovation and commitment to community growth. By constructing cutting-edge electric infrastructure, Entergy is laying the foundation for economic success in a region that has faced challenges such as population decline and outward migration.
Strategic site selection
Meta's data center will be built on what is referred to as the Franklin Farm mega site, a more than 1,400-acre certified site, in
"We're not going to just be powering a facility, we're going to be empowering a community," May added. "From job creation to infrastructure improvements, this partnership with Meta demonstrates what's possible when innovative companies and communities come together to build a brighter future.
"Our team is proud to have played a significant role in assisting the
Economic impact
Meta has announced their significant investment and associated impacts for their new artificial intelligence-optimized data center.
During construction, Entergy Louisiana projects will provide significant economic benefits and create:
- 1,500 to 1,800 construction jobs for the new advanced generation units being constructed
- 3,500 to 5,000 construction jobs for substation and transmission investment
- 44 permanent jobs
Infrastructure to power progress
To support the Richland Parish Data Center, as well as broader economic development in the state and our growing customer base, Entergy Louisiana will:
- Build three combined-cycle combustion turbines with a combined capacity of 2,260 megawatts, two of which will be in
Richland Parish - Construct two Entergy-owned substations and six customer-owned substations
- Install nearly 100 miles of 500kV transmission lines and eight new 230kV transmission lines
- Upgrade existing infrastructure, including a substation near
Sterlington
Pending regulatory approval, the new generators are expected to come online between 2028 and 2029.
Shared costs and community benefits
Revenue from Meta will significantly offset the costs associated to make service available to the company's data center and the region. Moreover, Meta will also share in the future cost of providing service like other customers including Formula Rate Plan costs, securitized storm costs and resiliency costs – this is expected to reduce costs that existing customers would otherwise pay by more than
Commitment to sustainability
Both Meta and Entergy Louisiana are committed to sustainability. The new generators will initially support the ability to utilize
Meta has also committed to helping fund CCS technology at an Entergy power plant in
The companies have also committed to exploring nuclear energy as a future power supply option alongside renewable sources like solar and wind. This effort includes researching conventional nuclear technologies, supporting small modular reactors and potential upgrades to enhance the output of existing nuclear plants in
About Entergy Louisiana
Entergy Louisiana, LLC provides electric service to more than 1 million customers in 58 parishes and natural gas service to more than 94,000 customers in
Cautionary note regarding forward-looking statements
In this news release, and from time to time, Entergy Louisiana makes certain "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. Such forward-looking statements include, among other things, statements regarding Entergy Louisiana's planned capital investments and its operational and load growth outlooks; and other statements of Entergy Louisiana's plans, beliefs, or expectations included in this news release. Readers are cautioned not to place undue reliance on these forward-looking statements, which apply only as of the date of this news release. Except to the extent required by the federal securities laws, Entergy Louisiana undertakes no obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events, or otherwise.
Forward-looking statements are subject to a number of risks, uncertainties, and other factors that could cause actual results to differ materially from those expressed or implied in such forward-looking statements, including (a) those factors discussed elsewhere in this news release and in Entergy Louisiana's most recent Annual Report on Form 10-K, any subsequent Quarterly Reports on Form 10-Q, and Entergy Louisiana's other reports and filings made under the Securities Exchange Act of 1934; (b) uncertainties associated with (1) rate proceedings, formula rate plans, and other cost recovery mechanisms, including the risk that costs may not be recoverable to the extent or on the timeline anticipated by the utilities and (2) implementation of the ratemaking effects of changes in law; (c) risks associated with operating nuclear facilities, including plant relicensing, operating, and regulatory costs and risks; (d) risks and uncertainties associated with executing on business strategies, including (1) strategic transactions that Entergy or its subsidiaries may undertake and the risk that any such transaction may not be completed as and when expected and the risk that the anticipated benefits of the transaction may not be realized, and (2) Entergy's ability to meet the rapidly growing demand for electricity, including from hyperscale data center and other large customers, and to manage the impacts of such growth on customers and Entergy's business; (e) direct and indirect impacts to Entergy or its customers from pandemics, terrorist attacks, geopolitical conflicts, cybersecurity threats, data security breaches, or other attempts to disrupt Entergy's business or operations, and/or other catastrophic events; and (f) effects on Entergy or its customers of (1) changes in federal, state, or local laws and regulations and other governmental actions or policies, including changes in monetary, fiscal, tax, environmental, or energy policies; (2) changes in commodity markets, capital markets, or economic conditions; and (3) technological change, including the costs, pace of development, and commercialization of new and emerging technologies.
View original content to download multimedia:https://www.prnewswire.com/news-releases/entergy-louisiana-to-power-metas-data-center-in-richland-parish-302324046.html
SOURCE Entergy Corporation