STOCK TITAN

Investing in Power Grid Reliability for Toledo Edison Families and Businesses in Northwest Ohio

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

FirstEnergy (NYSE: FE) and its transmission unit ATSI began construction Oct 22, 2025 on a major reliability project in Fulton County, Ohio that includes a new substation and a nine-mile 345-kV transmission line to serve Delta Village, Fulton, Pike, Swan Creek and York townships.

The substation is planned to be operational by December 2026 and will connect to the existing Sydney Substation via two new half-mile lines. The work is part of Energize365, a $28 billion grid modernization program (2025–2029), and ATSI plans to invest more than $200 million in northwest Ohio. FirstEnergy notes its transmission companies reduced outages on >100-kV lines by 50% since 2014.

FirstEnergy (NYSE: FE) e la sua unità di trasmissione ATSI hanno iniziato la costruzione il 22 ottobre 2025 su un importante progetto di affidabilità nel Fulton County, Ohio, che comprende una nuova sottostazione e una linea di trasmissione a 345 kV di nove miglia per servire Delta Village, Fulton, Pike, Swan Creek e York

La sottostazione dovrebbe essere operativa entro dicembre 2026 e si collegherà alla sottostazione di Sydney esistente tramite due nuove linee di mezzo miglio ciascuna. Il lavoro fa parte di Energize365, un programma di modernizzazione della rete da 28 miliardi di dollari (2025–2029), e ATSI prevede di investire più di 200 milioni di dollari nel nord-ovest dell'Ohio. FirstEnergy segnala che le sue aziende di trasmissione hanno ridotto le interruzioni sulle linee >100 kV del 50% dal 2014.

FirstEnergy (NYSE: FE) y su unidad de transmisión ATSI iniciaron la construcción el 22 de octubre de 2025 de un importante proyecto de confiabilidad en el condado de Fulton, Ohio, que incluye una nueva subestación y una línea de transmisión de 345 kV de nueve millas para servir a Delta Village, Fulton, Pike, Swan Creek y York townships.

Se espera que la subestación esté operativa para diciembre de 2026 y se conectará a la Subestación de Sydney existente mediante dos nuevas líneas de medio kilómetro. El trabajo forma parte de Energize365, un programa de modernización de la red de 28 mil millones de dólares (2025–2029), y ATSI planea invertir más de 200 millones de dólares en el noroeste de Ohio. FirstEnergy señala que sus empresas de transmisión han reducido los cortes en líneas de >100 kV en un 50% desde 2014.

FirstEnergy (NYSE: FE) 와 그의 송전 부문 ATSI 는 Delta Village, Fulton, Pike, Swan Creek 및 York 타운십에 서비스를 제공하기 위한 새로운 변전소와 9마일 길이의 345-kV 송전선을 포함하는 중요한 신뢰성 프로젝트의 건설을 2025년 10월 22일 시작했습니다.

이 변전소는 2026년 12월까지 가동될 예정이며 기존 Sydney 변전소와 두 개의 새로운 반마일 선으로 연결될 것입니다. 이 작업은 Energize365의 일부로, 2025–2029년의 280억 달러 규모의 그리드 현대화 프로그램이며 ATSI는 오하이오 북서부에 2억 달러 이상를 투자할 계획입니다. FirstEnergy 는 자사의 송전 회사들이 2014년 이후 >100 kV 선의 정전을 50% 감소시켰다고 밝힙니다.

FirstEnergy (NYSE: FE) et son unité de transmission ATSI ont commencé la construction le 22 octobre 2025 d'un important projet de fiabilité dans le comté de Fulton, Ohio, comprenant une nouvelle substation et une ligne de transmission à 345 kV sur neuf miles pour desservir Delta Village, Fulton, Pike, Swan Creek et York townships.

La sous-station devrait être opérationnelle d'ici décembre 2026 et sera connectée à la sous-station existante de Sydney via deux nouvelles lignes d'un demi-mile chacune. Le travail fait partie d'Energize365, un programme de modernisation du réseau de 28 milliards de dollars (2025–2029), et ATSI prévoit d'investir plus de 200 millions de dollars dans le nord-ouest de l'Ohio. FirstEnergy note que ses sociétés de transmission ont réduit les pannes sur les lignes >100 kV de 50% depuis 2014.

FirstEnergy (NYSE: FE) und seine Übertragungseinheit ATSI begannen am 22. Oktober 2025 mit dem Bau eines wichtigen Zuverlässigkeitsprojekts im Fulton County, Ohio, das eine neue Umspannstation und eine neun Meilen lange 345-kV-Übertragungsleitung umfasst, um Delta Village, Fulton, Pike, Swan Creek und York Townships zu versorgen.

Die Umspannstation soll bis Dezember 2026 betriebsbereit sein und wird über zwei neue halbe Meilen lange Leitungen mit der bestehenden Sydney-Umspannstation verbunden. Die Arbeiten sind Teil von Energize365, einem 28-Milliarden-Dollar Netzausrüstungsprogramm (2025–2029), und ATSI plant, mehr als 200 Millionen Dollar in Nordwest-OHIO zu investieren. FirstEnergy weist darauf hin, dass seine Übertragungsunternehmen die Ausfälle bei Linien >100 kV seit 2014 um 50% reduziert haben.

FirstEnergy (NYSE: FE) وUnit النقل التابعة لها ATSI بدأوا البناء في 22 أكتوبر 2025 على مشروع موثوقية رئيسي في مقاطعة فولتون، أوهايو يشمل محطة تحويل جديدة وخط نقل بقدرة 345 kV بطول تسع أميال لخدمة Delta Village و Fulton و Pike و Swan Creek و York Townships.

من المقرر أن تكون المحطة التشغيلية بحلول ديسمبر 2026 وستتصل بمحطة Sydney الحالية عبر خطين جديدين بطول نصف ميل. العمل جزء من Energize365، وهو برنامج تحديث شبكة بقيمة 28 مليار دولار (2025–2029)، وتخطط ATSI لاستثمار أكثر من 200 مليون دولار في شمال غرب أوهايو. وتلاحظ FirstEnergy أن شركات النقل التابعة لها خفضت الانقطاعات على خطوط >100 كV بنسبة 50% منذ 2014.

Positive
  • New substation planned to be operational by December 2026
  • Nine-mile 345-kV transmission line added in Fulton County
  • Two new half-mile lines connecting to the Sydney Substation
  • Energize365 $28 billion grid investment program (2025–2029)
  • ATSI investing more than $200 million in northwest Ohio
  • Transmission companies report 50% fewer outages on >100-kV lines since 2014
Negative
  • None.

Insights

New substation and a nine‑mile 345‑kV line backed by a $28 billion modernization plan should materially raise local grid reliability.

The project adds a new substation tied to the existing Sydney Substation with two half‑mile lines and a nine‑mile 345‑kV transmission route, creating alternate paths for power and increasing capacity. That network redundancy reduces single‑point failures and lets crews restore service faster, which directly improves service for homes and businesses served by Toledo Edison.

Dependencies and risks include timely commissioning by December 2026, successful integration with existing protection and control systems, and execution of the physical build. The announcement cites a 50% reduction in outages on >100‑kV lines since 2014 as context, but the local benefit depends on completion on schedule and correct interconnection work.

Concrete items to watch: completion of the substation by December 2026, progress milestones for the nine‑mile line, and the local spend pace from the $200 million northwest Ohio allocation within the broader $28 billion Energize365 program; expect meaningful local reliability improvements once the substation and ties are energized within the stated timeframe.

Construction recently kicked off on new substation and backup power lines

TOLEDO, Ohio, Oct. 22, 2025 /PRNewswire/ -- A major reliability project is transforming electric service in Fulton County, delivering stronger, more resilient power to thousands of residents and businesses in the greater Toledo area, including customers of Toledo Edison, a FirstEnergy (NYSE: FE) electric company.

Led by American Transmission Systems, Inc. (ATSI), a FirstEnergy Transmission company, the project includes a new substation and nine-mile-long 345-kilovolt (kV) transmission line to help prevent or minimize the impact of power outages in and around Delta Village, Fulton, Pike, Swan Creek and York townships and support continued future growth in northwest Ohio.

Faster Fixes, Fewer Outages
A new electric substation is planned to be up and running by December 2026. It will be connected to the existing Sydney Substation by two new half-mile power lines. These additions will bring more electricity to the area, making the system more flexible if a customer's main power line is taken out of service and will help crews restore power more quickly during outages.

It's like upgrading your neighborhood's power grid from a two-lane road to a multi-lane highway. More lanes mean more capacity, smoother traffic flow and fewer bottlenecks—especially during rush hour when energy demand is high. Just like a well-designed highway system, it's built to grow with the community, keeping pace as more homes and businesses come online.

Since 2014, FirstEnergy's transmission companies have collectively reduced outages by 50% on high-voltage power lines exceeding 100-kVs – proof that the companies' strategic infrastructure investments, like this work in northwest Ohio, are making the grid more reliable for customers.

Why this Project Matters to You
If you live in Fulton County, this project is all about helping your lights stay on, especially when demand is high, like during heat waves or cold snaps and during storms. If you do experience an outage, this upgrade adds back up power sources and smarter equipment that can reroute electricity. That means:

  • Fewer outages.
  • Faster restoration.
  • More reliable service for homes, businesses and companies looking to start or expand here.

Mark Mroczynski, President of Transmission for FirstEnergy: "Northwest Ohio has seen tremendous industrial growth in recent years, bringing new jobs, families and opportunities to the region. We're proud to support that momentum by investing in the power infrastructure needed to meet today's demand and tomorrow's potential."

View or download a video series on "Why a Modern Transmission System Matters to You" on FirstEnergy's YouTube channel.

Built for Today – and Tomorrow
This work is part of Energize365, FirstEnergy's $28 billion investment program to modernize the electric grid between 2025 and 2029. In northwest Ohio alone, ATSI is investing more than $200 million in high-voltage grid enhancements over the next few years. The goal: a smarter, more secure grid that meets the needs of today's customers and tomorrow's growth.

View or download video of this grid enhancement work underway in Fulton County.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Visit FirstEnergy online at firstenergycorp.com and follow FirstEnergy on X @FirstEnergyCorp

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/investing-in-power-grid-reliability-for-toledo-edison-families-and-businesses-in-northwest-ohio-302591709.html

SOURCE FirstEnergy Corp.

FAQ

What is FirstEnergy (FE) building in Fulton County, Ohio and when will it be ready?

FirstEnergy/ATSI is building a new substation and a nine-mile 345-kV line; the substation is planned to be operational by December 2026.

How much is ATSI investing in northwest Ohio as part of the FirstEnergy (FE) plan?

ATSI is investing more than $200 million in high-voltage grid enhancements in northwest Ohio over the next few years.

What is Energize365 and how does it relate to FirstEnergy (FE)?

Energize365 is FirstEnergy's $28 billion grid modernization program running from 2025 to 2029, funding projects including the Fulton County upgrades.

Will the Fulton County transmission upgrades reduce outages for Toledo Edison customers (FE)?

The upgrades add backup routes and smarter equipment; FirstEnergy reports its transmission companies have cut outages on >100-kV lines by 50% since 2014.

Which communities will benefit from the new FirstEnergy (FE) transmission work in northwest Ohio?

Customers in Delta Village, Fulton, Pike, Swan Creek and York townships in the greater Toledo area are the primary beneficiaries.
Firstenergy Corp

NYSE:FE

FE Rankings

FE Latest News

FE Latest SEC Filings

FE Stock Data

26.86B
547.61M
0.17%
92.8%
4.22%
Utilities - Regulated Electric
Electric Services
Link
United States
AKRON