New Transformer Installed and Energized in Downtown Bradford Substation
Rhea-AI Summary
FirstEnergy's Pennsylvania Electric Company (Penelec) has installed and energized a new transformer at a Bradford substation, enhancing service reliability for over 1,000 customers, including the University of Pittsburgh's Bradford campus. The 40,000-pound transformer replaced a faulty unit and features forced-air cooling fans for increased capacity. This installation is part of Energize365, a multi-year grid evolution program with planned investments of $26 billion between 2024-2028. Additionally, Penelec completed a forestry project in the Bradford area, removing approximately 1,400 hazardous trees and utilizing helicopter-mounted saws for efficient tree trimming along power lines.
Positive
- Installation of new transformer enhances service reliability for over 1,000 customers
- Part of $26 billion Energize365 grid evolution program (2024-2028)
- New transformer offers increased capacity with forced-air cooling system
- Completion of significant forestry project improving service reliability
Negative
- Previous transformer failure required temporary mobile substation solution
News Market Reaction
On the day this news was published, FE declined 0.41%, reflecting a mild negative market reaction.
Data tracked by StockTitan Argus on the day of publication.
New Penelec equipment to enhance electric service reliability for more than 1,000 customers
The substation's previous transformer experienced an issue last fall and could not be repaired. A mobile substation provided temporary service to customers until a new transformer could be located, transported and installed to help ensure long-term grid stability.
John Hawkins, FirstEnergy
The new transformer measures 7-feet by-4-feet, stands 11 feet tall and weighs nearly 40,000 pounds. A large crane hoisted the unit over the substation fence and onto a concrete foundation. Electricians installed new electric cables in the substation to power the transformer's forced-air cooling fans, which provide more capacity than the former transformer that relied on natural air circulation to cool. Access into the substation was also enhanced to prevent utility trucks from blocking the street when using the front gate.
With the new transformer in place and operating properly, the mobile substation has been disconnected and is ready for deployment to where it is needed next.
Photos of a crane removing the old transformer from the Bradford West Substation near the University of
The work is part of Energize365, a multi-year grid evolution program focused on transmission and distribution investments that will deliver the power FirstEnergy's customers depend on today while also meeting the challenges of tomorrow. With planned investments of
Earlier this year, Penelec completed a significant forestry project to improve electric service reliability for customers in the
As part of that effort, contractor Aerial Solutions used a helicopter saw to trim trees along a 13-mile power line running through rugged, heavily wooded terrain from a substation in
Penelec serves approximately 597,000 customers within 17,600 square miles of northern and central
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in
View original content to download multimedia:https://www.prnewswire.com/news-releases/new-transformer-installed-and-energized-in-downtown-bradford-substation-302286106.html
SOURCE FirstEnergy Corp.