Fermi Announces Binding Lease Agreement with TensorWave

(Very Positive)
Tags

Fermi (NASDAQ:FRMI) signed its first binding customer lease at the Project Matador AI data center campus in Carson County, Texas, with TensorWave TEX1, LLC, a subsidiary of AI cloud provider TensorWave. The turnkey lease for phase one covers a facility supported by 222 MW of total facility power once the final delivery phase begins.

The initial 15-year term is expected to generate about $6.5 billion in contracted revenue, excluding renewal options, and includes expansion rights for two additional data centers that could bring the partnership to over 650 MW. Deliveries are planned to start in phases in the second half of 2027, subject to customary conditions such as project guaranties and financing. Fermi reports that roughly 6 GW of the planned 17 GW at Project Matador is already permitted and that more than $1.5 billion has been invested in the buildout, with first power targeted for 2026.

Loading...
Loading translation...

Positive

  • $6.5 billion in total contracted revenue over 15-year initial term for phase one
  • Phase-one lease covers 222 MW of facility power, with expansion rights above 650 MW
  • First binding customer lease at Project Matador de-risks commercialization of the campus
  • Approximately 6 GW of the planned 17 GW already permitted at Project Matador
  • More than $1.5 billion invested in Project Matador buildout to date

Negative

  • Lease effectiveness and delivery are subject to customary conditions, including project guaranties and financing
  • Project Matador ramp to approximately 17 GW remains subject to entering additional binding customer agreements

News Explained

Under the turnkey lease, Fermi is responsible for developing, constructing, and delivering the phase-one facility, while TensorWave takes occupancy in phases; the agreement also remains subject to project guaranties and financing before closing.

Market reaction after 15-year data center lease: FRMI +19.35%

+19.35% $7.02
15m delay
+19.35% Vs previous close
+22.2% Peak in 7 min
$7.02 Last Price
$5.84 $8.16 Day Range
$4.48B Market Cap
1.2x Rel. Volume

Following this news, FRMI has gained 19.35%, reflecting a significant positive market reaction. Argus tracked a peak move of +22.2% during the session. Our momentum scanner has triggered 65 alerts so far, indicating high trading interest and price volatility. The stock is currently trading at $7.02.

Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.

Market Context

The stock is surging +21.1% following this news. A prior Fermi earnings-release notice drew a 8.66% ...
Analysis

The stock is surging +21.1% following this news. A prior Fermi earnings-release notice drew a 8.66% 24-hour reaction in the platform record. The lease added a commercial milestone, while recent net insider selling remained a sourced risk.

Key Figures

Contracted Revenue: $6.5 billion Initial Lease Term: 15 years Phase One Capacity: 222 MW +5 more
8 metrics
Contracted Revenue $6.5 billion Initial 15-year term for phase one
Initial Lease Term 15 years Following commencement of the final delivery phase
Phase One Capacity 222 MW Total facility power
Expansion Capacity More than 650 MW If rights for two additional data centers are exercised
Permitted Capacity Approximately 6 GW Of 17 GW planned at Project Matador
Buildout Investment More than $1.5 billion Invested to date
Planned Capacity 17 GW Planned Project Matador capacity
Delivery Start Second half of 2027 Phased facility delivery

Historical Context

5 past events · Latest: Jul 23 (Negative)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jul 23 Share admission Negative -4.0% New shares admitted for advisory fees and restricted stock unit settlement
Jul 21 Turbine arrival Positive -1.1% Three Siemens turbines arrived to support Project Matador power buildout
Jul 20 Earnings scheduling Neutral +8.7% Second quarter results and conference call were scheduled for August 13
Jul 15 Convertible offering Negative -7.3% Convertible notes offering expanded to support liquidity and Project Matador
Jul 13 Board resignation Negative -4.3% Former Fermi CFO Miles Everson resigned from the company board

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Project execution news previously diverged from price performance, while financing and governance-related events aligned with negative reactions.

Key Terms

behind the meter, inference
2 terms
behind the meter technical
"delivered behind the meter and on a private grid built and operated on site"
Energy generation or equipment located on a customer’s side of the utility meter, such as rooftop solar panels, battery storage, electric vehicle chargers or energy-saving controls. It matters to investors because it reduces the amount of electricity bought from utilities, can lower operating costs for businesses, change utility revenue patterns, and shift demand in energy markets—like a homeowner installing a rain barrel that cuts water bought from the city and alters suppliers’ sales.
inference technical
"for large-scale AI training and inference"
Inference is the process of drawing a conclusion from available evidence or data, like a detective piecing together clues to form a likely story. For investors it matters because these judgments turn raw reports, test results, or market signals into expectations about future performance, risk, or regulatory outcomes—so how someone infers from the same facts can change investment decisions and valuation.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Reason for change: Unfinalized version was submitted

Intends to grow the partnership to more than 650 megawatts (MW) over three phases

First phase to deliver a complete turnkey data center solution with 222 MW beginning in the second half of 2027, representing approximately $6.5 billion in total contracted revenue

Fermi and TensorWave have lined up world-class partners to collaborate on the project

DALLAS, TX / ACCESS Newswire / August 10, 2026 / Fermi Inc. (NASDAQ:FRMI)(LSE:FRMI), operating as Fermi America™ ("Fermi" or the "Company"), announced today that it has executed its first binding customer lease at its Project Matador campus in Carson County, Texas. The lease between Fermi's subsidiary Fermi Campus 1 LLC and TensorWave TEX1, LLC, a subsidiary of AI cloud provider TensorWave Inc., covers a facility supported by 222 megawatts (MW) of total facility power following commencement of the final delivery phase. Once fully delivered, the facility is being designed to support tens of thousands of next-generation AMD Instinct GPUs for large-scale AI training and inference. The lease is expected to generate approximately $6.5 billion in total contracted revenue over the initial 15-year term, for the first phase, excluding any renewal terms. The lease carries expansion rights for two additional data centers that when exercised, would bring the partnership to a total of more than 650 MW.

Construction at Project Matador is well underway, with approximately 6 gigawatts (GW) of the planned 17 GW already permitted, more than $1.5 billion invested in the buildout to date, and first power targeted for 2026. As a result, Fermi is positioned to deliver AI data center capacity in a market where many projects are still raising the capital required to build or being blocked by permitting issues.

"A lease of this size and this term is a tremendous vote of confidence in Fermi," said Marius Haas, Chairman of the Board of Directors of Fermi Inc. "In delivering this first binding agreement, we've now fulfilled the most important objective we shared with the market in May. The committed partner ecosystem of developers, guarantors, and financing providers are all industry-leading companies, and TensorWave is exactly the kind of anchor customer our project was designed for. I am incredibly proud of our team for executing the site buildout to date, and for delivering this agreement and advancing others that we expect to announce soon."

Transaction summary

  • Structure: Turnkey data center lease. Fermi develops, constructs and delivers the facility; TensorWave takes occupancy in phases.

  • Capacity: 222 MW of total facility power for phase one with expansion rights that would bring the partnership to a total of more than 650 MW.

  • Term: Initial term of 15 years following commencement of the final delivery phase, with two renewal options of five years each.

  • Contracted Revenue: Approximately $6.5 billion over the initial 15-year term for phase one.

  • Delivery: Phased, beginning the second half of 2027.

  • Conditions: The lease contains customary conditions, including the receipt of requisite project guaranties and financing.

"Power is the critical constraint in AI infrastructure, and the vision and scope of what Fermi is building at Project Matador resonates with our own," said Darrick Horton, CEO and Co-Founder of TensorWave. "Our customers need hundreds of thousands of next-generation AMD Instinct GPUs in aggregate, on timelines they can count on. Fermi has assembled the power, land, and permits to deliver at that pace, and we are proud to be the first customer at a campus built for the decades ahead."

Fermi has been advised by the Texas Tech University System that it supports the transaction and intends to work closely with Fermi toward a successful closing.

"The Texas Tech University System-Fermi partnership is delivering on the bold vision behind Project Matador," said Chancellor Brandon Creighton. "TensorWave's selection of Fermi sends a strong signal about the enormous potential of this project and the Texas Panhandle. The System is proud to help position our region at the forefront of America's energy, AI and national security future."

Fermi continues to advance discussions with additional hyperscale, neo-cloud and enterprise compute counterparties for capacity at Project Matador, and with development, construction, and financing partners for the campus. Fermi expects to provide further detail as agreements are finalized.

About Fermi's Project Matador
Fermi America is where AI gets power. The Company is developing one of the world's largest advanced energy and AI ecosystems, on an area in the Texas Panhandle that's more than half the size of Manhattan. The site, called Project Matador, is secured or under long-term lease with more than $1.5 billion invested in buildout to date. Fermi designed the project to solve the single biggest constraint in AI infrastructure: access to large-scale, reliable power on a timeline that meets customer demand - delivered behind the meter and on a private grid built and operated on site. Subject to entering into binding customer agreements, the project is expected to ramp to approximately 17 GW, with capital deployment matched to commercial progress.

Investor Contact
Barry Sievert | IR@fermiamerica.com

Media Contact
Fermi Inc. Communications | media@fermiamerica.com

About Fermi America™
Fermi America™ (NASDAQ:FRMI)(LSE:FRMI) develops next-generation private electric grids that deliver highly redundant power at gigawatt scale to support next-generation intelligence and AI compute. Fermi America™ combines cutting-edge technology with a deep bench of proven world-class multi-disciplinary leaders with a combined 25 GW of experience, to create the world's largest, 17 GW next-gen private grid, helping ensure America's energy and AI dominance. The behind-the-meter Project Matador campus is expected to integrate the nation's biggest combined-cycle natural gas project, one of the largest clean, new nuclear power complexes in America, utility grid power, solar power, and battery energy storage, to support hyperscale AI and advanced computing. For additional information visit www.fermiamerica.com.

About TensorWave
TensorWave is the AI cloud purpose-built for performance. Powered exclusively by AMD Instinct™ Series GPUs, TensorWave delivers high-bandwidth, memory-optimized infrastructure that scales with the most demanding training and inference workloads. Backed by funding from investors including Magnetar, AMD Ventures, Maverick Silicon, Nexus Venture Partners, and Western Frontier, TensorWave operates one of the world's largest all-AMD GPU clouds and is expanding rapidly to meet global demand. For more information, please visit tensorwave.com.

Forward-Looking Statements
This press release may contain "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995, including statements regarding the Company's commercial strategy, tenant agreements, Project Matador, expected capacity, delivery schedules, financing arrangements, expansion opportunities, the potential exercise of expansion rights and any resulting capacity or revenue, expected contracted revenue, the anticipated growth of the company's relationship with TensorWave, market demand, the timing and conditions of construction capital deployment, the sufficiency and continued availability of tenant credit support, the availability of project financing, and future operations. Forward-looking statements are based on current expectations and assumptions and are subject to risks and uncertainties that could cause actual results to differ materially from those expressed or implied. The Company undertakes no obligation to update any forward-looking statements except as required by law.

SOURCE: Fermi Inc.



View the original press release on ACCESS Newswire

FAQ

What did Fermi (FRMI) announce about its lease agreement with TensorWave on August 10, 2026?

Fermi announced its first binding customer lease at Project Matador with TensorWave, covering 222 MW of AI-focused data center capacity. According to Fermi, this turnkey lease is expected to generate about $6.5 billion in contracted revenue over a 15-year initial term for phase one.

How much revenue is Fermi (FRMI) expecting from the TensorWave lease at Project Matador?

Fermi expects approximately $6.5 billion in total contracted revenue from the first phase of the TensorWave lease. According to Fermi, this amount is over the initial 15-year term and excludes any renewal periods that TensorWave may later exercise.

What is the power capacity and term of Fermi’s TensorWave lease at Project Matador (FRMI)?

The phase-one lease supports 222 MW of total facility power with an initial 15-year term starting after final delivery. According to Fermi, the agreement includes two five-year renewal options and expansion rights that could bring the partnership above 650 MW in total capacity.

When will Fermi begin delivering data center capacity to TensorWave under the FRMI Project Matador lease?

Deliveries under the TensorWave lease are planned to begin in phases in the second half of 2027. According to Fermi, the lease becomes effective subject to customary conditions, including obtaining requisite project guaranties and financing for the Project Matador buildout.

How advanced is Fermi’s Project Matador buildout supporting the TensorWave agreement (FRMI)?

Fermi reports that around 6 GW of the planned 17 GW at Project Matador is already permitted. According to Fermi, more than $1.5 billion has been invested so far, with first power for the campus targeted for 2026, ahead of TensorWave’s phased occupancy.

Does the TensorWave deal cover all of Fermi’s Project Matador capacity (FRMI)?

No, the TensorWave lease currently covers 222 MW in phase one with expansion rights above 650 MW. According to Fermi, Project Matador is expected to ramp toward approximately 17 GW overall, subject to additional binding customer agreements and matched capital deployment.