Fermi (FRMI) Stock Rose 44% in Two Trading Days, and Its Hyperscaler Deal Is Still a Letter of Intent

Aerial view at dusk of a large graded empty site on the Texas prairie with glowing outlines of future buildings marked on the dirt, beside a power plant under construction with cranes

Fermi (FRMI) stock rose 44% over November 12 and 13, StockTitan data show. Fermi announced a 600 megawatt hyperscaler deal on the first day, and its 10-Q calls it a non-binding letter of intent. At market rates in Fermi's slides, the $200 million prepayment is under a tenth of the cost to build that power.

The short answer. Fermi agreed with a big, unnamed cloud company on a prepayment and early site work. The lease is not signed, and Fermi had not said by November 16 that the money arrived.

It matters beyond Fermi because it tests whether a campus that sells power can win a tech giant before any building exists. The prepayment is about 7% to 9% of what 600 megawatts would cost at the market rates in Fermi's slides. In 2025, a prospective tenant with a strong credit rating agreed, subject to conditions, to advance up to $150 million for early work.

It ended that agreement in December with no money drawn. Fermi is also asking Texas Tech for more time on a December 31 deadline for a signed tenant.

Fermi's hyperscaler deal in three numbers

Power in the letter of intent
~600 MW
Non-binding, signed November 10, 2026
Prepayment agreement
$200M
About 7% to 9% of the market cost to build 600 MW
Texas Tech deadline
Dec 31
Texas Tech condition: a signed lease of at least 200 MW
A 600 MW letter of intent with a $200 million prepayment agreement, and a Texas Tech deadline on December 31, 2026. Figures from Fermi Form 10-Q for the quarter ended September 30, 2026, as of November 12, 2026; Fermi investor presentation, Q3 2026 (8-K exhibit 99.2), page 11, as of November 12, 2026; Fermi release, New Agreements with Investment-Grade Hyperscaler, November 12, 2026, as of November 12, 2026.
The $200 million prepayment beside the cost to build 600 MW. At the low end of the market cost range in Fermi's investor presentation, building 600 MW of powered land would cost about 12 times the $200 million prepayment.
The $200 million prepayment beside the cost to build 600 MW At the low end of the market cost range in Fermi's investor presentation, building 600 MW of powered land would cost about 12 times the $200 million prepayment. Figures from Fermi investor presentation, Q3 2026 (8-K exhibit 99.2), page 11, as of November 12, 2026; Fermi Form 10-Q for the quarter ended September 30, 2026, as of November 12, 2026.
Show the data
ItemValueTimes the smallest
Cost to build 600 MW (low end)$2,340M12x
Cash and restricted cash, Sept. 30$316M1.6x
Prepayment agreement$200M1.0x

On this page

Every company reporting the same week, with its date and time, is in StockTitan's Earnings Calendar for the Week of November 9, 2026.

What is in Fermi's 600 MW hyperscaler deal?

A big cloud company has agreed to pay Fermi money up front and to start site work before it signs a lease. The lease itself, with the rent and the term, is still being negotiated.

Fermi's November 12 release says it entered "multiple new agreements" with an investment-grade hyperscaler. That means a giant cloud company with a strong credit rating. The deal covers an initial 600 megawatts of power at Project Matador, Fermi's campus near Amarillo, Texas, starting in 2027.

Two parts are signed. One is a $200 million prepayment agreement, which "provides for substantial upfront customer funding". The other is a $15 million agreement to start site preparation and construction. A third part, the sale of about $90 million of structural steel that Fermi bought early, is still being finalized.

The 10-Q, the quarterly report Fermi filed with the SEC that evening, names the core deal plainly. On November 10, Fermi "entered into a non-binding letter of intent with an investment-grade hyperscaler" for "approximately 600 megawatts ("MW") of powered land". A letter of intent sets out terms both sides mean to sign later. The filing adds that there is "no guarantee that the definitive lease with the IG Tenant will be executed."

The company is upbeat. CEO Lee McIntire said in the release that the customer "committed more than $200 million up front to accelerate construction." On the November 12 earnings call, Chief Commercial Officer Anna Bofa said lease talks are "very, very far along." She said the agreement requires the $200 million wire by November 13. She also said Fermi aims to start moving crews and equipment onto the site by December 1. As of 8:43 a.m. ET on November 16, Fermi had issued no release or SEC filing confirming the money arrived.

Fermi says the customer's identity is confidential. The Financial Times reported on November 13, citing people familiar with the matter, that the customer is Amazon; Fermi declined to comment, the paper said. Fermi's own filings tell of a 2025 tenant deal that ended before any money was drawn, covered below.

Piece of the dealAmountStatus in the 10-Q
Letter of intent for powered landAbout 600 MWSigned November 10, 2026, non-binding
Prepayment agreement$200 millionSigned
Early construction and site development agreement$15 millionSigned
Structural steel and building materials saleAbout $90 millionBeing finalized
Long-term leaseNot disclosedBeing negotiated

Source: Fermi Form 10-Q for the quarter ended September 30, 2026, and the November 12, 2026 release.

How Fermi stock moved after the announcement

The stock rose on the day of the announcement and the day after, with the bigger gain on November 13. It still closed far below its $21 IPO price.

Fermi stock closed at $2.61 on November 13, according to StockTitan price data. The larger daily gain, 26.7%, came that day, the day the Financial Times report on the customer, described above, came out. The stock had already risen 17.5% on November 11, before Fermi issued any release or SEC filing about the deal. The October 2025 IPO price was $21.00 a share, the 10-Q says.

DayOfficial closeChange from the day before
November 10, 2026$1.54-7.2%
November 11, 2026$1.81+17.5%
November 12, 2026$2.06+13.8%
November 13, 2026$2.61+26.7%

Source: StockTitan price data, official closes, read November 16, 2026. The November 9 close was $1.66.

What would Fermi's 600 MW cost to build?

At the market costs in Fermi's own slides, land with power ready for this customer would cost billions of dollars to build. The prepayment is a small slice of that.

The deal is for what Fermi calls Powered Land+. Fermi brings the power, water, fiber and site, and the customer builds its own data center. In what its investor presentation calls a turnkey deal, Fermi would build everything, the data center included.

The slides put the market cost of powered land at about a third of the turnkey cost per megawatt. CFO Rob Masson said on the call that this deal will be "within that range." At that range, 600 megawatts would cost about $2.3 billion to $3.1 billion to build. In his prepared remarks, Masson said the ranges come from past market deals and are "not necessarily indicative of where the market is today." The 10-Q expects spending of a similar size in the next 12 months, if leases are signed.

OfferWho builds the data centerMarket cost to build, per MW of power
Powered Land+The customer$3.9 million to $5.1 million
Powered ShellFermi builds the shell, the customer fits it out$5.1 million to $6.6 million
TurnkeyFermi$12.1 million to $15.0 million

Source: Fermi investor presentation, Q3 2026, pages 11 and 13. The 10-Q estimates about $2 billion to $3 billion of capital spending in the next 12 months, subject to signed leases.

How much cash and debt does Fermi have?

Fermi has no revenue yet. It ended September with $315.5 million of cash, part of it set aside for lenders, against $958.4 million of debt.

The net loss was $141.6 million in the quarter to September 30, 2026. General and administrative costs rose almost fourfold from a year earlier. The year-earlier loss was bigger mainly because of $309.0 million of other expense, which the 10-Q says primarily reflects non-cash charges.

The 10-Q says cash on hand is "not sufficient" for a year of planned spending, which raised "substantial doubt" about Fermi's ability to keep going. Management concluded its plans "alleviate the substantial doubt," while the filing adds there is "no guarantee" the plans will work. The filing says Fermi will time its spending to signed tenant deals and the loans that come with them. It also counts on its cash and on equipment loans it has not yet drawn.

MeasureQ3 2026Q3 2025
RevenueNoneNone
Net loss$141.6 million$346.8 million
Loss per share$0.22$0.84
General and administrative expense$142.2 million, including $65.8 million of stock pay$37.8 million
Other expense, net$1.6 million$309.0 million
Cash, cash equivalents and restricted cash$315.5 million ($29.2 million restricted)$183.0 million (September 30, 2025)
Debt, net of issuance costs and discounts$958.4 million$109.8 million (December 31, 2025)
Property, plant and equipment, net$1.67 billion, all land and construction in progress$935.3 million (December 31, 2025)

Source: Fermi Q3 2026 release and Form 10-Q. Restricted cash is held for a lender and a letter of credit. Construction in progress is equipment and site work not yet in use.

What deadlines does Fermi face before first power?

Fermi builds on land leased from Texas Tech. To start building data centers it needs a signed tenant lease of at least 200 megawatts by December 31, or Texas Tech may end the land lease. Fermi is asking for more time.

The campus sits on land Fermi rents for 99 years from the Texas Tech University System. Under that lease, Fermi must get a "notice to proceed" from Texas Tech by December 31, 2026 before it builds data centers. That notice requires a signed lease with a first tenant for at least 200 megawatts. If the notice does not come, Texas Tech may end the land lease.

The 10-Q says that condition "has not been satisfied." It adds: "We are in discussions with TTU regarding an extension of the deadline, but there can be no assurance that TTU will agree to an extension on acceptable terms or at all." The Q2 10-Q did not carry either sentence. In the release, Chancellor Brandon Creighton said Texas Tech "remains firmly committed to the success of Project Matador." That backs the project in general terms, and neither the release nor the 10-Q reports an agreed extension. On meeting Texas Tech's requirements, Bofa said on the call, "we fully anticipate being able to do that."

Lenders set dates too. A Keystone equipment loan, with $91.5 million owed on September 30, must be repaid early if no approved customer agreement arrives by December 31. Under the MUFG turbine loan, Fermi must close financing for at least 400 megawatts by February 10, 2027. Otherwise it is an event of default, which lets lenders demand repayment.

Two supply contracts need payment security from Fermi, which the 10-Q calls credit support. For gas it is due when Fermi elects to start deliveries or by December 31, whichever comes first. For grid power it is due before service starts. Hillcore is a partner that plans to build up to 2.6 GW of power on the site. It must sign final documents with Fermi by December 18, unless both sides extend that date. Bofa said the target is initial power in late Q2 or early Q3 2027.

The dates between Fermi's letter of intent and first power. Fermi faces several deadlines through December 31, 2026, then a February 10, 2027 financing deadline and a mid-2027 target for initial power.
The dates between Fermi's letter of intent and first power Fermi faces several deadlines through December 31, 2026, then a February 10, 2027 financing deadline and a mid-2027 target for initial power. Figures from Fermi Form 10-Q for the quarter ended September 30, 2026, as of November 12, 2026; Fermi Q3 2026 prepared remarks, as of November 12, 2026; Fermi Q3 2026 earnings call webcast, as of November 12, 2026.
Show the data
DateEvent
2026-11-13The $200 million wire was due, Fermi said on its call; receipt not confirmed by November 16
2026-12-01Target to start mobilizing on the site
2026-12-18Deadline for final documents with Hillcore, the power partner
2026-12-31Texas Tech notice to proceed due; it needs a signed lease of at least 200 MW
2026-12-31Keystone equipment loan must be repaid early without an approved customer agreement
2027-02-10Financing for at least 400 MW due, or the MUFG turbine loan is in default
Late Q2 or early Q3 2027Fermi's target for initial power to the customer

What happened to Fermi's earlier tenant deals?

Two earlier tenant arrangements ended. The signed TensorWave lease never took effect and ended on November 10, and in 2025 a tenant ended a $150 million advance before any money was drawn.

In August, Fermi signed a 15-year lease with TensorWave for 222 megawatts, worth about $6.5 billion in rent, according to the August 10 release. The lease only counted once conditions were met, including guarantees and project financing. In October, AMD agreed to stand behind it with a credit support agreement, a promise that helps a project raise loans.

The October 31 closing date "passed without extension," Fermi said in a November 3 statement. At that point both sides still said they were committed. The unmet conditions included "securing project-level financing sufficient to fund construction." The 10-Q says the lease was terminated on November 10 "in accordance with its terms." The November 12 release says the AMD credit support agreement was also terminated.

Fermi has not said which side ended it. Asked on the call, Chairman Marius Haas said the company would not give details of the talks. He said he would choose "a direct large hyperscaler deal" over "a complex 4 party deal" any day. McIntire's prepared remarks describe the TensorWave lease as one "involving multiple parties and requiring the support of third-party credit." The TensorWave lease needed a guarantor and project lenders on board before it counted, and the financing was still missing at the October 31 closing date.

The move to powered land was planned. In an October 21 letter, McIntire said Fermi was "prioritizing powered land deals" for its 2027 capacity and wanted customer money to come in earlier. In his prepared remarks for the call, he called the new deal "a simpler deal providing power to a single customer with less to finance." That means the customer pays for its own data center, so Fermi has less to build and borrow for.

TensorWave, August 2026Hyperscaler, November 2026
DocumentSigned lease with closing conditionsNon-binding letter of intent
Power222 MW in phase oneAbout 600 MW
Who builds the data centerFermi (turnkey)The customer (powered land)
Money disclosedAbout $6.5 billion of rent over 15 years$200 million prepayment, rent not disclosed
Credit behind itAMD credit support, terminated per the November 12 releaseCustomer described as investment-grade; no lease or guaranty signed
StatusEnded November 10, 2026Lease still being negotiated
Fermi's TensorWave lease and its new hyperscaler deal The new deal covers more power and leaves the buildings to the customer, and it is a letter of intent where TensorWave had a signed lease. Figures from Fermi release, Binding Lease Agreement with TensorWave, August 10, 2026, as of August 10, 2026; Fermi Form 10-Q for the quarter ended September 30, 2026, as of November 12, 2026; Fermi release, New Agreements with Investment-Grade Hyperscaler, November 12, 2026, as of November 12, 2026; Fermi Q3 2026 prepared remarks, as of November 12, 2026.

In 2025, an earlier tenant also agreed to pay for early work. Then it ended that payment deal. Fermi's 2025 annual report, its 10-K, tells the story. In September 2025, Fermi signed a non-binding letter of intent with an "investment grade-rated prospective tenant." Two months later that tenant agreed to advance up to $150 million to pay for early construction, and Fermi announced it on November 6. On December 11, 2025, the tenant ended that advance agreement, and "no funds were drawn," the 10-K says. Fermi said it kept negotiating with that tenant under the letter of intent, which it called a "commercial framework for negotiations."

Both deals paired a letter of intent with money for early work. Fermi has not said whether the two tenants are the same company. The Financial Times reported on November 13 that Fermi's talks with Amazon collapsed in December 2025, the month the advance ended.

Fermi's tenant deals since September 2025. The 2025 advance agreement ended with no funds drawn, and Fermi signed the new letter of intent on November 10, 2026, the day the TensorWave lease ended.
Fermi's tenant deals since September 2025 The 2025 advance agreement ended with no funds drawn, and Fermi signed the new letter of intent on November 10, 2026, the day the TensorWave lease ended. Figures from Fermi Form 10-K for 2025, as of March 30, 2026; Fermi Form 10-Q for the quarter ended September 30, 2026, as of November 12, 2026.
Show the data
DateEvent
2025-09Non-binding letter of intent with an investment-grade prospective tenant
2025-11-03That tenant agrees to advance up to $150 million for early construction
2025-12-11The tenant ends the advance agreement; no funds were drawn
2026-08-09Signed lease with TensorWave for 222 MW, subject to closing conditions
2026-10-31The TensorWave closing date passes without extension
2026-11-10TensorWave lease ends; letter of intent for 600 MW with a hyperscaler

Why is Fermi's co-founder pushing for a sale?

Co-founder Toby Neugebauer wants Fermi sold while it closes a tenant deal. In April, Fermi said a sale was not in the best interest of its work on the campus, and the two sides are also in court.

Co-founder Toby Neugebauer, who calls himself the largest shareholder, put out his own statement on November 5. He said: "Fermi must put the company up for sale now, while it closes a tenant deal." His reason, in the same statement, is that Fermi "needs a partner with a lower cost of capital, construction expertise and a customer." In plain terms, he wants a buyer that can borrow more cheaply and knows how to build. Fermi had said in an April 21 update that "a sale is not in the best interest of its continued momentum on Project Matador."

He also said: "The board has still not announced that critical closing conditions such as secured financing have been met." That line comes in a passage about the TensorWave lease, which ended five days later.

The two sides also disagree over a board seat. Under a 2025 agreement, investors tied to Neugebauer promised to vote for certain board nominees, Fermi's November 4 filing says. Fermi says it believes they voted against director Rick Perry instead, and that by its count he would have been elected had they voted as agreed. Through counsel, they disputed that the agreement required it. Neugebauer's lawsuit against the company and some of its directors, Perry among them, has a hearing on the defendants' motion to dismiss on November 19, the 10-Q says.

The deadlines, the cash and the sale fight all come back to one missing document, a signed lease. The 10-Q says Fermi's cash is not enough for a year of planned spending, and Texas Tech needs a signed tenant by December 31. Fermi's two earlier tenant arrangements ended before a lease took effect or an advance was drawn. The new deal adds a $200 million prepayment agreement, and the lease that would set the rent is still being negotiated.

What to watch

  • Whether the $200 million arrived: a Fermi release or an 8-K, the short SEC filing for major news.
  • Whether a definitive lease with the hyperscaler is signed: a Fermi release or 8-K.
  • Any extension of the Texas Tech notice to proceed: a Fermi release or 8-K, by December 31, 2026.
  • The Keystone equipment loan: repaid early unless an approved customer agreement reaches the lender by December 31, 2026, the 10-Q says; to be reported in a Fermi release, an 8-K or the 2026 10-K.
  • Credit support for the gas supply contract: due when Fermi elects to start deliveries or by December 31, 2026, whichever comes first, the 10-Q says; to be reported in a Fermi release, an 8-K or the 2026 10-K.
  • Final documents with Hillcore, which plans to build up to 2.6 GW of power on the site: due December 18, 2026 unless both sides extend it, to be reported in a Fermi release or 8-K.
  • Financing for at least 400 MW: due February 10, 2027 under the MUFG turbine loan, to be reported in a release or 8-K.
  • The hearing on the motion to dismiss Neugebauer's lawsuit on November 19, 2026: the outcome in an 8-K or the 2026 10-K.

Our numbers

These figures are our calculations from the sources linked in this article. The build cost is a total cost at the market range in Fermi's slides, not what is left to spend.

  • Cost to build 600 MW, about $2.3 billion to $3.1 billion: 600 megawatts times the $3.9 million to $5.1 million per megawatt the CFO said this deal falls within.
  • Prepayment, about 7% to 9% of that cost: $200 million divided by $3.06 billion and by $2.34 billion.
  • About 12 times the prepayment: the $2.34 billion low end divided by $200 million.
  • General and administrative costs up almost fourfold: $142.2 million in the third quarter of 2026 against $37.8 million a year earlier.
  • Rise of 44% on the announcement day and the day after: the November 13 close of $2.61 against the November 11 close of $1.81.

Frequently asked questions

Fermi stock rose on November 12, 2026, the day it announced the hyperscaler deal, and again on November 13. That day, the Financial Times reported, citing people familiar with the matter, that the customer is Amazon; Fermi has not named it. The stock closed at $2.61 on November 13, up from $1.81 on November 11, according to StockTitan official closing prices.

Fermi says the customer's identity is confidential. The Financial Times reported on November 13, 2026, citing people familiar with the matter, that it is Amazon. Fermi declined to comment, the paper said.

Not yet. The 10-Q calls the deal a non-binding letter of intent signed on November 10, 2026. The $200 million prepayment and $15 million site agreements are signed, and the long-term lease is still being negotiated.

Fermi said on its November 12 call that the agreement required the wire by November 13. As of the morning of November 16, it had issued no release or SEC filing confirming the money arrived.

Fermi says it is targeting initial power in late Q2 or early Q3 of 2027. The lease that would set the delivery terms is still being negotiated.

Fermi's releases are on its StockTitan news page, and its figures are on the FRMI financials page.

Sources

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

About Stock Titan Editorial Team

The Stock Titan Editorial Team is a group of market analysts and data scientists who specialize in transforming complex financial data into actionable insights.

Our team continuously monitors and integrates data from official sources including SEC filings, stock exchanges, and verified financial data providers directly into the StockTitan platform.

We maintain a neutral, unbiased approach to market analysis. Our goal is to present verified data clearly and accurately, helping investors of all experience levels understand market trends, sector performance, and individual stock movements.

Every article undergoes multi-source verification to ensure data accuracy and reliability.