FLORIDA CANYON FEASIBILITY STUDY DELIVERS SUBSTANTIAL INCREASE IN MINERAL RESERVE, GOLD PRODUCTION OVER AN 8-YEAR MINE LIFE AND US$0.8 BILLION IN AFTER-TAX FREE CASH FLOW; PROVIDES OPERATIONAL UPDATE
Rhea-AI Summary
Integra Resources (NYSE American: ITRG) released a new Florida Canyon feasibility study showing a 74% increase in Proven and Probable mineral reserves to 1.19 Moz gold and an 8-year operating mine life.
The plan outlines average annual gold sales of ~82 Koz, LOM site-level AISC of $2,331/oz, after-tax NPV5% of $600.6M, and total after-tax free cash flow of ~$0.8B. 2026 AISC guidance rises to $3,300–$3,500/oz while production guidance of 70–75 Koz is maintained.
AI-generated analysis. Not financial advice.
Positive
- Proven & Probable reserves increased 74% to 1.19 Moz Au
- Average annual gold sold rises to 81.8 Koz over 8 mining years
- After-tax NPV5% of $600.6M at base case gold prices
- Total LOM after-tax free cash flow of $769.5M
- LOM site-level AISC projected at $2,331/oz net of silver by-product
- Growth capital of $91.8M funded from existing cash flow
Negative
- 2026 site-level AISC guidance increased to $3,300–$3,500/oz
- Total sustaining capital and capitalized stripping of $216.7M
- Reclamation costs estimated at $40.2M over life-of-mine
Key Figures
Peers on Argus
Sector peers show mixed moves, with some gold names down and others up, and only one peer appearing in the momentum scanner. This pattern points to stock-specific factors rather than a broad sector rotation.
Historical Context
| Date | Event | Sentiment | Move | Catalyst |
|---|---|---|---|---|
| Jun 02 | Engineering appointment | Positive | -1.1% | Ausenco appointed to lead detailed engineering work at DeLamar project. |
| May 29 | Permitting milestone | Positive | +1.9% | BLM Notice of Intent starts NEPA review and EIS for DeLamar. |
| May 26 | Leadership additions | Positive | +2.9% | Appointment of three senior mining executives and related equity incentives. |
| May 13 | Tribal equity agreement | Positive | -1.8% | Equity agreement with Shoshone-Paiute Tribes linked to DeLamar project. |
| May 11 | Q1 2026 earnings | Positive | -1.7% | Stronger Q1 results with higher earnings and cash, but higher site costs. |
Recent positive corporate and permitting updates have produced mixed price reactions, with slightly more divergences than alignments.
Regulatory & Risk Context
Reported short interest appears relatively low, suggesting limited short-squeeze potential and a lower likelihood of extreme volatility driven purely by short covering.
Market Pulse Summary
This announcement outlines a materially larger, longer-life Florida Canyon mine generating projected after-tax free cash flow of about $0.8B. Investors may watch execution on cost reductions, the revised AISC path, and how this cash flow supports DeLamar and Nevada North development.
Key Terms
npv financial
all-in sustaining costs financial
heap-leach technical
strip ratio technical
reclamation regulatory
AI-generated analysis. Not financial advice.
TSXV: ITR; NYSE American: ITRG
www.integraresources.com
(All amounts in
2026 Florida Canyon Technical Report Highlights:
- Robust gold project economics: After-tax net present value
5% ("NPV") of M using base case metal prices3; After-tax NPV of$601 ~ M using spot metal prices4.$723 - Significant increase in Proven and Probable Mineral Reserve: Integra replaced gold ("Au") mined at Florida Canyon over the last two years and increased the Proven and Probable Mineral Reserve ("P&P") at Florida Canyon by
74% . The P&P increased from 685 Koz Au in the 2024 Mineral Reserve Statement5 to 1.19 million ounces ("Moz") Au in the 2026 Mineral Reserve Estimate, a 506 Koz Au increase in P&P6. - Substantial increase in oxide Mineral Resources: The Mineral Resource Estimate ("MRE") increased
128% in the oxide Measured and Indicated ("M&I") category and57% in the oxide Inferred ("Inf.") category, including a MRE on the Standard Mine located south of Florida Canyon. - Enhanced gold production profile and extended mine life: The annual production profile in the Technical Report has increased from 70 Koz Au to an average of 82 Koz Au over an 8-year operating mine life (inclusive of 2026), a 12 Koz Au increase in average annual production with operating mine life extending from 2030 to 2033 (not including 2 years of gold production from residual leaching starting in 2033).
- Strong free cash flow2 supports growth: Florida Canyon is expected to generate approximately
B in LOM after-tax free cash flow and average annual after-tax free cash flow of$0.8 M, supporting growth capital investments at Florida Canyon to increase mine life and annual production profile.$90 - Lower LOM All-in Sustaining Costs2 and Revised 2026 Cost Guidance: Site-level all-in sustaining costs ("AISC") are expected to average approximately
/oz over LOM. Due to the increase in tonnes mined, stacked and processed this year, along with inflationary pressures on diesel fuel and explosives, among others, the Company is revising its 2026 site-level AISC guidance from$2,331 to$2,750 to$2,950 to$3,300 while re-confirming and maintaining production guidance in 2026 of 70 Koz to 75 Koz Au. The updated mine plan in the Technical Report establishes a clear path toward lower long-term costs and higher annual gold production in future years.$3,500 - Optimized mine plan that unlocks value: Informed by two years of operating experience and a comprehensive review of historical performance and costs, the Technical Report delivers a more stable, predictable and executable mine plan for Florida Canyon. All production growth and planned heap leach pad expansion contemplated in the Technical Report can be supported within the existing Mine Plan of Operations.
- Cash flow to support project pipeline: Cash flow from Florida Canyon will support the advancement of the DeLamar Project through permitting, with the Final Environmental Impact Statement and Record of Decision expected in H2 2027, and the Company's Nevada North project. Creating a path for the Company to become a multi-asset, mid-tier precious metals producer in
the United States . - Multiple opportunities identified to increase LOM production and gold resource: The Company is evaluating several opportunities to further increase gold recoveries, production and operating efficiency at Florida Canyon, including additional crushing capacity, haul road optimization, and improved truck routing. In addition, a 42,500 m exploration program is underway to identify potential mineral resource growth adjacent to the existing operation and across the Project. These opportunities are conceptual and not included in the current Mineral Reserve Estimate or economic analysis.
|
George Salamis, President, CEO and Director of Integra commented: "Since acquiring Florida Canyon in late 2024, the team has developed a deep understanding of the operation and systematically addressed the opportunities identified during the acquisition. Through disciplined investment, exploration drilling, operational improvements and detailed mine planning, Florida Canyon has been transformed into a fundamentally stronger asset with higher gold production, lower future costs, a longer mine life and a substantially larger mineral reserve base. Florida Canyon is now expected to generate approximately
Mr. Salamis added: "Based on the updated mine plan, we are intentionally investing to drive future growth. The higher costs expected in 2026 are short-term in nature and are tied to increased mining rates at the mine this year. As Florida Canyon transitions to a more stable operation, we expect to benefit from lower costs and enhanced economics."
"The updated Mineral Resource Estimate demonstrates the significant value created at Florida Canyon since its acquisition. Despite two years of mining depletion, the Company has increased Proven and Probable Mineral Reserves by
Integra will host a conference call and webcast to discuss the Technical Report on June 26, 2026, at 8am Pacific Time / 11am Eastern Time, featuring a presentation from the senior management team and a live Q&A session. A recording will be available on Integra's corporate website at www.integraresources.com. To register for the webcast, please use the following link (call details are listed below):
https://events.q4inc.com/attendee/752689074
Technical Report Summary
The Technical Report reflects the evolution of Florida Canyon from a project with limited mine life and flat annual gold production into a project with an increased production profile and an extended mine life. The enhanced mine plan utilizes existing infrastructure and the current crushing circuit to support an 8-year operating mine life with a LOM site-level AISC of
The mine plan outlined in the Technical Report represents a material transformation of Florida Canyon. To realize this growth, Integra plans to use its existing cash flow to invest approximately
The Company retained Global Resource Engineering ("GRE") as lead consultants, along with other engineering consultants, to complete the Technical Report and prepare the Technical Report in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). The Technical Report is derived from the updated mineral reserve estimate effective May 31, 2026. The effective date of the Technical Report is June 25, 2026, and the Technical Report prepared in accordance with NI 43-101 will be filed on the Corporation's website and under its SEDAR+ profile within 45 days of this news release.
Table 1: Florida Canyon Technical Report Highlights1
Mining | |
Total Tonnage Mined (K tonnes ("Kt")) | 211,199 |
Total Ore Mined (Kt) | 116,935 |
Strip Ratio (Waste: Ore) | 0.81 |
Mine Life (Mining Yrs) | 8.0 |
Contained Gold (Koz Au) | 1,156 |
Production | |
LOM Average Gold Recovery (%) | 56.7 % |
LOM Gold Recoverable Placed (Koz Au) | 656 |
LOM Gold Sold (Koz Au) | 685 |
Average Annual Gold Sold (Koz Au) - Mining Yrs | 81.8 |
Costs per Tonne (Mining Years 2026 to 2033) | |
Mining Costs ($/t mined) | |
Mining Costs ($/t placed) | |
Crushing & Processing Costs ($/t placed) | |
G&A Costs ($/t placed) | |
Total Site Operating Cost ($/t placed) | |
LOM Site-Level Cash Costs ($/oz Au) | |
LOM Cash Cost, net-of-silver by-product | |
LOM Site-Level AISC, net-of-silver by-product 2 | |
LOM Capital Expenditure ($ M) | |
Sustaining Capital | |
Capitalized Stripping | |
Development Drilling | |
Financing Leases - Sustaining | |
Growth Capital | |
Financing Leases - Growth Capital | |
Salvage Value | ( |
Reclamation Cost | |
Bonding Cash Collateral Return | ( |
Gold Price Assumptions ($/oz) | |
Gold Price 2026 | |
Gold Price 2027 | |
Gold Price 2028 | |
Gold Price 2029 | |
Gold Price 2030 to 2035 | |
Project Economics ($ M) | |
After-Tax NPV5% | |
Average Annual Net Free Cash Flow (Mining Yrs) | |
Total Net Free Cash Flow |
(1) | Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table. |
(2) | Excluding closure costs. |
Figure 1: Florida Canyon Annual Production and Operating Cost Profile1

(1) | Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure. |
Figure 2: Florida Canyon LOM After-tax Free Cash Flow1

(1) | Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure. |
Table 2: Florida Canyon After-Tax NPV and LOM After-tax Net Cash Flow ("CF") Sensitivity to Gold Price1
Gold Price Estimate ($/oz) | ||||||||
Change in | After-Tax | After-Tax | 2026 | 2027 | 2028 | 2029 | 2030 to | |
(25 %) | ||||||||
(20 %) | ||||||||
(15 %) | ||||||||
(10 %) | ||||||||
(5 %) | ||||||||
Base | ||||||||
5 % | ||||||||
10 % | ||||||||
15 % | ||||||||
20 % | ||||||||
25 % | ||||||||
(1) | Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table. |
Property Description, Location and Access
Florida Canyon is located 125 miles (~201 kilometers) east of
Commercial mining operations at Florida Canyon began in 1986 using conventional open-pit mining and heap-leach processing methods. The mine operated continuously through 2011 before entering a period of intermittent production until 2015. Florida Canyon was subsequently restarted in mid-2016 following new investment and operational improvements and has remained in operation since. Since the restart, Florida Canyon has undergone modernization and expansion efforts, including upgrades to equipment, heap-leach infrastructure, permitting expansions, and long-term mine planning initiatives.
Figure 3: Florida Canyon Location Map

Updated Mineral Resource Estimate
Mineral resources were re-estimated from the resource model released in 2024 and include historic waste rock stockpiles whose grade exceeds current cut-off grades for the Project. The updated Mineral Resource Estimate ("MRE") incorporates a revised geological interpretation that includes structural domains and shear controls. These changes improved grade continuity within mineralized zones and reduced dilution associated with previous estimation domains. The revised geological model includes infill, confirmatory and exploration drilling completed since 2024, together with historical drilling completed by previous operators. In total, the MRE is based on 5,454 drill holes totaling 665,423 meters ("m"). The updated MRE for Florida Canyon was modeled following industry-standard and Canadian Institute of Mining, Metallurgy & Petroleum ("CIM") compliant protocols.
Key steps included:
- Verification of the drill hole database;
- Generation of drill hole intercepts for each shear zone;
- Statistical analysis of assay data;
- Compositing of assay intervals;
- Capping of outlier composite values;
- Geostatistical analysis, including variography;
- Construction of the block model and grade interpolation;
- Classification of the Mineral Resources;
- Validation of the block model;
- Calculation of cut-off grades;
- Pit optimization;
- Confirmation that reported blocks meet the RPEEE criteria; and
- Preparation of the Mineral Resource statement.
The MRE is constrained within an optimized pit shell generated using updated metal prices, metallurgical recoveries, operating costs and slope assumptions consistent with reasonable prospects for eventual economic extraction.
Table 3: Florida Canyon and Standard Mine MRE
Mineral Resources | Measured | Indicated | Measured & Indicated | Inferred | |||||||||
GOLD (Au) | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | |
Florida Canyon Mine | Oxide | - | - | - | 171,842 | 0.31 | 1,706 | 171,842 | 0.31 | 1,706 | 53,312 | 0.25 | 433 |
Sulphide | - | - | - | - | - | - | - | - | - | 104,004 | 0.86 | 2,876 | |
Standard Mine | Oxide | - | - | - | - | - | - | - | - | - | 8,532 | 0.49 | 135 |
Sulphide | - | - | - | - | - | - | - | - | - | 30 | 1.47 | 1 | |
TOTAL | Mixed | - | - | - | 171,842 | 0.31 | 1,706 | 171,842 | 0.31 | 1,706 | 165,879 | 0.65 | 3,446 |
Mineral Resources | Measured | Indicated | Measured & Indicated | Inferred | |||||||||
SILVER (Ag) | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | |
Florida Canyon Mine | Oxide | - | - | - | - | - | - | - | - | - | - | - | - |
Sulphide | - | - | - | - | - | - | - | - | - | - | - | - | |
Standard Mine | Oxide | - | - | - | - | - | - | - | - | - | - | - | - |
Sulphide | - | - | - | - | - | - | - | - | - | - | - | - | |
TOTAL | Mixed | - | - | - | - | - | - | - | - | - | - | - | - |
Notes for Florida Canyon Mineral Resource Estimate
Notes for Standard Mine Mineral Resource Estimate
|
Mineral Reserve Estimate
The Mineral Reserves were estimated by applying detailed mine design, production schedules, operating costs, metallurgical recoveries and economic criteria to the Measured and Indicated Mineral Resources. The engineered open pits were constrained with cut-off grades that reflect updated metal prices, metallurgical recoveries and known operating costs. Based on updated geotechnical assessment and operating experience, inter-ramp slope angles in selected areas were increased from 38 degrees to 42 degrees, resulting in additional economic pit inventory available for resource conversion. Along with confirmatory and exploration drilling, refined engineering and the inclusion of historic waste rock stockpiles, the updated mineral reserve estimate fully replaces mining depletion since the acquisition of Florida Canyon and supports an extension of active mining through 2033.
Table 4: Florida Canyon Mineral Reserve
Mineral Reserves | Proven | Probable | Proven & Probable | |||||||
GOLD (Au) | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | |
Florida Canyon Mine | Oxide | - | - | - | 118,471 | 0.31 | 1,191 | 118,471 | 0.31 | 1,191 |
TOTAL | Oxide | - | - | - | 118,471 | 0.31 | 1,191 | 118,471 | 0.31 | 1,191 |
Mineral Reserves | Proven | Probable | Proven & Probable | |||||||
SILVER (Ag) | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | |
Florida Canyon Mine | Oxide | - | - | - | - | - | - | - | - | - |
TOTAL | Mixed | - | - | - | - | - | - | - | - | - |
Notes to Mineral Reserves
|
Production Profile
The Technical Report outlines 8-years of active mining and ore placement, followed by approximately two years of residual gold recovery from heap leaching, extending the operating mine life from 2030 in the 2024 Technical Report to 2033 in the updated Technical Report. The 8-years of active mining at Florida Canyon are followed by 2-years of residual leaching. The updated mine plan shows an increase in annual production from 70 Koz Au in the 2024 Technical Report to 82 Koz in the updated Technical Report, which represents an annual increase of 12 Koz per year.
The Company anticipated 2026 would be a cost intensive transition year as it addressed a deferred stripping campaign in the Central pit and undertook fleet replacement and upgrades. The Technical Report reflects these investments and outlines a more stable and sustainable operating plan, reducing production variability and supporting a more consistent and predictable production profile over an increased LOM.
Mining
Mining is currently conducted as a conventional open-pit operation using truck-and-loader methods. The mine plan schedules 22.0 to 28.1 million tonnes ("Mt") of total material movement per year ("/yr"), which is consistent with historical mining performance and fleet capability, with an average of 14.6 Mt/yr of ore transferred to the heap leach pad. Approximately, 7.1 Mt/yr of ore is scheduled for crushing to 2.5 inches, consistent with capacity and historical operating performance of the existing crushing circuit. Crushed material will be blended with approximately 4.5 Mt to 9.3 Mt/yr of run-of-mine ("ROM") material during the 10-year LOM (8-years of active mining). The mine plan schedules 211.2 Mt of total material movement over the 8-year active mine life, including 116.9 Mt of ore with an average grade of 0.31 g/t Au, resulting in 656 Koz Au recoverable placed on the heap leach pad over LOM. The LOM average strip ratio of 0.81 waste tonnes per ore tonne is consistent with historical operating performance and supports the economic extraction of the reserve inventory.
The increased mine life and enhanced production profile are primarily driven by the expansion of the Central Pit and Radio Tower Pit. Mining is planned in the Central Pit from 2026 through 2028, followed by the Radio Tower Pit from 2028 through 2030. Mining from 2030 through 2033 will occur at the Jasperoid Pit and through the processing of historic waste rock stockpiles.
Mining assumptions were developed using recent operating performance, equipment productivity analyses, labour requirements, maintenance planning and detailed production scheduling. The Technical Report provides a mine plan that can be executed effectively and deliver consistent production. Through an improved geological model and detailed forward planning, the Company expects to improve operation reliability and preserve flexibility that supports multiple ore sources to unlock additional value from the Mineral Reserve base.

Figure 4: Florida Canyon Mining Profile
Processing and Recovery
Crushed ore at Florida Canyon passes through two stages of open circuit crushing to a final crush size of
Crushed ore, representing
Heap leach pad expansions at Florida Canyon are planned within the existing Mine Plan of Operations at the Project. The heap leach pad expansion will take place over four total phases, with two phases completed between 2026 and 2028 and two phases completed in 2030 and 2031.

Figure 5: Florida Canyon Project Ounces Recoverable Placed Crushed vs. ROM
Table 5: Florida Canyon Project Mining & Processing Summary
ROM | Crushing | Total | |
Mining | |||
Total Ore Mined (Kt) | 61,648 | 55,287 | 116,935 |
Total Waste (Kt) | 94,264 | ||
Total Mined (Kt) | 211,199 | ||
Strip Ratio (Waste: Ore) | 0.81 | ||
Grade & Contained Metals | |||
Average Gold Grade (g/t Au) | 0.21 | 0.42 | 0.31 |
Contained Gold (Koz Au) | 410 | 746 | 1,156 |
Production | |||
LOM Average Gold Recovery (%) | 44.8 % | 63.3 % | 56.7 % |
LOM Gold Recoverable Placed (Koz Au) | 184 | 473 | 656 |
Ounces on the Heap Leach Pad as of Dec 31, 2025 (Koz Au) | 29 | ||
LOM Gold Sold (Koz Au) | 685 | ||
Operating Costs
The Technical Report provides a comprehensive assessment of Florida Canyon with a mine plan that reflects current and future operating realities. The Technical Report includes nearly two years of detailed review and analysis by Integra of operating costs, maintenance requirements, labour assumptions and long-term mine planning. The Company completed a bottom-up evaluation of all major cost categories at the Project, incorporating historical operating performance, budget variances and previously underrepresented costs to develop a more comprehensive and realistic cost structure. Assumptions have been updated to reflect current market conditions, including labour costs consistent with
The Technical Report also incorporates a fully integrated mine plan to support the expanded reserve base, including permitting costs and engineered plans for future heap leach pads. Equipment assumptions have been updated to reflect a more proactive maintenance strategy, integrating both planned component replacement programs and expected unplanned downtime based on historical operating performance. The Technical Report also includes investments in fleet modernization, including the transition to larger haul trucks and other equipment upgrades designed to improve productivity, increase reliability and reduce unit mining costs over time. Together, these investments support a more stable and predictable operating profile while providing the infrastructure and equipment capacity required to execute the mine plan.
Table 6: Florida Canyon Operating Cost Breakdown
Mining Years (2026 to 2033) | $ Per Tonne | |||
Operating Costs 2026 to 2033 | Mined | Placed | ||
Mining | ||||
Crushing and Conveying / Processing | ||||
G&A | ||||
Total Site Costs | ||||
Figure 6: Florida Canyon Annual Operating Cost ("Opex") per Tonne Placed

Table 7: Florida Canyon LOM Cash Costs and Site-Level AISC1
Life Of Mine | $/oz Au | ||
Site-Level Cash Costs, AISC Breakdown | By-Product | ||
Mining | |||
Crushing and Conveying / Processing | |||
G&A | |||
Total Site Costs | |||
Transport & Refining | |||
Royalties | |||
Total Cash Costs | |||
Silver By-Product Credits | ( | ||
Total Cash Costs Net of Silver by-Product | |||
Sustaining Capital | |||
Site-Level All-in Sustaining Costs - Excluding Closure Costs | |||
Closure Costs Net of Residual Value | |||
Site-Level All-in Sustaining Costs – Including Closure Costs | |||
(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table. |
Capital Cost Estimates
The expanded production profile outlined in the Technical Report is expected to be funded from Florida Canyon's existing and future cash flow. The updated mine plan at Florida Canyon will be realized through growth capital investments of
Sustaining capital of approximately
Table 8: Florida Canyon Capital Cost Breakdown
Yr 2026 to | Yr 2036 to | Combined LOM | |
Sustaining Capital Costs | |||
Sustaining Capital | |||
Capitalized Stripping | |||
Development Drilling | |||
Lease Payments (Financing) - Sustaining | |||
Total Sustaining Capital & Stripping | |||
Other Capital | |||
Lease Payments (Financing) - Growth | |||
Growth Capital | |||
Residual Value 1 | ( | ( | |
Reclamation 2 | |||
Cash collateral return 3 | ( | ( | |
Total Other Capital | |||
TOTAL SUSTAINING CAPITAL & OTHER |
(1) | The residual value represents estimated salvage value of mobile mining equipment and process / crushing / conveying equipment. |
(2) | Reclamation costs include |
(3) | Current cash collateral is assumed released in final year, once the reclamation is completed. |
Next Steps and Opportunities
The Technical Report includes multiple opportunities for further additional Project optimization. These opportunities are conceptual in nature and not included in current Mineral Reserve Estimate or economic analysis.
- Near mine exploration: Exploration drilling completed in 2025 and 2026 contributed to a significant increase in mineral resources, demonstrating the potential for mineral resource growth next to existing infrastructure. In April 2026, Integra initiated a 42,500 m drill program at Florida Canyon to test underexplored extensions of known mineralization and evaluate targets along newly identified key structures that are known to control mineralization. Near mine drilling has the potential to increase mineral resources, mineral reserves, and production opportunities adjacent to Florida Canyon's existing mining and processing infrastructure.
- Property wide exploration: Limited exploration has been completed by previous operators on the wider Florida Canyon property, which encompasses approximately 84 square miles (135 square kilometers). During the 2026 exploration program, Integra will drill at the Standard Mine south of Florida Canyon to evaluate historical backfill, waste material, and previously identified gold targets that have not seen significant exploration work in years. In addition, the Company will conduct first-pass drilling on several greenfield targets generated through geological work, geophysical surveys, geochemical sampling, and AI-assisted mineral targeting.
- Crushing and recovery: The Company is evaluating the potential for additional crushing capacity at Florida Canyon to increase recovery and gold production in the future. As part of the assessment, detailed analysis will also focus on further optimizing crush size to accelerate gold recovery.
- Enhanced mine productivity: The Company is implementing fleet management and dispatch systems to optimize haul road performance and planning, potentially lowering unit mining costs and increasing material movement reliability and efficiency.
- Improved material routing: Refining cutoff grade strategies, stockpile management and ROM-to-crusher routing to maximize value capture from mined material and improve economic returns.
Guidance Update
The Company is revising its 2026 site-level AISC guidance at Florida Canyon. The adjustment to AISC is primarily attributed to an increase in the tonnes, mined, stacked and processed to support production, lower gold ounces sold during Q1 2026, increased royalties1 and excise taxes resulting from stronger-than-anticipated gold prices, and higher diesel fuel and explosive costs. The Company now expects 2026 site-level AISC guidance to increase from
(1) | Cost guidance calculated using average Au price of |
Florida Canyon Technical Report Conference Call & Webcast
Integra will host a conference call and webcast on Friday, June 26, 2026, at 11:00 AM Eastern Time / 8:00 AM Pacific Time, to discuss the Florida Canyon Technical Report. Details for the conference call and webcast are included below.
Dial-In Numbers / Webcast:
Conference ID: 5650865
Toll-Free: (800) 715-9871
Toll: +1 (646) 307-1963
Webcast: https://events.q4inc.com/attendee/752689074
About Integra
Integra is a growing precious metals producer in the Great Basin of the
ON BEHALF OF THE BOARD OF DIRECTORS
George Salamis
President, CEO and Director
CONTACT INFORMATION
Corporate Inquiries: ir@integraresources.com
Company website: www.integraresources.com
Office phone: 1 (604) 416-0576
Qualified Persons
The scientific and technical information contained in this news release has been reviewed and approved by James Frost, P.Eng., Director, Technical Services of Integra Resources Corp., who is a Qualified Person as defined by NI 43-101.
The Company retained Global Resource Engineering as lead consultants, along with other engineering consultants, to complete the Technical Report. The following independent Qualified Persons with associated firms have reviewed and approved this news release as defined by NI 43-101:
Antoine Teixeira de Carvalho, P.Geo. - BT Africa Mining Services
Dave Swanton, MSc, P. Geo, - Equity Exploration Consultants Ltd.
Hamad Samari, Ph.D, MMSA QP – Global Resource Engineering, Ltd.
Larry
Maxime Lamothe, P.E. - Alius Mine Consulting
Terre Lane, MMSA QP - Global Resource Engineering, Ltd.
Todd Harvey, Ph.D., SME Register Member – Global Resource Engineering, Ltd.
Data Verification
The Qualified Persons responsible for the Technical Report have verified the data for which they are accountable, including the sampling, analytical, and test data underlying the information disclosed in this news release. Geological, mine engineering and metallurgical reviews included, among other things, reviewing drill data and core logs, review of geotechnical and hydrological studies, environmental and community factors, the development of the life-of-mine plan, capital and operating costs, transportation, taxation and royalties, and review of existing metallurgical test work. In the opinion of the Qualified Persons, the data, assumptions, and parameters used in the sections of the Technical Report that they are responsible for preparing are sufficiently reliable for those purposes. The Technical Report, when filed, will contain more detailed information concerning individual Qualified Persons responsibilities, associated quality assurance and quality control, and other data verification matters, and the key assumptions, parameters and methods used by the Company.
Sampling and QA/QC Procedure
Thorough QA/QC protocols are followed on the Project, including insertion of duplicate, blank and standard samples in the assay stream for all drill holes. The samples are submitted directly to American Assay Labs in
Additional supporting details regarding the information in this news release, will be provided in the Technical Report which will be available on SEDAR+ under the Company's profile within 45 days of this news release, including all qualifications, assumptions and exclusions that relate to the Technical Report. The Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context.
Forward Looking Statements
Certain information set forth in this news release contains "forward‐looking statements" and "forward‐looking information" within the meaning of applicable Canadian securities legislation and in applicable
Investors are cautioned not to put undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date of this news release and, accordingly, are subject to change after such date. The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws. Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed online under the Company's profile on SEDAR+ at www.sedarplus.ca.
Cautionary Note Regarding Non-GAAP Financial Measures
Alternative performance measures in this news release such as "cash cost", "AISC", "free cash flow" and "sustaining capital costs" are furnished to provide additional information. These non-GAAP performance measures are included in this news release because these statistics are used as key performance measures that management uses to monitor and assess performance of Florida Canyon, and to plan and assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a standardized meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with IFRS.
Cash Costs
Cash costs include site operating costs (mining, processing, site G&A), refinery costs and royalties, but excludes head office G&A and exploration expenses. While there is no standardized meaning of the measure across the industry, the Company believes that this measure is useful to external users in assessing operating performance.
Site-Level All-In Sustaining Cost
Site-level AISC includes cash costs and sustaining capital, but excludes head office G&A and exploration expenses. The Company believes that this measure is useful to external users in assessing operating performance and the Company's ability to generate free cash flow from potential operations.
Free Cash Flow
Free cash flows are revenues net of operating costs, royalties, capital expenditures and cash taxes. The Company believes that this measure is useful to the external users in assessing the Company's ability to generate cash flows from the Project.
Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves
NI 43-101 is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.