INTEGRA APPOINTS AUSENCO TO LEAD DETAILED ENGINEERING AT DELAMAR, NEPA PUBLIC SCOPING PERIOD UNDERWAY

(Neutral)
(Neutral)
Tags

Integra Resources (NYSE American: ITRG) appointed Ausenco as lead engineering partner for detailed engineering at the DeLamar gold-silver project in Idaho. Ausenco has engaged SLR Consulting for heap leach engineering, metallurgy and mine planning.

Detailed engineering is underway through Q1 2027, alongside the NEPA review, with a final EIS and ROD from the BLM anticipated in H2 2027.

Loading...
Loading translation...

Positive

  • Ausenco appointed to lead detailed engineering and execution readiness at DeLamar
  • SLR engaged for heap leach engineering, metallurgy and mine planning expertise
  • Detailed engineering work already underway, expected to continue through Q1 2027
  • Long-lead procurement activities planned from H2 2026 through 2027
  • Final EIS and ROD from BLM anticipated in H2 2027 to inform construction decision

Negative

  • Project construction decision dependent on receipt of final EIS and ROD in 2027
  • NEPA review and public scoping introduce regulatory and stakeholder process timelines

News Market Reaction – ITRG

-1.15%
-1.15% Session close to close

In the Jun 2 session, ITRG declined 1.15%, reflecting a mild negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

Market Context

This announcement advances DeLamar into detailed engineering with Ausenco leading design, procuremen...
Analysis

This announcement advances DeLamar into detailed engineering with Ausenco leading design, procurement planning, and execution readiness while NEPA public scoping proceeds. The news highlights a structured path toward a final Environmental Impact Statement and Record of Decision targeted for the second half of 2027. Investors may watch progress on engineering through Q1 2027, timing of long-lead procurement, and milestones in the NEPA review as indicators of project execution risk.

Key Figures

Public scoping period: 30 days Final EIS and ROD timing: Second half of 2027 Detailed engineering completion: Q1 2027 +3 more
6 metrics
Public scoping period 30 days NEPA public scoping and stakeholder engagement period initiated by NOI
Final EIS and ROD timing Second half of 2027 BLM anticipated timing for DeLamar final EIS and Record of Decision
Detailed engineering completion Q1 2027 Detailed engineering work expected to continue through Q1 2027
Long-lead procurement start Second half of 2026 Long-lead procurement activities beginning later this year
Technical report date February 2, 2026 Date of DeLamar Feasibility Study and Technical Report
Technical report effective date December 8, 2025 Effective date of DeLamar technical report prepared by SLR (Forte)

Historical Context

5 past events · Latest: May 29 (Positive)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
May 29 Permitting milestone Positive +1.9% BLM Notice of Intent starting NEPA review for DeLamar.
May 26 Leadership additions Positive +2.9% Appointment of three senior mining executives and equity awards.
May 13 Tribal equity agreement Positive -1.8% Equity grant to Shoshone-Paiute Tribes tied to DeLamar.
May 11 Q1 2026 earnings Positive -1.7% Higher revenue and earnings with elevated cash costs and AISC.
Apr 29 Nevada North permitting Positive +2.3% Final approval of Exploration Plan of Operations for Wildcat.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Recent project and permitting milestones have often seen positive price alignment, while some financing and partnership news showed divergence.

Recent Company History

Over the last few months, Integra has advanced both permitting and corporate development. On Apr 29, it secured key NEPA approvals for the Wildcat deposit, followed by stronger Q1 2026 results reported on May 11. Subsequent announcements included a tribal equity agreement on May 13, leadership additions on May 26, and the DeLamar NEPA Notice of Intent on May 29. Today’s detailed engineering update further extends this steady DeLamar de-risking sequence.

Key Terms

heap leach, national environmental policy act, nepa, environmental impact statement, +3 more
7 terms
heap leach technical
"which brings specialized heap leach engineering, metallurgy, and mine planning expertise"
Heap leach is a mining method where crushed ore is piled into a heap and a liquid is dripped or sprayed over it to dissolve valuable metals, which are then collected from the runoff. Investors care because it is a lower-cost, scalable way to produce metals like gold or copper, but it also affects project timelines, recovery rates, capital needs and environmental or regulatory risk — like choosing a cheap, slow way to extract juice from a fruit versus pressing it quickly.
national environmental policy act regulatory
"public scoping and stakeholder engagement period of the National Environmental Policy Act ("NEPA") review process"
A U.S. law that requires federal agencies to evaluate and disclose the likely environmental effects of major projects and decisions before they proceed. For investors, that review can delay approvals, add compliance costs, or change project plans—like a required safety inspection that can uncover problems or require fixes before construction continues—so NEPA processes are a key source of timing, cost and legal risk for projects involving federal permits or funding.
nepa regulatory
"public scoping and stakeholder engagement period of the National Environmental Policy Act ("NEPA") review process"
The National Environmental Policy Act (NEPA) is a U.S. law that requires federal agencies to evaluate and report the environmental impacts of major projects, like permitting, construction, or resource development. For investors, NEPA is important because its reviews and required studies can delay, alter, or block projects—much like a safety inspection that must be passed before a vehicle is allowed on the road—affecting timelines, costs and the potential revenue of affected companies.
environmental impact statement regulatory
"final Environmental Impact Statement ("EIS") and Record of Decision ("ROD") from the BLM"
An environmental impact statement is a formal report that evaluates the likely effects a proposed project or plan will have on air, water, land, wildlife and local communities; it lays out potential harms, proposed mitigation measures, and alternatives. Think of it as a project’s environmental report card and repair plan: regulators use it to decide permits, and investors use it to assess delays, extra costs, legal risks and reputation exposure tied to environmentally sensitive issues.
record of decision regulatory
"final Environmental Impact Statement ("EIS") and Record of Decision ("ROD") from the BLM"
A record of decision is an official written statement from a government regulator that explains and finalizes its approval or denial of a proposed project after reviewing environmental and legal factors. For investors, it matters because it removes a major regulatory uncertainty — like a referee’s final whistle — allowing a project to move forward, be funded, or be halted, which can change timelines, costs, and potential liabilities.
notice of intent regulatory
"the United States Bureau of Land Management ("BLM") has published the Notice of Intent ("NOI") in the Federal Register"
A notice of intent is a formal written announcement that an organization plans to take a specific action—such as filing legal claims, seeking regulatory approval, issuing securities, or starting a procurement process. For investors it matters because it signals a likely future event that could change a company’s costs, revenues, risk profile or ownership; think of it like a heads-up that a major move is being prepared so stakeholders can anticipate and reassess their positions.
feasibility study technical
"prepared the technical report for DeLamar titled "Feasibility Study and Technical Report on the DeLamar Project""
A feasibility study is an assessment that evaluates whether a proposed project or idea is practical and likely to succeed before investing significant time and resources. It considers factors like costs, potential benefits, and challenges, helping stakeholders decide if moving forward makes sense. Think of it as a detailed plan that gauges if a new venture is worth pursuing.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

TSXV: ITR; NYSE American: ITRG
www.integraresources.com

VANCOUVER, BC, June 2, 2026 /PRNewswire/ - Integra Resources Corp. ("Integra" or the "Company") (TSXV: ITR) (NYSE American: ITRG) is pleased to announce the appointment of Ausenco Engineering USA South Inc. ("Ausenco") as lead engineering partner for detailed engineering activities at the Company's DeLamar Project ("DeLamar" or the "Project") in southwestern Idaho. As part of the engagement, Ausenco has retained SLR Consulting ("SLR"), which brings specialized heap leach engineering, metallurgy, and mine planning expertise to the Project. The start of detailed engineering marks a significant step in project development for DeLamar and coincides with the launch of the public scoping and stakeholder engagement period of the National Environmental Policy Act ("NEPA") review process.

The Company announced on May 29, 2026, that the United States Bureau of Land Management ("BLM") has published the Notice of Intent ("NOI") in the Federal Register. The publication of the NOI started the 30-day public scoping and stakeholder engagement period of the NEPA process. Concurrent with the NEPA process, Ausenco and Integra will advance detailed engineering at DeLamar, with the final Environmental Impact Statement ("EIS") and Record of Decision ("ROD") from the BLM anticipated in the second half of 2027.

"Entering the detailed engineering phase at DeLamar is a major milestone for the Company. As one of the largest and most advanced heap leach projects currently in the NEPA process, DeLamar has the potential to drive long-term economic growth and job creation in southwestern Idaho," said George Salamis, President, Chief Executive Officer and Director of Integra. "The appointment of Ausenco strengthens the Company's position to advance DeLamar as the Company progresses through the NEPA process."

Cliff Lafleur, Chief Operating Officer of Integra, commented: "We have assembled an experienced detailed engineering team led by Ausenco, which has a proven track record of executing similar mandates on open pit projects of this scale. Detailed engineering work is already underway and will continue through Q1 2027, with long-lead procurement activities beginning in the second half of this year and continuing through 2027. The detailed engineering, along with the expected receipt of the final EIS and ROD next year, will inform a construction decision for DeLamar."

Ausenco is a globally recognized engineering, consulting and project delivery firm with extensive experience in the design and construction of precious metals mining projects worldwide, including several recent North American gold and silver developments.  Under the scope of work with Integra, Ausenco will lead detailed engineering and execution readiness activities for the Project. These activities will include engineering design advancement, procurement planning, constructability reviews, project execution planning, and support for future development activities. 

SLR, which recently acquired Forte Analytical and Forte Dynamics ("Forte"), will focus on heap leach engineering, metallurgy and mine planning. SLR (Forte) prepared the technical report for DeLamar titled "Feasibility Study and Technical Report on the DeLamar Project, Owyhee County, Idaho, USA" dated February 2, 2026, with an effective date of December 8, 2025, available under Integra's SEDAR+ profile at www.sedarplus.ca and EDGAR profile at www.sec.gov.

About Ausenco

Ausenco is a global engineering, consulting and project delivery firm built for the minerals and metals industry. With three decades of global experience, Ausenco works alongside clients to navigate complex challenges from first study to final closure—across every phase, on five continents. Deeply rooted in the minerals and metals industry, their people combine technical depth, hands-on expertise, and hard-earned insight to deliver practical, forward-thinking solutions that reduce risk and unlock value. More information on Ausenco is available at: www.ausenco.com.

About SLR

SLR is a global leader in sustainability solutions, with a team of 5,000+ talented professionals operating from a network of offices in Europe, the Americas, Asia-Pacific, Africa, and the Middle East.  SLR partners with mining and investment clients globally, serving as their trusted experts and providing integrated technical, advisory, and sustainability solutions across the entire mining lifecycle. More information on SLR is available at: www.slrconsulting.com.

About Integra Resources Corp.

Integra is a growing precious metals producer in the Great Basin of the Western United States. Integra is focused on demonstrating profitability and operational excellence at its principal operating asset, the Florida Canyon Mine, located in Nevada. In addition, Integra is committed to advancing its flagship development-stage heap leach projects: the past producing DeLamar Project located in southwestern Idaho and the Nevada North Project located in western Nevada. Integra creates sustainable value for shareholders, stakeholders, and local communities through successful mining operations, efficient project development, disciplined capital allocation, and strategic M&A, while upholding the highest industry standards for environmental, social, and governance practices.

ON BEHALF OF THE BOARD OF DIRECTORS

George Salamis
President, CEO and Director

CONTACT INFORMATION
Corporate Inquiries: ir@integraresources.com
Company website: www.integraresources.com Office phone: 1 (604) 416-0576

Forward Looking Statements

Certain information set forth in this news release contains "forward‐looking statements" and "forward‐looking information" within the meaning of applicable Canadian securities legislation and in applicable United States securities law (referred to herein as forward‐looking statements). Forward-looking statements are often identified by the use of words such as "may", "will", "could", "would", "anticipate", "believe", "expect", "intend", "potential", "estimate", "budget", "scheduled", "plans", "planned", "forecasts", "goals" and similar expressions. Except for statements of historical fact, certain information contained herein constitutes forward‐looking statements which includes, but is not limited to, statements with respect to: the completion and expected timing of the EIS and ROD; the potential benefits of the appointment of Ausenco and SLR; the Company's plans, objectives and expectations in respect of its projects; and the future financial or operating performance of the Company.

Forward-looking statements are based on a number of factors and assumptions made by management and considered reasonable at the time such statement was made. Assumptions and factors include: the Company's ability to complete its planned exploration and development programs; the absence of adverse conditions at the Company's mineral properties including absence of any equipment or infrastructure failures; no unforeseen operational delays; no material delays in obtaining necessary permits; results of independent engineer technical reviews; the possibility of cost overruns and unanticipated costs and expenses; the price of gold remaining at levels that continue to render the Company's mineral properties economic; the Company's ability to continue raising necessary capital to finance operations; and the ability to realize on the mineral resource and reserve estimates. Forward‐looking statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance or result expressed or implied by such forward‐looking statements. These risks and uncertainties include, but are not limited to: general business, economic and competitive uncertainties; the actual results of current and future exploration activities; conclusions of economic evaluations; meeting various expected cost estimates; benefits of certain technology usage; changes in project parameters and/or economic assessments as plans continue to be refined; future prices of metals; possible variations of mineral grade or recovery rates; the risk that actual costs may exceed estimated costs; geological, mining and exploration technical problems; failure of plant, equipment or processes to operate as anticipated; accidents, labor disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; risks related to local communities; the speculative nature of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); title to properties; and other factors beyond the Company's control and as well as those factors included herein and elsewhere in the Company's public disclosure. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in the forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Readers are advised to study and consider risk factors disclosed in Integra's Annual Information Form dated March 24, 2026 for the fiscal year ended December 31, 2025, which is available on the SEDAR+ issuer profile for the Company at www.sedarplus.ca and available as Exhibit 99.1 to Integra's Form 40-F, which is available on the EDGAR profile for the Company at www.sec.gov.

Investors are cautioned not to put undue reliance on forward-looking statements.  The forward-looking statements contained herein are made as of the date of this news release and, accordingly, are subject to change after such date.  The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws.  Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed online under the Company's profile on SEDAR+ at www.sedarplus.ca.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/integra-appoints-ausenco-to-lead-detailed-engineering-at-delamar-nepa-public-scoping-period-underway-302787691.html

SOURCE Integra Resources Corp.

FAQ

What did Integra Resources (ITRG) announce about the DeLamar Project on June 2, 2026?

Integra Resources announced Ausenco as lead engineering partner for detailed engineering at the DeLamar Project. According to Integra, this phase advances engineering design, execution readiness, and procurement planning while the NEPA review and stakeholder engagement processes move forward in parallel.

Who is Ausenco and what is its role at Integra Resources’ DeLamar Project (ITRG)?

Ausenco is an engineering, consulting and project delivery firm with precious metals experience. According to Integra, Ausenco will lead detailed engineering, procurement planning, constructability reviews and project execution planning to support potential future development of the DeLamar open pit, heap leach operation.

How is SLR Consulting involved in Integra Resources’ DeLamar Project (ITRG)?

SLR Consulting has been retained by Ausenco to support DeLamar. According to Integra, SLR will focus on heap leach engineering, metallurgy and mine planning and previously prepared the DeLamar feasibility study and technical report with an effective date of December 8, 2025.

What is the NEPA public scoping period for Integra Resources’ DeLamar Project (ITRG)?

The NEPA public scoping and stakeholder engagement period began after the BLM’s Notice of Intent publication on May 29, 2026. According to Integra, this initial 30-day period gathers public input as part of the federal environmental review process for DeLamar.

When are the final EIS and ROD expected for Integra Resources’ DeLamar Project (ITRG)?

Integra anticipates the final Environmental Impact Statement and Record of Decision from the BLM in the second half of 2027. According to Integra, these NEPA outcomes are expected to help inform a future construction decision for the DeLamar Project.

What is the engineering and procurement timeline at Integra Resources’ DeLamar Project (ITRG)?

Detailed engineering at DeLamar is already underway and planned through Q1 2027. According to Integra, long-lead procurement activities are expected to begin in the second half of 2026 and continue through 2027, supporting potential project development readiness.