Red Metal Site Visit Confirms Development Progress at Carrizal IOCG Project

(Neutral)
Tags

Red Metal Resources (OTC: RMESF) reported progress at its Farellon 1/8 concession, part of the Carrizal copper-gold-cobalt project in Chile. Lease operator KMT is advancing underground development in both North and South Mine areas, with Red Metal earning a 10% sales royalty on ore sold to ENAMI.

De-watering of historic Level 7 in the North Mine is ~90% complete, restoring access to zones that previously yielded 5,080 tonnes at 1.97% Cu, 9.62 g/t Ag and 0.14 g/t Au. The South Mine portal has advanced 10 metres toward a vein with historic drill intercepts up to 3.72% Cu.

KMT indicates development toward full production is ahead of schedule, with production targeted before the original seven‑month goal and by end of summer. Red Metal staff will visit twice monthly to oversee operations and sampling, while IP survey results expected in July will support further drill targeting.

Loading...
Loading translation...

AI-generated analysis. How Rhea-AI works. Not financial advice.

Positive

  • Red Metal earns 10% sales royalty on all ore sold to ENAMI
  • Level 7 de-watering ~90% complete, enabling access to past ore zones
  • Historic Level 7 output of 5,080 tonnes at 1.97% copper
  • Development toward production reported ahead of original seven-month target

Negative

  • Production has not yet commenced; first output targeted by end of summer
  • South decline still advancing toward target vein, not yet reached
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Vancouver, British Columbia--(Newsfile Corp. - July 7, 2026) - RED METAL RESOURCES LTD. (CSE: RMES) (OTC Pink: RMESF) (FSE: I660) ("Red Metal" or the "Company") is pleased to provide an operational update on the small-scale mining activities at its Farellon 1/8 mineral concession, part of the Company's Carrizal Copper-Gold-Cobalt Property ("Carrizal" or the "Property") in Chile's Atacama Region.

The update follows recent site visits by Red Metal's in-country staff, who will be visiting the operation twice monthly to monitor progress by lease operator Minera KMT SpA ("KMT"). KMT signed a mining agreement with Red Metal (see news release May 14, 2026) leasing the Farellon 1/8 mineral concession for small-scale mining. Red Metal will collect a 10% sales royalty from KMT on all ore sold to Empresa Nacional de Mineria ("ENAMI").

Highlights

  • Red Metal's in-country staff completed site visits June 18th and July 1st, 2026, confirming that mine development by KMT is actively underway at Farellon 1/8, and will continue to visit twice monthly.

  • De-watering of the historic Level 7 workings at the North Mine is approximately 90% complete, restoring access to known high-grade underground copper mineralization.

  • The South Mine portal has been advanced 10 metres in the direction of a mineralized vein intersected by previous drilling

  • KMT advises that the path to full production operations is ahead of schedule

Site Visit and Operational Update

During recent site visits, Red Metal's in-country staff met with KMT's mine shift supervisor to review operational activities and report on progress. As part of the Company's ongoing oversight of the lease, Red Metal staff will conduct site visits twice monthly to evaluate progress, take samples and ensure KMT is adhering to all terms of the contract. KMT is currently working on road construction, building camp infrastructure, and advancing underground development in both the North and South Mine areas.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4932/304172_b55380c9b4ab6808_001.jpg

Figure 1 - scooptram on Southern decline Figure 2 - miners camp Figure 3 - Northern portal with dewatering lines 

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4932/304172_b55380c9b4ab6808_001full.jpg

Underground Development

In the north workings, de-watering of the historic Level 7 workings is approximately 90% complete, with water being pumped to surface and discharged. Restoring access to Level 7 is a key step in re-establishing production, as a total of 5,080 tonnes of ore were previously extracted from Level 7 between 2016 and 2017, grading 1.97% copper, 9.62 g/t silver and 0.14 g/t gold. Copper and gold grades within the sulphide mineralization have been shown to increase and become more consistent with depth in the historic workings.

In the south sector, a crew of two drillers and a scoop tram operator continue to advance the decline toward a previously drilled vein with intercepts in the area. Intercepts listed below are historic drill intercepts in the area being targeted by the Southern decline.

Table 1 - historic drill intercepts targeted by the Southern Decline

Hole IDDepth From mDepth To mLength mAu g/tCu %
FAR-11-00680112320.991.35
FAR-96-0222939101.311.53
FAR-96-02210010882.493.72
FAR-09-B7586110.671.35
FAR-09-C778692.441.60
FAR-09-D9510380.332.02

 

Drill intercepts are not true widths; true widths are estimated at between 70-90% of drilled widths

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4932/304172_b55380c9b4ab6808_002.jpg

Figure 4 - Farellon site with surface sampling results and North and South mine portal locations

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4932/304172_b55380c9b4ab6808_002full.jpg

Red Metal Resources President and CEO, Caitlin Jeffs, stated, "The reports from our in-country team are encouraging, confirming active development and steady progress on many fronts with an experienced local crew. With de-watering of Level 7 well advanced and the south tunnel approaching the target vein, KMT is on track to begin production before the original seven month target. Having our staff on-site twice a month gives us close oversight of the operation as it advances, while continuing to support local Chilean miners and providing a reliable revenue stream from our Chilean operations."

Next Steps

  • KMT will continue to de-water Level 7 in the northern mine sector in preparation for the commencement of production by end of summer

  • the southern mine sector will be further extended until the target mineralized vein is reached.

  • IP results expected in July to aide in drill targeting

Cautionary Statement

Mining at the Farellon 1/8 concession is being carried out by the lessee, Minera KMT [SpA], under a lease and royalty arrangement. Red Metal is the lessor and royalty holder and is not the operator of the mining activities. The mining is not based on a feasibility study, preliminary feasibility study or other technical study demonstrating economic or technical viability, and no current mineral resource or mineral reserve estimate has been prepared for the Property under National Instrument 43-101.

Qualified Person

The technical content of this news release has been reviewed and approved by Caitlin Jeffs, P. Geo, who is a Qualified Person ("QP") as defined in National Instrument 43-101, Standards of Disclosure for Mineral Projects.

About Red Metal Resources Ltd.

Red Metal Resources is a mineral exploration company focused on growth through acquiring, exploring and developing clean energy and strategic minerals projects. The Company's current portfolio includes the Company's Chilean projects, located in the prolific Candelaria Iron Oxide Copper-Gold (IOCG) belt of Chile's coastal Cordillera, as well as claims in Quebec and Ontario, Canada.

Red Metal is quoted on the Canadian Securities Exchange under the symbol RMES, on the OTC Link alternative trading system on the OTC Pink marketplace under the symbol RMESF, and on the Frankfurt Stock Exchange under the symbol I660.

For more information, please visit www.redmetalresources.com.

Contact:
Red Metal Resources Ltd.
Caitlin Jeffs
President & CEO
1-866-907-5403
invest@redmetalresources.com
www.redmetalresources.com

Forward-Looking Statements - All statements in this press release, other than statements of historical fact, are "forward-looking information" within the meaning of applicable securities laws. Red Metal provides forward-looking statements for the purpose of conveying information about current expectations and plans relating to the future and readers are cautioned that such statements may not be appropriate for other purposes. By its nature, this information is subject to inherent risks and uncertainties that may be general or specific, and which give rise to the possibility that expectations, forecasts, predictions, projections or conclusions will not prove to be accurate, that assumptions may not be correct and that objectives, strategic goals and priorities will not be achieved. These risks and uncertainties include but are not limited to the ability to raise adequate financing, receipt of required approvals, as well as those risks and uncertainties identified and reported in Red Metal's public filings under its SEDAR+ profile at www.sedarplus.ca. Although Red Metal has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Red Metal disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise unless required by law.

Neither the Canadian Securities Exchange nor the Market Regulator (as that term is defined in the policies of the Canadian Securities Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/304172

FAQ

What operational progress did Red Metal (RMESF) report at the Carrizal Farellon 1/8 project on July 7, 2026?

Red Metal reported active underground development and substantial de-watering progress at Farellon 1/8. According to Red Metal, KMT is advancing both North and South Mine workings, with Level 7 roughly 90% de-watered and road and camp infrastructure under construction.

How does Red Metal (RMESF) earn revenue from the Carrizal Farellon 1/8 mining agreement?

Red Metal earns a 10% sales royalty on all ore KMT sells to ENAMI. According to Red Metal, this lease-based structure provides a recurring revenue stream while KMT funds and operates small-scale mining at the Farellon 1/8 concession.

What are the key underground development milestones at Carrizal’s North Mine reported by Red Metal (RMESF)?

At the North Mine, de-watering of historic Level 7 is about 90% complete. According to Red Metal, prior mining there produced 5,080 tonnes grading 1.97% copper, 9.62 g/t silver and 0.14 g/t gold between 2016 and 2017.

What historic drill results are being targeted by the South decline at Red Metal’s (RMESF) Carrizal project?

The South decline targets a mineralized vein intersected in several historic holes. According to Red Metal, notable intervals include 8 metres at 2.49 g/t gold and 3.72% copper, and 32 metres at 0.99 g/t gold and 1.35% copper.

When does Red Metal (RMESF) expect small-scale production to start at the Carrizal Farellon 1/8 concession?

KMT is reported to be ahead of schedule and on track to begin production before the original seven-month target. According to Red Metal, commencement of production is currently planned by the end of summer, subject to ongoing development.

How is Red Metal (RMESF) overseeing KMT’s mining operations at the Carrizal Farellon 1/8 property?

Red Metal’s in-country staff will visit the site twice monthly to monitor operations. According to Red Metal, these visits review development progress, collect samples, and confirm KMT’s compliance with contract terms and operational plans at the North and South Mines.

What are the next exploration and development steps for Red Metal’s (RMESF) Carrizal project?

Next steps include completing Level 7 de-watering and extending the southern decline to the target vein. According to Red Metal, induced polarization (IP) survey results expected in July will help refine drill targeting across the Carrizal property.