TeraWulf Expands Strategic Partnership with Fluidstack Through New 168 MW AI Compute Joint Venture
TeraWulf (NASDAQ:WULF) announced a 51% majority joint venture with Fluidstack to develop 168 MW of critical IT load at the Abernathy, Texas campus, with expected delivery in the second half of 2026.
The JV includes a 25-year hosting commitment representing approximately $9.5 billion in contracted revenue and expands TeraWulf’s contracted HPC platform to more than 510 MW. Google will back roughly $1.3 billion of Fluidstack’s long-term lease obligations to support project debt. Total project cost is estimated at $8–10 million per MW. TeraWulf secured an exclusive right to partner on the next ~168 MW Fluidstack-led project and is targeting 250–500 MW of additional contracted capacity per year.
TeraWulf (NASDAQ:WULF) ha annunciato una joint venture a maggioranza del 51% con Fluidstack per sviluppare 168 MW di carico IT critico presso il campus di Abernathy, Texas, con consegna prevista nella seconda metà del 2026.
La JV comprende un impegno di hosting di 25 anni che rappresenta circa 9,5 miliardi di dollari di entrate contrattate e amplia la piattaforma HPC contrattata di TeraWulf a più di 510 MW. Google sosterrà circa 1,3 miliardi di dollari delle obbligazioni di leasing a lungo termine di Fluidstack per supportare il debito del progetto. Il costo totale del progetto è stimato in 8–10 milioni di dollaro per MW. TeraWulf ha ottenuto il diritto esclusivo di collaborare al prossimo progetto guidato da Fluidstack di ~168 MW e mira a 250–500 MW di capacità contrattata aggiuntiva all'anno.
TeraWulf (NASDAQ:WULF) anunció una empresa conjunta mayoritaria del 51% con Fluidstack para desarrollar 168 MW de carga crítica de TI en el campus de Abernathy, Texas, con entrega prevista para la segunda mitad de 2026.
La JV incluye un compromiso de hosting de 25 años que representa aproximadamente 9,5 mil millones de dólares en ingresos contratados y expande la plataforma HPC contratada de TeraWulf a más de 510 MW. Google respaldará aproximadamente 1,3 mil millones de dólares de las obligaciones de arrendamiento a largo plazo de Fluidstack para apoyar la deuda del proyecto. El costo total del proyecto se estima en 8–10 millones de dólares por MW. TeraWulf aseguró un derecho exclusivo para asociarse al siguiente proyecto de ~168 MW liderado por Fluidstack y apunta a 250–500 MW de capacidad contratada adicional por año.
TeraWulf (NASDAQ:WULF)는 Fluidstack와 51% 지분의 공동벤처를 발표하여 Abernathy, 텍사스 캠퍼스에서 168 MW의 중요한 IT 부하를 개발하며, 2026년의 후반부에 납기를 예상합니다.
이 JV는 약 25년 호스팅 약정을 포함하며 약 95억 달러의 계약 매출을 나타내고 TeraWulf의 계약 HPC 플랫폼을 510 MW 이상으로 확장합니다. 구글은 프로젝트 채무를 지원하기 위해 Fluidstack의 장기 임대 의무의 약 13억 달러를 보조할 것입니다. 총 프로젝트 비용은 MW당 800만–1000만 달러로 추정됩니다. TeraWulf는 Fluidstack가 주도하는 다음 약 168 MW 프로젝트와의 파트너십에 대한 독점 권리를 확보했으며 연간 250–500 MW의 추가 계약 용량을 목표로 하고 있습니다.
TeraWulf (NASDAQ:WULF) a annoncé une coentreprise majoritaire à 51% avec Fluidstack pour développer 168 MW de charge informatique critique sur le campus d'Abernathy, Texas, avec une livraison prévue dans la deuxième moitié de 2026.
La coentreprise comprend un Engagement d'hébergement de 25 ans représentant environ 9,5 milliards de dollars de revenus contractés et étend la plateforme HPC contractée de TeraWulf à plus de 510 MW. Google soutiendra environ 1,3 milliard de dollars des obligations de bail à long terme de Fluidstack afin de soutenir la dette du projet. Le coût total du projet est estimé à 8–10 millions de dollars par MW. TeraWulf a obtenu le droit exclusif de collaborer sur le prochain projet de ~168 MW dirigé par Fluidstack et vise 250–500 MW de capacité contractée additionnelle par an.
TeraWulf (NASDAQ:WULF) kündigte eine Mehrheits-Joint-Venture von 51% mit Fluidstack an, um 168 MW kritische IT-Lasten am Campus Abernathy, Texas, zu entwickeln, mit voraussichtlicher Lieferung in der zweiten Hälfte 2026.
Die JV umfasst eine 25-jährige Hosting-Verpflichtung, die ungefähr 9,5 Milliarden US-Dollar an vertraglich zugesicherten Einnahmen repräsentiert und Terawulf's vertraglich gebundene HPC-Plattform auf mehr als 510 MW erweitert. Google wird etwa 1,3 Milliarden US-Dollar der langfristigen Leasingverpflichtungen von Fluidstack unterstützen, um die Projektverschuldung zu stützen. Die Gesamtkosten des Projekts werden auf 8–10 Millionen US-Dollar pro MW geschätzt. TeraWulf sicherte sich das exklusive Recht, am nächsten ~168 MW von Fluidstack geführten Projekt zu partnerschaftlich mitzuwirken und strebt 250–500 MW zusätzlicher vertraglich gebundener Kapazität pro Jahr an.
TeraWulf (NASDAQ:WULF) أعلن عن مشروع مشترك حصة الأغلبية 51% مع Fluidstack لتطوير 168 MW من الحمل الحيوي لتقنية المعلومات في حرم أبنارثي، تكساس، مع توقع التسليم في النصف الثاني من 2026.
يشمل المشروع المشترك التزام استضافة لمدة 25 عاماً يمثل حوالي 9.5 مليار دولار من الإيرادات المتعاقدة ويوسع منصة HPC المتعاقدة لـ TeraWulf إلى أكثر من 510 MW. ستدعم Google حوالي 1.3 مليار دولار من التزامات الإيجار طويلة الأجل لـ Fluidstack لدعم ديون المشروع. يُقدر التكلفة الإجمالية للمشروع بــ 8–10 ملايين دولار أمريكي لكل MW. حصلت TeraWulf على حق حصري للشراكة في مشروع Fluidstack التالي حوالي ~168 MW وتستهدف 250–500 MW من السعة المتعاقدة الإضافية سنوياً.
TeraWulf (NASDAQ:WULF) 宣布与 Fluidstack 51% 的控股合资企业,在Abernathy, Texas校园开发 168 MW 的关键 IT 负载,预计在 2026 年下半年 交付。
该合资企业包含一个 25 年 hosting 承诺,约代表 95 亿美元 的合约收入,并将 TeraWulf 的合约 HPC 平台扩展到 超过 510 MW。谷歌将支持 Fluidstack 的长期租赁义务大约 13 亿美元,以支持项目债务。项目总成本估计为每 MW 800–1000 万美元。TeraWulf 获得了与下一大约 168 MW 的 Fluidstack 主导项目合作的专属权,并目标是每年 250–500 MW 的额外合约容量。
- 25-year hosting commitment ≈ $9.5B contracted revenue
- TeraWulf holds 51% majority stake in the 168 MW joint venture
- Contracted HPC platform now exceeds 510 MW critical IT load
- Google backing of $1.3B to support Fluidstack lease obligations
- Estimated $8–10M per MW total project cost implies high upfront capex
- 25-year hosting revenue tied to a single global hyperscale AI platform (concentration risk)
- TeraWulf equity contributions will be made in staged installments, creating timing uncertainty for funding
Insights
TeraWulf and Fluidstack formed a 168 MW, 25-year JV that brings ~
The joint venture will deliver 168 MW of critical IT load at Abernathy with TeraWulf holding a 51% stake and a 25‑year hosting commitment equating to about
Dependencies and risks include project completion timelines, accurate capex per MW, and successful project financing using the disclosed Google support of
Watch the
25-year lease agreement represents approximately
Google backstops
Exclusive right to partner with Fluidstack on next ~168 MW critical IT load project
Expands TeraWulf’s contracted HPC platform to 510 MW of critical IT load and supports an upwardly revised growth strategy targeting 250–500 MW of new contracted capacity annually
EASTON, Md., Oct. 28, 2025 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), a leading owner and operator of vertically integrated, low-carbon digital infrastructure, today announced that it has executed a long-term high-performance computing (HPC) joint venture with Fluidstack, a premier AI cloud platform that builds and operates HPC clusters for some of the world’s largest companies.
Under the agreement, the parties will develop and deliver 168 MW of critical IT load at the Abernathy, Texas campus, serving workloads for a global hyperscale AI platform developing frontier-scale foundation models, backed by an investment-grade, long-duration infrastructure commitment through Fluidstack’s platform. The facility is expected to be delivered in the second half of 2026.
The 25-year hosting commitment represents approximately
Separately, TeraWulf has secured the exclusive right to partner with Fluidstack for up to
As a result of this transaction, TeraWulf’s contracted HPC platform now exceeds 510 MW of critical IT load. The Company is executing on an upwardly revised growth strategy targeting an additional 250 MW to 500 MW of contracted critical IT load per year, having already secured 510 MW of contracted critical IT load in the last 10 months.
The joint venture will be project-financed, with Google backing approximately
Leadership Commentary
“We are very pleased to deepen our strategic alignment with Fluidstack and Google through this long-term joint venture,” said Paul Prager, Chief Executive Officer of TeraWulf. “On our last conference call — immediately following the Lake Mariner announcement — I made clear that our focus was execution, execution, execution. Today’s transaction demonstrates that execution in practice.”
“What began as a single site has matured into a repeatable, credit-enhanced platform model backed by Tier-1 partners. This is exactly the evolution we outlined: converting advantaged infrastructure positions into contracted megawatts with investment-grade counterparties and doing so at strategic scale.”
“Securing more than 510 MW of critical IT load in the past 10 months provides a direct proof-point of our growth strategy – supporting our goal of contracting an additional 250–500 MW of new capacity annually over the coming years.”
“Fluidstack is proud to partner again with TeraWulf as we expand our platform to support next-generation GPU clusters for foundation model developers,” said César Maklary, Co-Founder and President of Fluidstack. “TeraWulf brings exceptional operational discipline, energy expertise, and development scale at precisely the moment the market requires hardened, sustainable infrastructure.”
Joint Venture Structure & Economics
- Capacity: 168 MW critical IT load (240 MW gross)
- Contract Value: ~
$9.5 billion to the joint venture over 25-year term - Lease Structure: Modified gross lease with annual escalators
- Total Project Cost:
$8 -$10 million per MW of critical IT load - TeraWulf Ownership:
51% majority stake - Google Support:
$1.3 billion long-term lease backing in support of project debt - Abernathy Expansion: joint venture right to develop future phases beyond initial 168 MW
Platform Expansion & Growth Outlook
- Contracted Platform Scale: >510 MW critical IT load
- Growth Model: Targeting 250–500 MW of additional contracted IT load annually
- Strategic Optionality: Exclusive WULF right to partner on next ~168 MW Fluidstack-led project
Advisors
Morgan Stanley is serving as sole financial advisor to TeraWulf. Paul, Weiss, Rifkind, Wharton & Garrison LLP and Stutzman, Bromberg, Esserman & Plifka, P.C. are serving as legal counsel.
About TeraWulf
TeraWulf develops, owns, and operates environmentally sustainable, industrial-scale data center infrastructure in the United States, purpose-built for high-performance computing (HPC) hosting and bitcoin mining. Led by a team of veteran energy infrastructure entrepreneurs, TeraWulf is committed to delivering scalable, low-carbon compute capacity for next-generation AI and HPC customers.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “seek,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “strategy,” “opportunity,” “predict,” “should,” “would” and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf’s management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) the ability to mine bitcoin profitably; (2) TeraWulf’s ability to attract additional customers to lease its HPC data centers; (3) TeraWulf’s ability to perform under its existing data center lease agreements; (4) changes in applicable laws, regulations and/or permits affecting TeraWulf’s operations or the industries in which it operates; (5) the ability to implement certain business objectives, including its bitcoin mining and HPC data center development, and to timely and cost-effectively execute related projects; (6) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to expansion or existing operations; (7) adverse geopolitical or economic conditions, including a high inflationary environment, the implementation of new tariffs and more restrictive trade regulations; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability and cost of power as well as electrical infrastructure equipment necessary to maintain and grow the business and operations of TeraWulf; and (10) other risks and uncertainties detailed from time to time in TeraWulf’s filings with the Securities and Exchange Commission (“SEC”). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in TeraWulf’s filings with the SEC, which are available at www.sec.gov.
Contacts
Investors: investors@terawulf.com
Media: media@terawulf.com
__________________________________
1 Lease term may be shortened to 20 years or 15 years pursuant to certain contractual options.