Highlander Silver (TSX:HSLV) details progress at Corani silver project

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Highlander Silver Corp. reports continued site development progress at its Corani Silver Project in Peru. The workforce has surpassed 300 team members, with a focus on hiring from local communities, and camp and facility construction is underway.

Preliminary earthworks for site infrastructure, pits and collection ponds have begun, along with internal road rehabilitation, external access road construction and substation construction. The project management team is led by Carlos Ojeda, who has over 25 years of technical services experience at major open-pit mines in Peru.

The Company notes that long-lead-time orders and work on the transmission line are expected to commence in August. Highlander Silver describes Corani as the largest silver deposit in development globally and also highlights its San Luis gold-silver project and Mercedes mine.

Positive

  • None.

Negative

  • None.
Corani workforce over 300 team members Site development workforce size at Corani Silver Project
Project leader experience over 25 years Technical services experience of VP & General Manager Carlos Ojeda
forward-looking information regulatory
"Certain information contained in this news release constitutes “forward-looking information” under Canadian securities legislation."
Forward-looking information are predictions, plans, estimates or expectations about a company’s future performance, results or events, such as sales forecasts, project timelines, or anticipated costs. It matters to investors because these statements guide expectations but rely on assumptions and uncertain factors—like a weather forecast for a business—so investors should treat them as informed guesses rather than guarantees and consider the risks and possible changes behind the numbers.
long-lead-time orders financial
"Long-lead-time orders to be placed in August"
substation construction technical
"Substation construction underway, with transmission line to commence in August"
transmission line technical
"Substation construction underway, with transmission line to commence in August"
A transmission line is the infrastructure—wires, towers, ducts or cables—that carries electricity or data over long distances from producers to users or networks. Investors care because these lines determine how reliably and cheaply power or communications can be delivered; like a highway for goods, congested or aging lines can cause delays, extra costs, outages or regulatory expenses that affect revenue, maintenance needs and future growth prospects.
bonanza-grade financial
"the bonanza-grade San Luis gold-silver project, which ranks among the 10 highest-grade projects globally"
Bonanza-grade describes a deposit, sample or finding that is unusually rich in valuable material compared with normal expectations — like hitting a very high-yield pocket in a mine. For investors it signals potential for much higher revenue per unit of work or lower production costs than typical deposits, which can sharply change a project's economics and a company's market value if confirmed and sustainable.
open-pit mines technical
"experience in engineering, construction and operations at major open-pit mines in Peru"
A large surface excavation where rock and soil are removed to access minerals or ore near the surface, shaped like a stepped bowl or quarry. Open-pit mines matter to investors because they determine how much ore can be produced, the cost and timing of extraction, and exposure to environmental permitting, reclamation and commodity-price risk—factors that influence a mining company's revenue, costs and capital needs.
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

FAQ

What did Highlander Silver (HSLV) report in its latest 6-K filing?

Highlander Silver reported development progress at its Corani Silver Project in Peru, highlighting key construction and infrastructure milestones. The update focuses on workforce growth, early-stage site works, camp and facility construction, road access, and power infrastructure preparations, rather than detailed financial or production metrics.

How many workers are currently at Highlander Silver’s Corani project?

The company states that the Corani project workforce has surpassed 300 team members. Highlander Silver emphasizes hiring from local communities, suggesting a growing on-site presence as development advances through camp construction, earthworks, road building and early-stage power infrastructure activities at the Peruvian project.

What construction activities are underway at Highlander Silver’s Corani site?

Highlander Silver reports camp and facility construction is underway, along with preliminary earthworks for site infrastructure, pits and collection ponds. It also notes internal road rehabilitation, external access road construction, and substation construction as active work areas supporting future operations at the Corani Silver Project.

Who leads project management at Highlander Silver’s Corani Silver Project?

The project management team is led by Carlos Ojeda, Vice President & General Manager. The company notes he has over 25 years of technical services experience in engineering, construction and operations at major Peruvian open-pit mines, including Quellaveco, Antamina and Constancia, supporting project execution capabilities.

What upcoming milestones does Highlander Silver mention for Corani in August?

Highlander Silver states that substation construction is underway and that work on the transmission line is expected to commence in August. It also plans to place long-lead-time orders in August, identifying these schedule items as forward-looking and subject to typical mining project execution risks and uncertainties.

What assets besides Corani does Highlander Silver (HSLV) operate or develop?

Highlander Silver highlights a portfolio of advanced-stage assets in Peru and Mexico. It is developing the Corani silver project and the bonanza-grade San Luis gold-silver project, and operates the Mercedes gold-silver mine in Mexico, positioning the company as a silver-growth and precious metals producer.
 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of July 2026

Commission File Number: 001-43170

Highlander Silver Corp.
(Translation of registrant's name into English)

2500 – 100 King Street West
Toronto, Ontario, M5X 1A9 Canada

(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [   ]      Form 40-F [ X ]

 

 


EXHIBIT INDEX

 

Exhibit Number Description
   
99.1 Press Release dated July 7, 2026


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

      Highlander Silver Corp.    
  (Registrant)
   
  
Date: July 7, 2026     /s/ Purni Parikh    
  Purni Parikh
  SVP Corporate Affairs and Corporate Secretary
  

EXHIBIT 99.1

Highlander Silver Showcases Key Development Milestones in Corani Photo Update

TORONTO, July 07, 2026 (GLOBE NEWSWIRE) -- Highlander Silver Corp. (TSX, NYSE American: HSLV) (“Highlander Silver” or the “Company”) is pleased to provide a photo update showcasing key milestones achieved in the site development of its Corani Silver Project in Peru.

Site Development – Key Milestones

  • Workforce surpasses 300 team members, with emphasis on hiring from local communities
  • Project management team led by Carlos Ojeda, Vice President & General Manager, with over 25 years of technical services experience in engineering, construction and operations at major open-pit mines in Peru, including Quellaveco, Antamina, and Constancia
  • Camp and facility construction underway
  • Preliminary earthworks for site infrastructure, pits and collection ponds underway
  • Internal road rehabilitation and construction underway
  • External access road construction underway
  • Substation construction underway, with transmission line to commence in August
  • Long-lead-time orders to be placed in August

Images 







On behalf of Highlander Silver 

“Daniel Earle”
President and CEO

Information contact

Arun Lamba, Vice President Corporate Development
alamba@highlandersilver.com

About Highlander Silver

Highlander Silver is a high-quality silver-growth company developing a portfolio of advanced-stage assets in Peru which includes the Corani silver project, the largest silver deposit in development globally, and the bonanza-grade San Luis gold-silver project, which ranks among the 10 highest-grade projects globally in both gold and silver categories.1 The Company also operates the Mercedes gold-silver mine in Mexico. Highlander Silver's major shareholders include the Augusta Group, Lundin family, and Eric Sprott.

Forward-looking statements

Certain information contained in this news release constitutes “forward-looking information” under Canadian securities legislation. This includes, but is not limited to, the transmission line to commence in August and long-lead-time orders to be placed in August. Such forward looking information or statements can be identified by the use of words such as “ramp up”, “attempting”, “intends”, “believes”, “plans”, “suggests”, “targets” or “prospects” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “will” be taken, occur, or be achieved. Forward-looking information involves known and unknown risks, uncertainties, and other factors which may cause the actual results, performance, or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance, or achievements expressed or implied by the forward-looking information. Such factors include, among others, general business, economic, competitive, political and social uncertainties, the actual results of current exploration activities, changes in project parameters as plans continue to be refined, future prices of precious and base metals, accident, labour disputes and other risks of the mining industry, and delays in obtaining governmental or stock exchange approvals or financing. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that could cause actions, events or results to differ from those anticipated, estimated or intended. Forward-looking information contained herein are made as of the date of this news release. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management’s estimates or opinions should change, except as required by applicable securities laws. Accordingly, the reader is cautioned not to place undue reliance on forward-looking information.

__________________________________________________________
     1
S&P Global rankings including the Corani silver project and San Luis gold-silver project.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/e902252f-6a5e-406b-b825-05aab416988e 

https://www.globenewswire.com/NewsRoom/AttachmentNg/2c9dfed5-fcee-4bdf-8d4d-108b63ffd811 

https://www.globenewswire.com/NewsRoom/AttachmentNg/6b3b8afb-8284-417d-bdc1-69b6b3cc73a9 

https://www.globenewswire.com/NewsRoom/AttachmentNg/bf998bca-3a3c-4ed2-9730-f3e8df85cd9d 

https://www.globenewswire.com/NewsRoom/AttachmentNg/c82f9e99-e185-4f54-833b-d6c85d5aedbd

https://www.globenewswire.com/NewsRoom/AttachmentNg/eb75a761-2f15-4c38-a0d2-999104be651d

Filing Exhibits & Attachments

1 document