[10-Q] Westwater Resources, Inc. Quarterly Earnings Report
Westwater Resources, Inc. is a development-stage battery-grade graphite company advancing its Kellyton Graphite Plant and the Coosa Graphite Deposit. The company reported a $6.5 million net loss for the six months ended June 30, 2025, and ended the period with $6.7 million in cash, $150.5 million of total assets and which exceed current assets of $7.3 million, prompting management to disclose that substantial doubt exists about the company’s ability to continue as a going concern.
Westwater expects Phase I of Kellyton to cost $245 million, has incurred approximately $124.4 million to date, and projects Phase I capacity of 12,500 metric tons per year of CSPG. The company closed a $5.0 million Series A-1 convertible note and subsequently agreed to a $5.0 million Series B-1 offering, retains available equity facilities of approximately $47.3 million (ATM) and $26.3 million (Lincoln Park), and continues construction and customer qualification activities while seeking additional financing to complete Phase I.
Westwater Resources, Inc. è una società in fase di sviluppo specializzata in grafite per batterie e sta portando avanti il Kellyton Graphite Plant e il Coosa Graphite Deposit. La società ha registrato una perdita netta di 6,5 milioni di dollari nei sei mesi chiusi al 30 giugno 2025 e ha chiuso il periodo con 6,7 milioni di dollari in cassa, 150,5 milioni di dollari di attività totali e 14,3 milioni di dollari di passività correnti che superano le attività correnti di 7,3 milioni di dollari, inducendo la direzione a comunicare che sussistono dubbi rilevanti sulla capacità della società di proseguire come going concern.
Westwater prevede che la Fase I di Kellyton costerà 245 milioni di dollari, ha già sostenuto circa 124,4 milioni di dollari e stima una capacità della Fase I di 12.500 tonnellate metriche all’anno di CSPG. La società ha chiuso un convertibile Series A-1 da 5,0 milioni di dollari e ha successivamente concordato un’offerta Series B-1 da 5,0 milioni di dollari, mantiene linee azionarie disponibili per circa 47,3 milioni (ATM) e 26,3 milioni (Lincoln Park), e continua la costruzione e le attività di qualificazione clienti mentre cerca finanziamenti aggiuntivi per completare la Fase I.
Westwater Resources, Inc. es una empresa en fase de desarrollo dedicada a la grafita de grado para baterías, que avanza con la planta Kellyton Graphite Plant y el depósito Coosa Graphite Deposit. La compañía registró una pérdida neta de 6,5 millones de dólares en los seis meses cerrados el 30 de junio de 2025 y finalizó el periodo con 6,7 millones de dólares en efectivo, 150,5 millones de dólares en activos totales y 14,3 millones de dólares en pasivos corrientes que superan los activos corrientes de 7,3 millones de dólares, lo que llevó a la dirección a indicar que existen dudas significativas sobre la capacidad de la compañía para continuar como empresa en funcionamiento.
Westwater espera que la Fase I de Kellyton cueste 245 millones de dólares, ha incurrido aproximadamente en 124,4 millones de dólares hasta la fecha y proyecta una capacidad de Fase I de 12.500 toneladas métricas por año de CSPG. La compañía cerró una nota convertible Series A-1 por 5,0 millones de dólares y posteriormente acordó una oferta Series B-1 por 5,0 millones de dólares, dispone de facilidades de capital disponibles por aproximadamente 47,3 millones (ATM) y 26,3 millones (Lincoln Park), y continúa con la construcción y las actividades de calificación de clientes mientras busca financiamiento adicional para completar la Fase I.
Westwater Resources, Inc.는 배터리급 흑연을 개발하는 개발 단계 기업으로 Kellyton Graphite Plant와 Coosa Graphite Deposit을 진행하고 있습니다. 회사는 2025년 6월 30일로 종료된 6개월 동안 순손실 6.5백만 달러를 보고했으며, 해당 기간 말 현금 6.7백만 달러, 총자산 150.5백만 달러와 유동자산 7.3백만 달러를 밑도는 유동부채 14.3백만 달러를 보유해 경영진이 회사의 계속기업 존속 능력에 중대한 의문이 있다고 공시했습니다.
Westwater는 Kellyton 1단계 비용을 245백만 달러로 예상하고 있으며 현재까지 약 124.4백만 달러를 지출했고, 1단계의 CSPG 연간 생산능력을 12,500 메트릭톤으로 예상합니다. 회사는 Series A-1 전환사채 5.0백만 달러를 완료했으며 이후 Series B-1 5.0백만 달러 제공에 합의했으며, 약 47.3백만 달러(ATM) 및 26.3백만 달러(Lincoln Park)의 가용 자본 수단을 보유하고, 1단계 완료를 위해 추가 자금 조달을 모색하는 한편 건설과 고객 인증 작업을 계속하고 있습니다.
Westwater Resources, Inc. est une société en phase de développement spécialisée dans le graphite de qualité batterie, qui fait progresser le Kellyton Graphite Plant et le Coosa Graphite Deposit. La société a enregistré une perte nette de 6,5 millions de dollars sur les six mois clos le 30 juin 2025 et a terminé la période avec 6,7 millions de dollars en liquidités, 150,5 millions de dollars d'actifs au total et 14,3 millions de dollars de passifs courants dépassant les actifs courants de 7,3 millions de dollars, ce qui a amené la direction à indiquer qu'il existait des doutes importants quant à la capacité de la société à poursuivre son activité.
Westwater prévoit que la Phase I de Kellyton coûtera 245 millions de dollars, a engagé environ 124,4 millions de dollars à ce jour et projette une capacité de Phase I de 12 500 tonnes métriques par an de CSPG. La société a conclu une obligation convertible Series A-1 de 5,0 millions de dollars et a ensuite convenu d'une offre Series B-1 de 5,0 millions de dollars, dispose de facilités d'équité disponibles d'environ 47,3 millions (ATM) et 26,3 millions (Lincoln Park), et poursuit la construction et les activités de qualification clients tout en cherchant des financements supplémentaires pour achever la Phase I.
Westwater Resources, Inc. ist ein Unternehmen in der Entwicklungsphase für batterietaugliches Graphit und treibt das Kellyton Graphite Plant sowie das Coosa Graphite Deposit voran. Das Unternehmen meldete einen Nettoverlust von 6,5 Millionen US-Dollar für die sechs Monate zum 30. Juni 2025 und schloss den Zeitraum mit 6,7 Millionen US-Dollar an liquiden Mitteln, 150,5 Millionen US-Dollar an Gesamtvermögen und 14,3 Millionen US-Dollar an kurzfristigen Verbindlichkeiten ab, die die kurzfristigen Vermögenswerte von 7,3 Millionen US-Dollar übersteigen, weshalb das Management erhebliche Zweifel an der Fortführungsfähigkeit des Unternehmens äußerte.
Westwater rechnet mit Kosten von 245 Millionen US-Dollar für Phase I von Kellyton, hat bislang rund 124,4 Millionen US-Dollar aufgewendet und prognostiziert eine Kapazität von 12.500 metrischen Tonnen pro Jahr CSPG für Phase I. Das Unternehmen schloss eine Series A-1 Wandelanleihe über 5,0 Millionen US-Dollar ab und vereinbarte anschließend ein Series B-1 Angebot über 5,0 Millionen US-Dollar, hält verfügbare Eigenkapitalfazilitäten von etwa 47,3 Millionen (ATM) und 26,3 Millionen (Lincoln Park) und setzt Bau- sowie Kundenqualifizierungsarbeiten fort, während es zusätzliche Finanzierung zur Fertigstellung von Phase I sucht.
- None.
- None.
Insights
TL;DR Westwater shows operational progress and customer traction but faces near-term funding and dilution risks while burning cash.
The company demonstrates material project advancement: equipment delivery (~85% of Phase I equipment received), commissioning of a micronization and spheroidization mill and production of >1 mt of CSPG qualification samples. Secured offtake for 100% of anticipated Phase I output de-risks near-term commercial uptake. However, the balance sheet shows current liabilities ($14.3M) exceed current assets ($7.3M) and a disclosed going-concern qualification. Recent financings include a $5.0M Series A-1 (fair-value measured liability) and a subsequent $5.0M Series B-1, plus available capacity under ATM and Lincoln Park facilities. Key near-term drivers are successful syndication of the targeted ~$150M construction debt facility and the timing of additional equity or debt to complete Phase I.
TL;DR Project progress is offset by liquidity strain and covenant/dilution risks that could materially affect execution if funding fails.
Material risks include the going-concern disclosure and a minimum cash covenant of $2.25M under the Series A-1 notes which constrains liquidity flexibility. The company’s plan relies on a large external secured debt syndication (~$150M) and further equity draws; market volatility or failure to syndicate would likely force construction delays or strategic changes and could trigger impairment reviews. Convertible note mechanics (Series A-1 convertible at up to $0.63, convertible into ~9.13M shares at that cap) introduce dilution pressure and conversion caps that may limit immediate conversions but will affect capitalization if converted. These are material execution risks for investors to monitor.
Westwater Resources, Inc. è una società in fase di sviluppo specializzata in grafite per batterie e sta portando avanti il Kellyton Graphite Plant e il Coosa Graphite Deposit. La società ha registrato una perdita netta di 6,5 milioni di dollari nei sei mesi chiusi al 30 giugno 2025 e ha chiuso il periodo con 6,7 milioni di dollari in cassa, 150,5 milioni di dollari di attività totali e 14,3 milioni di dollari di passività correnti che superano le attività correnti di 7,3 milioni di dollari, inducendo la direzione a comunicare che sussistono dubbi rilevanti sulla capacità della società di proseguire come going concern.
Westwater prevede che la Fase I di Kellyton costerà 245 milioni di dollari, ha già sostenuto circa 124,4 milioni di dollari e stima una capacità della Fase I di 12.500 tonnellate metriche all’anno di CSPG. La società ha chiuso un convertibile Series A-1 da 5,0 milioni di dollari e ha successivamente concordato un’offerta Series B-1 da 5,0 milioni di dollari, mantiene linee azionarie disponibili per circa 47,3 milioni (ATM) e 26,3 milioni (Lincoln Park), e continua la costruzione e le attività di qualificazione clienti mentre cerca finanziamenti aggiuntivi per completare la Fase I.
Westwater Resources, Inc. es una empresa en fase de desarrollo dedicada a la grafita de grado para baterías, que avanza con la planta Kellyton Graphite Plant y el depósito Coosa Graphite Deposit. La compañía registró una pérdida neta de 6,5 millones de dólares en los seis meses cerrados el 30 de junio de 2025 y finalizó el periodo con 6,7 millones de dólares en efectivo, 150,5 millones de dólares en activos totales y 14,3 millones de dólares en pasivos corrientes que superan los activos corrientes de 7,3 millones de dólares, lo que llevó a la dirección a indicar que existen dudas significativas sobre la capacidad de la compañía para continuar como empresa en funcionamiento.
Westwater espera que la Fase I de Kellyton cueste 245 millones de dólares, ha incurrido aproximadamente en 124,4 millones de dólares hasta la fecha y proyecta una capacidad de Fase I de 12.500 toneladas métricas por año de CSPG. La compañía cerró una nota convertible Series A-1 por 5,0 millones de dólares y posteriormente acordó una oferta Series B-1 por 5,0 millones de dólares, dispone de facilidades de capital disponibles por aproximadamente 47,3 millones (ATM) y 26,3 millones (Lincoln Park), y continúa con la construcción y las actividades de calificación de clientes mientras busca financiamiento adicional para completar la Fase I.
Westwater Resources, Inc.는 배터리급 흑연을 개발하는 개발 단계 기업으로 Kellyton Graphite Plant와 Coosa Graphite Deposit을 진행하고 있습니다. 회사는 2025년 6월 30일로 종료된 6개월 동안 순손실 6.5백만 달러를 보고했으며, 해당 기간 말 현금 6.7백만 달러, 총자산 150.5백만 달러와 유동자산 7.3백만 달러를 밑도는 유동부채 14.3백만 달러를 보유해 경영진이 회사의 계속기업 존속 능력에 중대한 의문이 있다고 공시했습니다.
Westwater는 Kellyton 1단계 비용을 245백만 달러로 예상하고 있으며 현재까지 약 124.4백만 달러를 지출했고, 1단계의 CSPG 연간 생산능력을 12,500 메트릭톤으로 예상합니다. 회사는 Series A-1 전환사채 5.0백만 달러를 완료했으며 이후 Series B-1 5.0백만 달러 제공에 합의했으며, 약 47.3백만 달러(ATM) 및 26.3백만 달러(Lincoln Park)의 가용 자본 수단을 보유하고, 1단계 완료를 위해 추가 자금 조달을 모색하는 한편 건설과 고객 인증 작업을 계속하고 있습니다.
Westwater Resources, Inc. est une société en phase de développement spécialisée dans le graphite de qualité batterie, qui fait progresser le Kellyton Graphite Plant et le Coosa Graphite Deposit. La société a enregistré une perte nette de 6,5 millions de dollars sur les six mois clos le 30 juin 2025 et a terminé la période avec 6,7 millions de dollars en liquidités, 150,5 millions de dollars d'actifs au total et 14,3 millions de dollars de passifs courants dépassant les actifs courants de 7,3 millions de dollars, ce qui a amené la direction à indiquer qu'il existait des doutes importants quant à la capacité de la société à poursuivre son activité.
Westwater prévoit que la Phase I de Kellyton coûtera 245 millions de dollars, a engagé environ 124,4 millions de dollars à ce jour et projette une capacité de Phase I de 12 500 tonnes métriques par an de CSPG. La société a conclu une obligation convertible Series A-1 de 5,0 millions de dollars et a ensuite convenu d'une offre Series B-1 de 5,0 millions de dollars, dispose de facilités d'équité disponibles d'environ 47,3 millions (ATM) et 26,3 millions (Lincoln Park), et poursuit la construction et les activités de qualification clients tout en cherchant des financements supplémentaires pour achever la Phase I.
Westwater Resources, Inc. ist ein Unternehmen in der Entwicklungsphase für batterietaugliches Graphit und treibt das Kellyton Graphite Plant sowie das Coosa Graphite Deposit voran. Das Unternehmen meldete einen Nettoverlust von 6,5 Millionen US-Dollar für die sechs Monate zum 30. Juni 2025 und schloss den Zeitraum mit 6,7 Millionen US-Dollar an liquiden Mitteln, 150,5 Millionen US-Dollar an Gesamtvermögen und 14,3 Millionen US-Dollar an kurzfristigen Verbindlichkeiten ab, die die kurzfristigen Vermögenswerte von 7,3 Millionen US-Dollar übersteigen, weshalb das Management erhebliche Zweifel an der Fortführungsfähigkeit des Unternehmens äußerte.
Westwater rechnet mit Kosten von 245 Millionen US-Dollar für Phase I von Kellyton, hat bislang rund 124,4 Millionen US-Dollar aufgewendet und prognostiziert eine Kapazität von 12.500 metrischen Tonnen pro Jahr CSPG für Phase I. Das Unternehmen schloss eine Series A-1 Wandelanleihe über 5,0 Millionen US-Dollar ab und vereinbarte anschließend ein Series B-1 Angebot über 5,0 Millionen US-Dollar, hält verfügbare Eigenkapitalfazilitäten von etwa 47,3 Millionen (ATM) und 26,3 Millionen (Lincoln Park) und setzt Bau- sowie Kundenqualifizierungsarbeiten fort, während es zusätzliche Finanzierung zur Fertigstellung von Phase I sucht.