Helium One Global (HLOGF) has provided an update on its Galactica-Pegasus helium development project in Colorado, where it holds a 50% working interest. The company reports that the initial Galactica facility development is proceeding as planned, with site preparatory work largely complete and first helium production on schedule for December 2025.

Key developments include: completion of surveying for gathering lines, plant site, and access roads; finalization of technology vendor selection for amine/CO2 removal and helium recovery units; and securing all necessary construction permits. The project timeline indicates first helium production in December 2025 and first CO2 production in H1 2026, with the Galactica plant processing facility ramping up as wells are tied in during H1 2026.

Helium One Global (HLOGF) ha fornito un aggiornamento sul progetto di sviluppo di elio Galactica-Pegasus in Colorado, dove detiene il 50% di interesse operativo. L’azienda riferisce che lo sviluppo iniziale della struttura Galactica procede come previsto, con i lavori preparatori del sito essenzialmente completati e la prima produzione di elio prevista per dicembre 2025.

Gli sviluppi chiave includono: completamento della rilevazione per le linee di raccolta, sito dell’impianto e strade di accesso; finalizzazione della selezione del fornitore tecnologico per la rimozione amina/CO2 e unità di recupero dell’elio; e l’ottenimento di tutti i permessi di costruzione necessari. La timeline del progetto indica la prima produzione di elio a dicembre 2025 e la prima produzione di CO2 nel primo semestre del 2026, con l’impianto Galactica che accelera una volta che i pozzi saranno allacciati nel corso del primo semestre del 2026.

Helium One Global (HLOGF) ha proporcionado una actualización sobre su proyecto de desarrollo de helio Galactica-Pegasus en Colorado, donde posee un interés de trabajo del 50%. La empresa informa que la infraestructura inicial de la instalación Galactica avanza según lo previsto, con los trabajos de preparación del sitio prácticamente completos y la primera producción de helio programada para diciembre de 2025.

Los avances clave incluyen: finalización de la topografía para las líneas de recolección, el sitio de la planta y las vías de acceso; la finalización de la selección del proveedor tecnológico para la eliminación de amina/CO2 y las unidades de recuperación de helio; y la obtención de todos los permisos de construcción necesarios. La cronología del proyecto indica primera producción de helio en diciembre de 2025 y primera producción de CO2 en la mitad de 2026, con la planta Galactica aumentando su capacidad a medida que se conectan los pozos durante la primera mitad de 2026.

Helium One Global (HLOGF)가 콜로라도에서 50%의 지분을 보유하고 있는 Galactica-Pegasus 헬륨 개발 프로젝트에 대한 업데이트를 제공했습니다. 회사는 Galactica 시설 개발이 계획대로 진행 중이며, 현장 준비 작업이 대체로 완료되었고 2025년 12월에 첫 헬륨 생산이 예정되어 있다고 보고합니다.

주요 개발 내용으로는 수집 배관, 플랜트 부지, 접근로에 대한 측량 완료; 아민/CO2 제거 및 헬륨 회수 유닛에 대한 기술 공급업체 선정을 최종 확정; 모든 필요한 건설 허가를 확보하는 것이 포함됩니다. 프로젝트 일정상 2025년 12월 첫 헬륨 생산2026년 상반기 CO2 첫 생산이 예상되며, wells가 2026년 상반기에 연결되면서 Galactica 공장 가동이 점진적으로 확대될 예정입니다.

Helium One Global (HLOGF) a fourni une mise à jour sur son projet de développement d’hélium Galactica-Pegasus au Colorado, où elle détient 50 % des droits d’exploitation. La société indique que le développement initial de l’installation Galactica se déroule comme prévu, le travail de préparation du site étant en grande partie terminé et la première production d’hélium prévue pour décembre 2025.

Parmi les avancées clés: achèvement des relevés pour les conduites de collecte, le site de l’usine et les routes d’accès; finalisation de la sélection du fournisseur de technologie pour l’élimination d’amines/CO2 et les unités de récupération d’hélium; et sécurisation de tous les permis de construction nécessaires. Le calendrier du projet prévoit la première production d’hélium en décembre 2025 et la première production de CO2 au cours du premier semestre 2026, l’usine Galactica opérant à plein régime à mesure que les puits seront raccordés au cours du premier semestre 2026.

Helium One Global (HLOGF) hat ein Update zum Galactica-Pegasus-Heliumentwicklungsprojekt in Colorado gegeben, an dem sie 50% Betriebsbeteiligung hält. Das Unternehmen berichtet, dass die erste Galactica-Anlage wie geplant voranschreitet, die Vorbereitungsarbeiten auf dem Standort größtenteils abgeschlossen sind und die erste Heliumproduktion für Dezember 2025 geplant ist.

Zu den wichtigen Entwicklungen gehören: Abschluss der Vermessung für Sammelleitungen, Standort der Anlage und Zufahrtsstraßen; Finalisierung der Auswahl des Technologielieferanten für Amine/CO2-Entfernung und Heliumrückgewinnungseinheiten; sowie Sicherstellung aller erforderlichen Baugenehmigungen. Der Projektzeitplan sieht erste Heliumproduktion im Dezember 2025 und erste CO2-Produktion im ersten Halbjahr 2026 vor, wobei die Galactica-Anlage schrittweise in Betrieb geht, während die Bohrungen im ersten Halbjahr 2026 angeschlossen werden.

Helium One Global (HLOGF) قدّمت تحديثاً حول مشروع تطوير الهليوم Galactica-Pegasus في كولورادو، حيث تمتلك حصة تشغيلية بنسبة 50%. وتفيد الشركة بأن تطور منشأة Galactica الأولي يسير كما هو مخطط، مع الانتهاء إلى حد كبير من أعمال تجهيز الموقع والإنتاج الأول للهليوم المقرر في ديسمبر 2025.

وتشمل التطورات الرئيسية: استكمال المسح لخطوط التجميع وموقع المنشأة والطرق، والانتهاء من اختيار مزود التكنولوجيا لإزالة الأمين/CO2 ووحدات استرداد الهليوم، وت secured جميع تصاريح البناء اللازمة. ويشير الجدول الزمني للمشروع إلى الإنتاج الأول للهليوم في ديسمبر 2025 والإنتاج الأول لـCO2 في النصف الأول من 2026، مع زيادة تشغيلية لمرفق Galactica حين يتم ربط الآبار خلال النصف الأول من 2026.

Helium One Global (HLOGF) 对其在科罗拉多州的 Galactica-Pegasus 氦气开发项目提供了更新,该公司在该项目中拥有 50% 的工作权益。公司表示 Galactica 设施初步开发按计划进行,现场准备工作基本完成,预计于 2025 年 12 月开始首次氦气产量。

关键进展包括:完成用于集管线、厂址和通道的测量工作;最终确定用于胺/CO2 去除与氦气回收单元的技术供应商;以及获取所有必要的施工许可。项目时间表显示 2025 年 12 月首次氦气产量,以及 2026 年上半年首次 CO2 产量,Galactica 工厂在 2026 年上半年油气井并网时将逐步提升处理能力。

Positive
  • Project remains on schedule for first helium production in December 2025
  • All construction permits secured and site preparatory work largely complete
  • Successful completion of six well development drilling campaign in H1 2025
  • Wells demonstrated promising flow potential with helium concentrations up to 3.3%
Negative
  • CO2 removal systems required as part of production process
  • Full production capacity won't be reached until H1 2026

LONDON, UK / ACCESS Newswire / September 18, 2025 / Helium One Global (AIM:HE1), the primary helium explorer in Tanzania with a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA ("the Galactica Project"), provides an update following the Blue Star Helium (ASX: BNL) ("Blue Star") announcement issued today regarding the Galactica Project.

Highlights

  • Initial Galactica facility development is proceeding as planned

  • Site preparatory work now largely complete

  • First helium production on schedule for December

Details

The project continues to advance steadily, with foundational and preparatory work now largely complete. All activities remain on track for plant commissioning and operational readiness during December 2025.

Site pre-development activities have progressed and all relevant construction permits now in place.

All surveying of gathering lines, the plant site and access road locations are complete.

Final engineering plans for the gas gathering system are nearing completion, and the contractor has been selected.

General facilities engineering is also nearing completion and critical equipment packages have been selected. Technology review and vendor selection for the amine/CO2 removal unit and the helium recovery unit are both finalised, with the balance of plant equipment identification also completed. Elements of the amine/CO2 removal unit are depicted in the contractor's yard below.

The project remains on schedule to deliver first helium in December 2025 and first CO2 in H1 2026. The Galactica plant processing facility will be ramped up as wells are tied in during H1 2026.

Lorna Blaisse, Chief Executive Officer, commented:

"We are very pleased to see this phase of the development progressing towards first gas in Q4. With contractor selection progressing and relevant permitting in place, we are excited to see the installation and commissioning process come to fruition over the coming months."

For further information, please contact:

Helium One Global Ltd

+44 20 7920 3150

Lorna Blaisse, CEO
Graham Jacobs, Finance and Commercial Director

Panmure LiberumLimited (Nominated Adviser and Joint Broker)
Scott Mathieson
Gaya Bhatt

+44 20 3100 2000

Zeus Capital Limited (Joint Broker)
Simon Johnson
Louisa Waddell

+44 20 3829 5000

Tavistock(Financial PR)
Nick Elwes

+44 20 7920 3150

Further information on the Company can be found on its website at www.helium-one.com

Notes to Editors

Helium One Global, the primary helium explorer in Tanzania with a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA. The Company holds helium licenses within two distinct helium project areas, across two continents. With an expanding global footprint, the company has the potential to become a strategic player in resolving a supply-constrained helium market.

The Company's flagship southern Rukwa Project is located within the southern Rukwa Rift Basin in south-west Tanzania. This project entering a full appraisal and development stage following the success of the 2023/24 exploration drilling campaign, which proved a helium discovery at Itumbula West-1 and, following an extended well test ("EWT"), successfully flowed 5.5% helium continually to surface in Q3 2024.

Following the success of the EWT, the Company filed a Mining Licence ("ML") application with the Tanzania Mining Commission in September 2024 and the 480km2 ML was formally awarded to the Company in July 2025.

The Company also owns a 50% working interest in the Galactica-Pegasus helium development project in Las Animas County, Colorado, USA. This project is operated by Blue Star Helium Ltd (ASX: BNL) and has successfully completed a six well development drilling campaign in H1 2025. The completion of the development programme is a key component of the broader Galactica-Pegasus development strategy; aimed at progressing the helium and CO2 discoveries to near-term commercial production. This programme has seen a systematic approach to developing the extensive Lyons Formation reservoir. The programme has delivered encouraging results, in line with expectations, consistently encountering good helium (up to 3.3% He) and CO2 concentrations in the target formation and demonstrating promising flow potential. The next steps will see the Galactica wells tied into initial production in Q4 2025.

Helium One is listed on the AIM market of the London Stock Exchange with the ticker of HE1 and on the OTCQB in the United States with the ticker HLOGF.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

SOURCE: Helium One Global Ltd



View the original press release on ACCESS Newswire

FAQ

When will Helium One Global (HLOGF) begin helium production at the Galactica Project?

Helium One Global is scheduled to begin helium production at the Galactica Project in December 2025, with full ramp-up expected in H1 2026.

What is Helium One Global's ownership stake in the Galactica-Pegasus project?

Helium One Global holds a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA, with Blue Star Helium (ASX: BNL) as the operator.

What helium concentrations were found in the Galactica-Pegasus development wells?

The development drilling program encountered helium concentrations of up to 3.3% He in the target Lyons Formation, demonstrating promising flow potential.

What is the current status of the Galactica facility development?

The facility development is proceeding as planned with site preparatory work largely complete, all construction permits in place, and final engineering plans nearing completion for the gas gathering system.

When will the Galactica plant reach full production capacity?

The Galactica plant processing facility will be ramped up during H1 2026 as additional wells are tied into the system, with first CO2 production also expected in H1 2026.