STOCK TITAN

Highlander Silver Showcases Development Progress in Corani Photo Update

Most work packages have been awarded, while long-lead-time equipment ordering has begun.

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags

Highlander Silver (HSLV) provided a development update on its Corani Silver Project in Peru, detailing construction progress and procurement activity. Road construction has completed 40 km, while substation and transmission-line construction has completed 2 km. A 600-bed camp is under construction, and infrastructure earthworks continue. Long-lead-time equipment ordering has begun, and most work packages have been awarded.

Loading...
Loading translation...

Positive

  • Minor pointRoad construction has completed 40 km, with internal and external roads still under construction.
  • Minor pointSubstation and transmission line are under construction, with 2 km completed.
  • Minor point600-bed camp and related facilities are under construction.
  • Minor pointEarthworks continue for infrastructure, plant, pits and collection ponds.
  • Minor pointLong-lead-time equipment order process has commenced.
  • Minor pointMajority of work packages awarded to international, Peruvian and local firms.

Negative

  • None.
Argus 15 min delay 2 alerts
+6.52% vs previous close $4.25 last price 26.8x rel. volume Open Argus
Details

Market Reaction – HSLV

$4.19 – $4.25 Day Range
$864.97M Mkt Cap at Last Price

On Nov 4, the day this news came out, the latest delayed price for HSLV is 6.52% above the previous close. Our momentum scanner has recorded 2 alerts for this stock so far that day. The latest delayed price is $4.25. Relative volume is exceptionally heavy at 26.8x what this stock usually trades by this time of day.

Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.

Key Figures

On-site workforce: 350 people Technical services team: 70 people Camp capacity: 600 beds +2 more
On-site workforce
350 people
Corani project development
Technical services team
70 people
Led by Carlos Ojeda
Camp capacity
600 beds
Camp and related facilities under construction
Roads completed
40 km
Internal and external roads
Transmission line completed
2 km
Transmission line under construction

Historical Context

1 past event · Latest: Jul 07
1 event
  1. Jul 07

    site development

    24h Move
    -7.4%

    Workforce exceeded 300, with camp, facilities, earthworks, roads and substation construction underway.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

TORONTO, Nov. 04, 2026 (GLOBE NEWSWIRE) -- Highlander Silver Corp. (TSX, NYSE American: HSLV) (“Highlander Silver” or the “Company”) is pleased to provide a photo update showcasing development progress at its Corani Silver Project in Peru.

Site Development – Key Milestones

  • 350-person workforce on site, hired preferentially from local communities
  • 70-person technical services team led by Carlos Ojeda, Vice President & General Manager, spanning all aspects of project design, control and execution
  • 600-bed camp and related facilities under construction
  • Internal and external roads under construction, with 40 km completed
  • Earthworks for infrastructure, plant, pits and collection ponds continuing
  • Substation and transmission line under construction, with 2 km completed
  • Long-lead-time equipment order process commenced
  • Majority of work packages awarded to leading international, Peruvian and local firms

Images

Corani_Photo_1_1

Corani_Photo_2

Corani_Photo_3

Corani_Photo_4

Corani_Photo_5

On behalf of Highlander Silver

“Daniel Earle”
President and CEO

Information contact

Arun Lamba, Vice President Corporate Development
alamba@highlandersilver.com

About Highlander Silver

Highlander Silver is a high-quality silver-growth company developing a portfolio of advanced-stage assets in Peru, including the bonanza-grade San Luis gold-silver project, which ranks among the 10 highest-grade projects globally in both gold and silver categories, and the Corani Silver Project, the largest silver deposit in development globally.1 The Company also operates the Mercedes gold-silver mine in Mexico. Highlander Silver's major shareholders include the Augusta Group, the Lundin family, and Eric Sprott.

Forward-looking statements

Certain information contained in this news release constitutes “forward-looking information” under Canadian securities legislation. This includes, but is not limited to, future construction and development at Corani. Such forward-looking information or statements can be identified by the use of words such as “anticipates”, “expects”, “intends”, “believes”, “plans”, “may”, “subject to” or “underway” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “will” be taken, occur, or be achieved. Forward-looking information is based on management’s reasonable assumptions, estimates, expectations, analyses and opinions, including: assumptions with regard to development of Corani; the ability to secure adequate financing; the Company maintaining its current strategy and objectives; and the Company’s ability to achieve its growth objectives. Forward-looking information involves known and unknown risks, uncertainties, and other factors which may cause the actual results, performance, or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance, or achievements expressed or implied by the forward-looking information. Such factors include, among others: general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of precious and base metals; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental or stock exchange approvals or financing; and risks related to the facility with Natixis CIB, including that definitive documentation may not be completed on the terms contemplated or at all, ongoing due diligence may not be completed to the satisfaction of Natixis CIB, conditions precedent may not be satisfied, the cost overrun facility may not be established on acceptable terms or at all, closing or drawdowns under the facility may be delayed or may not occur, interest rates may change, or project costs may increase, or the development of the Corani Silver Project may be delayed, cost more than anticipated or be adversely affected by technical, environmental, social, permitting, construction or other development risks. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that could cause actions, events or results to differ from those anticipated, estimated or intended. Forward-looking information contained herein is made as of the date of this news release. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management’s estimates or opinions should change, except as required by applicable securities laws. Accordingly, the reader is cautioned not to place undue reliance on forward-looking information.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/a2f182ea-4778-4548-b99f-67a3912bd6db

https://www.globenewswire.com/NewsRoom/AttachmentNg/6b359acf-9c8e-425d-afe2-40275d0bbb00

https://www.globenewswire.com/NewsRoom/AttachmentNg/383eb3a2-fdb4-45db-b5dd-0915362b61d5

https://www.globenewswire.com/NewsRoom/AttachmentNg/e7dc3b6f-095b-4983-856a-d2ca4b746834

https://www.globenewswire.com/NewsRoom/AttachmentNg/c5ad6032-0605-41f4-8663-aaffb4c0c596


1 S&P Global rankings including the Corani Silver Project and San Luis gold-silver project.


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What construction progress has Highlander Silver reported at Corani?

Corani has completed 40 km of roads, and substation and transmission-line construction has completed 2 km. A 600-bed camp and related facilities are under construction, while earthworks continue for infrastructure, plant, pits and collection ponds.

How many people are working on Highlander Silver's Corani project?

Corani has a 350-person workforce on site, hired preferentially from local communities. A 70-person technical services team led by Carlos Ojeda, Vice President and General Manager, covers project design, control and execution.

Keep reading