Namib Minerals Completes Commissioning of Expanded Milling Plant at How Mine

How Mine’s expected annualized run-rate is more than 30,000 ounces at current grades as the company turns to ramp-up.

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags

Namib Minerals (NAMM) completed commissioning of its expanded milling plant at How Mine ahead of the previously communicated mid-October deadline. The company expects monthly processing capacity to rise from approximately 40,500 tonnes to 55,000 tonnes, an increase of approximately 36%. Full capacity is targeted for December 2026. Redwing Mine's restart remains on schedule, with first gold targeted by January 2027.

Loading...
Loading translation...
5 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 0 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate pointHow Mine expanded milling plant commissioning completed ahead of the previously communicated mid-October deadline.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Monthly processing capacity expected to rise approximately 36%, from approximately 40,500 tonnes to 55,000 tonnes.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.How Mine expected annualized run-rate is more than 30,000 ounces at current grades.
  • Minor point. Forward-looking: it has not happened yet and may not happen.How Mine full processing capacity of 55,000 tonnes per month targeted for December 2026.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Redwing Mine restart remains on schedule, with first gold targeted by January 2027.

Negative

  • None.

Key Figures

Monthly processing capacity: Approximately 40,500 to 55,000 tonnes Milling capacity increase: Approximately 36% Annualized run-rate target: More than 30,000 ounces +2 more
Monthly processing capacity
Approximately 40,500 to 55,000 tonnes
How Mine, following commissioning
Milling capacity increase
Approximately 36%
How Mine expanded plant
Annualized run-rate target
More than 30,000 ounces
At current grades
Full capacity target
December 2026
How Mine
First gold target
January 2027
Redwing Mine restart

Historical Context

1 past event · Latest: Oct 01
1 event
  1. Oct 01

    Mill expansion update

    24h Move
    +35.0%

    Expansion was substantially complete; commissioning was expected mid-October with approximately 36% more processing capacity.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

New York, Oct. 08, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (Nasdaq: NAMM), today announced the completion of commissioning of its expanded milling plant at How Mine. The Company notes the commissioning is ahead of the mid-October deadline previously communicated.

Completion of the plant installation and commissioning is expected to increase How Mine's monthly processing capacity from approximately 40,500 tonnes to 55,000 tonnes. The commissioning represents a significant milestone for the Company, with an expected increase in milling capacity of approximately 36%.

"Our focus now turns to a disciplined ramp-up to full capacity and to delivering the expected annualized run-rate of more than 30,000 ounces at current grades that we outlined on our recent call," said Tulani Sikwila, Chairman and CEO.

The Company’s focus now turns to ramping up processing capacity to 55,000 tonnes per month, with full capacity targeted to be achieved in December 2026. In parallel, the restart of Redwing Mine remains on schedule, with first gold targeted by January 2027.

About Namib Minerals

Namib Minerals (NASDAQ: NAMM) is a gold producer, developer and explorer with operations focused in Zimbabwe. Currently Namib Minerals operates the How Mine, an underground gold mine in Zimbabwe, and aims to restart two assets in Zimbabwe. For additional information, please visit namibminerals.com.

Forward-Looking Statements

This press release may include forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Any statements that refer to restarts of mines, future financing or other future events or circumstances, including any underlying assumptions, are also forward-looking statements. Forward-looking statements include, without limitation, statements regarding the Company’s governance and leadership structure, its financing programme and the planned restart of the Redwing Mine. Forward-looking statements are based on current expectations, are inherently subject to uncertainties and changes in circumstance, and speak only as of the date of such statement. There can be no assurance that future developments will be those that have been anticipated. These statements involve a number of risks and uncertainties described in the filings we make with the Securities and Exchange Commission, and you should carefully consider those factors. We caution you against placing undue reliance on forward-looking statements, which reflect current beliefs and are based on information currently available as of the date a forward-looking statement is made.

Contact:

Investor Relations:
Investor.relations@namibminerals.com



FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much will Namib Minerals’ How Mine milling capacity increase?

Monthly processing capacity is expected to increase from approximately 40,500 tonnes to 55,000 tonnes, or approximately 36%. Commissioning of the expanded plant is complete, and full capacity is targeted for December 2026.

What gold production run-rate does Namib Minerals expect at How Mine after ramp-up?

Namib Minerals expects an annualized run-rate of more than 30,000 ounces at current grades. The company is now focused on ramping up the expanded milling plant to full capacity.