Red Metal Resources (CSE: RMES; OTC: RMESF; FSE: I660) reported on the impact of unusually heavy mid-July 2026 rainfall near Vallenar, Chile, on its Carrizal Copper-Gold-Cobalt Property. Its geophysical contractor temporarily demobilized the induced polarization (IP) survey crew for about one week due to hazardous road access, then safely remobilized, and the company does not currently anticipate a material impact on the overall IP program timeline.

Mining operations at the Farellon 1/8 concession, conducted by lessee Minera KMT, continued without interruption after diversion trenches were built to protect the mine entrance and camp. Red Metal also recapped 2026 work to date, including a private placement, LiDAR and IP surveys, a lease and royalty agreement for Farellon 1/8, and capital markets initiatives. Next steps focus on completing the northern IP block at Carrizal as conditions permit and continuing small-scale mining at Farellon 1/8.

Loading...
Loading translation...

Positive

  • None.

Negative

  • None.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Vancouver, British Columbia--(Newsfile Corp. - July 30, 2026) - RED METAL RESOURCES LTD. (CSE: RMES) (OTC: RMESF) (FSE: I660) ("Red Metal" or the "Company") is providing an update on the impact of recent rainfall in the Vallenar area of Chile's Atacama Region on activities at its Carrizal Copper-Gold-Cobalt Property ("Carrizal" or the "Property"). As a safety precaution, the Company's induced polarization ("IP") survey crew temporarily demobilized from the site for approximately one week due to hazardous road conditions, while mining operations on the Property continued without interruption.

Impact of Recent Rainfall on Operations

The Vallenar area of Chile's Atacama Region experienced unusually heavy rainfall between approximately July 15 and 19, 2026, resulting in hazardous conditions on local roads and access routes to the Carrizal Property. In the interest of crew safety, the Company's geophysical contractor, Geophysical Studies Chile, temporarily demobilized the IP survey crew from site for approximately one week. The crew has since safely remobilized and the Company does not currently expect a material impact on the overall IP program timeline.

According to Chilean meteorological and disaster-response authorities, the Vallenar area recorded approximately 104 millimetres of rainfall over the five-day period from July 15th to 19th, including a peak daily total of approximately 50 millimetres on July 19. Vallenar's average annual rainfall is only about 30 to 55 millimetres, meaning the region received roughly two to three years' worth of its typical annual precipitation in less than a week. The Atacama Region is one of the driest inhabited places on Earth, and the storm prompted regional emergency declarations, widespread road closures and isolation of communities across the Atacama and Coquimbo regions. The event ranks among the most significant rainfall events to affect the region since the catastrophic Atacama floods of March 2015.

Mining operations at the Farellon 1/8 concession, carried out by the lessee Minera KMT, were not affected by the rains. The operator constructed diversion trenches to direct water away from the mine entrance and the on-site camp, protecting infrastructure and allowing mining activities to continue safely without interruption.

Red Metal Resources President and CEO, Caitlin Jeffs, stated, "The safety of anyone working on our properties is our first priority, and temporarily pulling the IP team off site during dangerous road conditions was the right decision. I am pleased that our mining operator acted proactively to protect the mine entrance and their camp with diversion trenches, allowing production to continue uninterrupted. Our thoughts are with the communities across the Atacama and Huasco regions affected by these storms."

2026 Work Completed to Date

  • Closed a non-brokered private placement financing in multiple tranches in the first quarter of 2026, strengthening the Company's treasury (see news releases January 8, 2026 and January 19, 2026).

  • Completed a LiDAR survey and structural interpretation over the Carrizal Property (see news releases dated February 4, 2026 and April 22, 2026).

  • Entered into a lease and royalty agreement with the lessee Minera KMT for the Farellon 1/8 concession and advanced small-scale mining and underground development, monitored through regular site visits by in-country staff (see news releases dated May 14, 2026 and July 7, 2026).

  • Actively working on a three-dimensional induced polarization (IP) survey at Carrizal on two high-priority blocks with Geophysical Studies Chile and reported preliminary results from the southern block, defining a kilometre-long chargeability target that remains open along strike and at depth (see news releases dated April 2, 2026, April 28, 2026, and July 16, 2026).

  • Strengthened its capital-markets presence, including engaging an investor relations firm and a market maker and receiving proceeds from the exercise of warrants (see news releases dated February 23, 2026, June 4, 2026 and June 23, 2026).

Next Steps

  • The IP survey crew to continue the northern block survey at Carrizal as road conditions permit.

  • Continue small-scale mining operations at the Farellon 1/8 concession under the lease and royalty arrangement.

About Red Metal Resources Ltd.

Red Metal Resources is a mineral exploration company focused on growth through acquiring, exploring and developing clean energy and strategic minerals projects. The Company's current portfolio includes the Company's Chilean projects, located in the prolific Candelaria Iron Oxide Copper-Gold (IOCG) belt of Chile's coastal Cordillera, as well as claims in Quebec and Ontario, Canada.

Red Metal is quoted on the Canadian Securities Exchange under the symbol RMES, on the OTC Link alternative trading system on the OTC Expert marketplace under the symbol RMESF, and on the Frankfurt Stock Exchange under the symbol I660.

For more information, please visit www.redmetalresources.com.

Contact:
Red Metal Resources Ltd.
Caitlin Jeffs
President & CEO
1-866-907-5403
invest@redmetalresources.com
www.redmetalresources.com

Forward-Looking Statements - All statements in this press release, other than statements of historical fact, are "forward-looking information" within the meaning of applicable securities laws. Red Metal provides forward-looking statements for the purpose of conveying information about current expectations and plans relating to the future and readers are cautioned that such statements may not be appropriate for other purposes. By its nature, this information is subject to inherent risks and uncertainties that may be general or specific, and which give rise to the possibility that expectations, forecasts, predictions, projections or conclusions will not prove to be accurate, that assumptions may not be correct and that objectives, strategic goals and priorities will not be achieved. These risks and uncertainties include but are not limited to the ability to raise adequate financing, receipt of required approvals, as well as those risks and uncertainties identified and reported in Red Metal's public filings under its SEDAR+ profile at www.sedarplus.ca. Although Red Metal has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Red Metal disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise unless required by law.

Neither the Canadian Securities Exchange nor the Market Regulator (as that term is defined in the policies of the Canadian Securities Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/307266

FAQ

How did recent rainfall near Vallenar affect Red Metal Resources (RMESF) operations at Carrizal?

The heavy July 2026 rainfall temporarily halted Carrizal’s IP survey for about one week. According to Red Metal, the IP crew demobilized for safety due to hazardous roads but has remobilized, and no material impact is currently expected on the IP program timeline.

Did the July 2026 storms disrupt mining at Red Metal’s Farellon 1/8 concession (RMESF)?

Mining at Farellon 1/8 continued without interruption during the storms. According to Red Metal, lessee Minera KMT constructed diversion trenches to direct water away from the mine entrance and camp, protecting on-site infrastructure and allowing operations to proceed safely.

What work has Red Metal Resources (RMESF) completed at Carrizal in 2026 so far?

In 2026, Red Metal completed LiDAR and structural interpretation and advanced a 3D IP survey at Carrizal. According to Red Metal, preliminary southern block IP results defined a kilometre-long chargeability target open along strike and at depth on the property.

What financing and capital markets steps has Red Metal Resources (RMESF) taken in 2026?

Red Metal closed a non-brokered private placement in multiple Q1 2026 tranches, strengthening its treasury. According to Red Metal, it also engaged an investor relations firm, a market maker, and received proceeds from warrant exercises to enhance its capital-markets presence.

What are the next operational steps for Red Metal Resources (RMESF) after the July 2026 rainfall?

Red Metal plans to continue the northern IP block survey at Carrizal as road conditions allow. According to Red Metal, it also intends to maintain small-scale mining and underground development at the Farellon 1/8 concession under the existing lease and royalty arrangement.

How severe was the July 2026 rainfall event in Chile’s Atacama Region affecting Red Metal (RMESF)?

The Vallenar area recorded about 104 millimetres of rain between July 15 and 19, 2026. According to Red Metal, this equaled roughly two to three years of typical annual precipitation, prompting emergency declarations, road closures and regional disruption across the Atacama and Coquimbo regions.