Salazar Resources' 25% El Domo Interest Remains Fully Carried Through Updated US$298 Million Construction Budget
Salazar will not fund the budget increase, while El Domo's production target moves four months later.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Salazar Resources (OTCQB: SRLZF) retains its fully carried 25% El Domo interest through commercial production despite an increased construction budget. Operator Silvercorp Metals updated the copper-gold project's budget to US$298.2 million, up US$14.6 million, approximately 5%, from February 2026. Salazar has no additional construction or development financing obligations.
Silvercorp now targets production in November 2027, four months later than planned, attributing the delay to extended rainfall. Construction spending reached US$90.9 million through September 30, 2026, leaving US$207.3 million. The budget retains US$14.3 million of contingency. External power-line construction is delayed pending CNEL reviews and approvals; prolonged generator use may increase operating costs. Salazar also began Yumi drilling in October, with first results expected in early December 2026, and plans Monja drilling for January 2027.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Major pointSalazar's 25% El Domo interest remains fully carried through commercial production, with no additional development or construction funding obligations.
- Moderate pointOpen-pit mining and stripping contract awarded to China Railway 19th Bureau Group for US$35 million, on a unit-cost basis. 58% of market cap
- Minor pointEl Domo construction spending reached US$90.9 million through September 30, 2026.
- Minor pointProcess plant site preparation completed; foundation and building work is in progress.
- Minor pointMost process plant equipment ordered with approximately 30% down payments; prefabricated structural steel shipped from factories.
4 minor points
- Minor pointFirst batch of major long lead-time equipment, including the mill, arrived at port in Ecuador.
- Minor pointSite substation construction is under way; ten generator sets totaling 17 MW are manufactured and ready for shipment.
- Minor point. Forward-looking: it has not happened yet and may not happen.Yumi drilling began in October 2026, with 1,500 metres planned and first results expected in early December 2026.
- Minor point. Forward-looking: it has not happened yet and may not happen.Monja drilling is scheduled to begin in January 2027.
Negative
- Moderate pointEl Domo budget increased US$14.6 million, approximately 5%, to US$298.2 million from the February 2026 estimate. 24% of market cap
- Moderate point. Forward-looking: it has not happened yet and may not happen.Production now targeted for November 2027, four months later; Silvercorp attributes the delay to extended rainfall.
- Moderate point. Forward-looking: it has not happened yet and may not happen.External power-line construction is delayed pending CNEL reviews and approvals; longer generator reliance may increase operating costs.
- Minor point. Forward-looking: it has not happened yet and may not happen.Production timing remains dependent on weather conditions and contractor performance.
- Minor pointContingency fell US$2.7 million to US$14.3 million, reducing the allowance for future increases rather than delivering direct savings.
2 minor points
- Minor pointTailings storage facility and non-contact water channel identified as main delay sources in the site preparation package.
- Minor pointSalazar has not independently verified the operator-provided El Domo information.
AI-generated analysis. How Rhea-AI works. Not financial advice.
Operator targets production in November 2027; US
Vancouver, British Columbia--(Newsfile Corp. - November 5, 2026) - Salazar Resources Limited (TSXV: SRL) (OTCQB: SRLZF) (FSE: CCG) ("Salazar" or the "Company") reports that Silvercorp Metals Inc. (TSX: SVM) (NYSE American: SVM) ("Silvercorp"), the operator of the Curipamba-El Domo copper-gold project ("El Domo" or the "Project"), has updated the Project's construction budget to US
More than half of the net budget increase, US
In its news release of October 27, 2026, the Company stated that it would report the updated schedule once the operator provided it. This news release fulfils that undertaking.
HIGHLIGHTS (AS REPORTED BY SILVERCORP IN ITS NEWS RELEASE DATED NOVEMBER 3, 2026)
Spending: US
$90.9 million to September 30, 2026, with US$207.3 million remaining. The budget includes US$36.7 million of value added tax.Schedule: production is now targeted for November 2027, four months later than previously planned. Silvercorp attributes the four-month delay to extended rainfall at site linked to the Super El Niño.
Budget: US
$298.2 million , a net increase of US$14.6 million (approximately5% ) from Silvercorp's February 4, 2026, estimate of US$283.6 million (the 2021 Feasibility Study budget was US$248 million ). Gross increases of US$24.4 million were partly offset by US$9.8 million of reductions.Main cost increases: diesel fuel (US
$8.3 million ), after Ecuador eliminated diesel subsidies; water management enhancements at the tailings storage facility ("TSF") (US$4.7 million ); processing plant construction (US$3.7 million ), following execution of the plant construction contract; site power equipment and distribution (US$2.4 million ); and new items, including two reactive power compensators and other power items (US$3.3 million ) and additional water-control works at the TSF (approximately US$2.0 million ).Offsetting reductions: US
$9.8 million , including a US$2.7 million reduction in contingency. Silvercorp notes that the contingency reduction is a lower allowance for future cost increases, not a direct cost saving. Owner's contingency of US$14.3 million remains in the budget.Mining contract: open-pit mining and stripping has been awarded to China Railway 19th Bureau Group Co., Ltd. on a unit-cost basis, valued at US
$35 million . The mining package budget has increased by US$5.0 million , of which US$4.7 million relates to diesel.Power: construction of the substation at the El Domo site is under way. Silvercorp now reports that only construction of the substation has commenced and that construction of the external power line has been delayed pending further reviews and approvals from CNEL. Silvercorp's October 19, 2026, news release, on which the Company's news release of October 27, 2026, was based, had reported that construction of the external power line had also commenced. Ten generator sets with a combined capacity of 17 MW have been manufactured and are ready to be shipped to site. Silvercorp notes that continued delays to the power line would require the Project to rely on the generator sets for longer, which may increase operating costs.
UPDATED BUDGET BY PACKAGE
Silvercorp's updated budget by package, compared with its February 4, 2026, estimate and actual expenditures to September 30, 2026, is summarised below (US$ million):
| Package | Feb 4, 2026 budget | Nov 3, 2026 updated budget | Spent to Sep 30, 2026 | Remaining |
| Package #1 - Site preparation, roads, channels, TSF and SWD | 57.4 | 57.2 | 26.7 | 30.5 |
| Package #2 - Open-pit mining and stripping | 35.0 | 40.0 | 2.4 | 37.6 |
| Package #3 - Processing plant construction and equipment | 54.8 | 62.2 | 14.1 | 48.1 |
| Construction and permanent camps | 7.0 | 6.3 | 3.2 | 3.1 |
| Packages #4 and #5 - Site infrastructure (bypass roads, power line, standby diesel generators, water treatment plant) | 45.4 | 49.3 | 16.6 | 32.7 |
| Direct costs sub-total | 199.3 | 215.1 | 63.0 | 152.1 |
| Owner's contingency | 17.0 | 14.3 | 0.0 | 14.3 |
| Owner's cost | 32.1 | 32.0 | 19.1 | 12.9 |
| Value added tax (VAT) | 35.2 | 36.7 | 8.8 | 27.9 |
| Grand total | 283.6 | 298.2 | 90.9 | 207.3 |
Totals may not sum due to rounding.
CONSTRUCTION PROGRESS
Silvercorp reported that site preparation for the process plant has been completed and that foundation and building work is in progress. Completion by area at September 30, 2026, was as follows:
| Process plant area | Type of work | Completed at Sep 30, 2026 |
| Fine ore bin | Foundations | |
| Dewatering plant | Foundations | |
| Laboratory | Building | |
| Warehouse | Foundations | |
| Office | Building | |
| Grinding and flotation | Foundations | |
| Oil depot | Foundations | |
| Thickener | Foundations |
Most of the process plant equipment has been ordered, with down payments of approximately
MANAGEMENT COMMENTARY
Fredy Salazar, President and CEO of Salazar Resources, stated: "Silvercorp has reset the schedule after an exceptionally wet season, and the process plant is now taking shape on site. Our
SALAZAR EXPLORATION
While Silvercorp builds El Domo, Salazar is advancing its
SOURCE OF INFORMATION
The information in this news release about El Domo is taken from Silvercorp's news release dated November 3, 2026, which is available under Silvercorp's profile on SEDAR+ at www.sedarplus.ca. Readers are referred to that release for full details of the updated budget and schedule. The Company has relied on the information provided by the operator and has not independently verified it.
ABOUT SALAZAR RESOURCES LIMITED
Salazar Resources Limited (TSXV: SRL) (OTCQB: SRLZF) (FSE: CCG) is a Canadian junior exploration company focused on the discovery and development of mineral deposits in Ecuador. The Company's strategy combines in-house geological expertise with a disciplined, systematic approach to project generation and advancement. Alongside a
For further information, please contact Nick DeMare, Director, at ndemare@chasemgt.com or at 604-685-9316. Please also visit the Company's website at www.salazarresources.com.
Investor Relations: Patrick Piette, Minera IR Inc., ppiette@minera.ca, 416-526-9911
FORWARD-LOOKING STATEMENTS
This news release contains "forward-looking information" within the meaning of applicable Canadian securities legislation, including statements about the development of the Curipamba-El Domo project, its construction budget and schedule, the targeted timing of production, the power supply to the Project and the absence of funding obligations for the Company. Forward-looking information is based on management's current expectations and assumptions, including that the operator of the Curipamba-El Domo project will continue to advance and fund construction as described. Forward-looking information is subject to risks and uncertainties that could cause actual results to differ materially, including construction and commissioning risks at the Curipamba-El Domo project; weather conditions and contractor performance; further cost increases; delays in reviews, permits and approvals for the external power line and the associated risk of longer reliance on generator sets and higher operating costs; the Company's reliance on information provided by the operator; metal prices; and regulatory and political conditions in Ecuador. There can be no assurance that production will commence when targeted. Readers should not place undue reliance on forward-looking information. The Company undertakes no obligation to update forward-looking information except as required by applicable law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/322638
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
Does Salazar Resources have to fund El Domo's increased construction budget?
No. Salazar's 25% interest remains fully carried through commercial production, with no additional development or construction financing obligations. It is not required to fund any part of the budget increase.
When is production at Salazar Resources' El Domo project now targeted?
Silvercorp targets production for November 2027, four months later than previously planned. The operator attributes the schedule change to extended rainfall at the site linked to the Super El Niño. Timing remains subject to weather conditions and contractor performance.
What drove the construction cost increases at Salazar Resources' El Domo project?
Higher diesel costs after Ecuador eliminated diesel subsidies account for US$8.3 million of the increase. Other increases include US$4.7 million for tailings-facility water management enhancements, US$3.7 million for processing plant construction, US$2.4 million for site power equipment and distribution, US$3.3 million for new power items, and approximately US$2.0 million for additional tailings-facility water-control works.