STOCK TITAN

Silvercorp Announces the Construction Plan and Schedule for the Development of the Chaarat ZAAV Project

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

Silvercorp (TSX/NYSE American: SVM) approved a US$196.3 million budget for joint venture Chaarat ZAAV to develop the Tulkubash (Phase 1) and Kyzyltash (Phase 2) gold projects in Kyrgyzstan. Planned spending is US$57.3 million in 2026 and US$139.0 million in 2027.

Phase 1 allocates US$166.3 million to build a 4 Mtpa open-pit heap leach mine at Tulkubash, including mining, heap leach, crusher, ADR plant and power station. Phase 2 earmarks US$30 million for 2026–2027 drilling and studies at Kyzyltash ahead of planned 2028–2031 development.

Loading...
Loading translation...

AI-generated analysis. Not financial advice.

Positive

  • ZAAV Board approves US$196.3 million two-phase development budget
  • US$166.3 million allocated to Tulkubash heap leach mine construction (Phase 1)
  • US$30 million committed to Kyzyltash drilling and studies for Phase 2
  • 50,000–60,000 m Kyzyltash drilling program budgeted at US$15 million in 2026
  • Further 60,000 m Kyzyltash drilling and PEA/PFS work budgeted at US$15 million in 2027
  • Updated Tulkubash feasibility study targeted for completion by July 2026

Negative

  • Total planned capital spend of US$196.3 million represents large funding commitment
  • Heap leach system budget may change after BGRIMM redesign and finalization by March 2027

News Market Reaction – SVM

-1.68%
3 alerts
-1.68% News Effect
-$40M Valuation Impact
$2.33B Market Cap
0.0x Rel. Volume

On the day this news was published, SVM declined 1.68%, reflecting a mild negative market reaction. Our momentum scanner triggered 3 alerts that day, indicating moderate trading interest and price volatility. This price movement removed approximately $40M from the company's valuation, bringing the market cap to $2.33B at that time.

Data tracked by StockTitan Argus on the day of publication.

Key Figures

ZAAV total budget: US$196.3 million 2026 forecast spending: US$57 million 2027 forecast spending: US$139 million +5 more
8 metrics
ZAAV total budget US$196.3 million Chaarat ZAAV Phase 1 and Phase 2 development plan
2026 forecast spending US$57 million Planned Chaarat ZAAV expenditures in 2026
2027 forecast spending US$139 million Planned Chaarat ZAAV expenditures in 2027
Tulkubash ore throughput 4 million tonnes per year Oxidized ore open-pit heap leach operation design capacity
Total Phase 1 capex US$166.3 million Development of Tulkubash open pit and processing facilities
Phase 2 studies budget US$30.0 million Kyzyltash drilling and studies for 2026–2027
2026 drilling program 50,000–60,000 metres Kyzyltash in-fill and step-out drilling plan for 2026
2027 drilling 60,000 m Drilling to support Kyzyltash Pre-Feasibility Study in 2027

Peers on Argus

SVM traded lower while key silver peers like EXK, MAG, AG, and TGB also declined...

SVM traded lower while key silver peers like EXK, MAG, AG, and TGB also declined, indicating the move occurred alongside broader Basic Materials weakness.

Historical Context

5 past events · Latest: Jun 12 (Positive)
Pattern 5 events
Date Event Sentiment Move Catalyst
Jun 12 Reserve update Positive +7.5% Major Mineral Reserve increase and longer mine life at Ying district.
May 26 Earnings report Positive -4.3% Fiscal 2026 revenue and cash flow growth with strong adjusted earnings.
May 25 Listing application Positive +5.6% Proposed Hong Kong listing and related global equity offering plans.
May 22 Dividend declaration Positive +5.6% Announcement of semi-annual dividend to shareholders with set record date.
May 22 Results timing update Neutral -3.3% Change in release date and call timing for Fiscal 2026 results.
Pattern Detected

Recent news generally leads to aligned price moves, though strong earnings have triggered some selling pressure.

Regulatory & Risk Context

Short Interest: 11.89%
Short Interest
11.89% of shares outstanding
as of 2026-05-29 Days to cover: 7.34

Short interest appears elevated, suggesting potential for sharper price swings and squeeze dynamics if sentiment changes quickly.

Market Pulse Summary

This announcement details a US$196.3 million multi‑year plan to build Tulkubash and advance Kyzyltas...
Analysis

This announcement details a US$196.3 million multi‑year plan to build Tulkubash and advance Kyzyltash, expanding Silvercorp’s gold pipeline beyond China. Investors may track feasibility milestones, drilling results, and capital allocation relative to existing Ying cash flows.

Key Terms

bankable feasibility studies, jorc code, heap leach, preliminary economic assessment (pea), +2 more
6 terms
bankable feasibility studies financial
"The Tulkubash project design is based on the Bankable Feasibility Studies completed by Tetra Tech"
A bankable feasibility study is a thorough, independently verified review of a proposed project that lays out detailed engineering plans, costs, schedules, revenue forecasts, and legal or environmental requirements so lenders and investors can judge whether to provide financing. It matters to investors because it reduces uncertainty and acts like a lender-ready blueprint and budget: a strong study makes it far more likely a project will obtain loans, set realistic value expectations, and reveal key risks.
jorc code regulatory
"Bankable Feasibility Studies completed by Tetra Tech (Joint Ore Reserves Committee ("JORC") Code standard)"
The JORC Code is a professional standard for reporting mineral exploration results, mineral resources, and ore reserves so that geological and economic statements about a mining project are transparent and consistent. Think of it as an independent checklist and labeling system that requires qualified experts to document how estimates were made, making company claims verifiable and comparable. Investors use JORC-compliant reports to assess how reliable a mine’s reported size and potential value are before committing funds.
heap leach technical
"Phase 1 Operation Process Flowsheet is a standard heap leach flow sheet, and consists of:"
Heap leach is a mining method where crushed ore is piled into a heap and a liquid is dripped or sprayed over it to dissolve valuable metals, which are then collected from the runoff. Investors care because it is a lower-cost, scalable way to produce metals like gold or copper, but it also affects project timelines, recovery rates, capital needs and environmental or regulatory risk — like choosing a cheap, slow way to extract juice from a fruit versus pressing it quickly.
preliminary economic assessment (pea) financial
"complete a series of studies, including a Preliminary Economic Assessment (PEA), a Feasibility Study"
A preliminary economic assessment (PEA) is an early-stage study that shows whether a proposed mining or resource project could make money by estimating likely production levels, costs, and returns using accessible but limited data. It matters to investors because a PEA acts like a rough business plan or feasibility snapshot: it highlights potential value, capital needs and main risks so investors can decide whether to fund further, more detailed work or walk away.
bacterial oxidization ("biox") technical
"open pit/underground mine, plus flotation, bacterial oxidization ("BIOX") and carbon in leach"
Bacterial oxidization, often shortened to “biox,” is a biological process in which microbes change the chemical form of a substance by transferring oxygen or removing electrons, for example converting metals or organic pollutants into different, more stable forms. Investors care because companies use biox in industries like mining, waste treatment, and chemical processing to lower costs, meet environmental rules, and create value from waste—so progress or setbacks can affect revenue, permitting and cleanup liabilities.
carbon in leach ("cil") technical
"flotation, bacterial oxidization ("BIOX") and carbon in leach ("CIL")."
Carbon-in-leach (CIL) is a gold processing method where crushed ore is mixed with a chemical that dissolves gold, and porous activated carbon is added to capture the dissolved gold as the solution is being treated. Think of it like steeping tea while the tea bag soaks up the flavor at the same time, so extraction and collection happen in one step. For investors, CIL signals how efficiently a mine can recover gold, affects operating costs, capital needs and environmental controls, and therefore influences projected production and profit.

AI-generated analysis. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Silvercorp Metals Inc.

Trading Symbol: TSX/NYSE American: SVM

VANCOUVER, BC, June 22, 2026 /PRNewswire/ - Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX: SVM) (NYSE American: SVM), is pleased to announce a budget US$196.3 million for Chaarat ZAAV CJSC ("ZAAV") which includes the development of Tulkubash (Phase 1) and initial expenditures to advance Kyzyltash (Phase 2). The forecast spending for 2026 is US$57 million and the forecast spending for 2027 is US$139 million.

ZAAV is a joint venture company with Silvercorp holding a 70% interest and being the operator, and Kyrgyzaltyn holding a 30% free-carried interest. ZAAV holds a 100% interest in the mining license (~7 km2) hosting the fully-permitted Tulkubash/Kyzyltash gold projects as well as surrounding exploration licenses (27.42 km2) hosting the Karator and Ishakuld gold zones (the "Projects") in the Tien Shan area of the Kyrgyz Republic. The Board of Directors of ZAAV has approved the budget outlined in the table below:

Cost Items

Total

($ Million)

2026

($ Million)

2027

($ Million)

Phase 1 Development of Tulkubash

Mining




Open Pit and Waste Dump

51.5

10.6

40.9

Mine Pit Water Treatment Plant

3.0

-

3.0

Mine Auxiliary Facilities

8.0

2.1

5.9

Heap Leach System

Heap Leach

22.7

8.4

14.3

Crusher

26.5

4.5

22.0

ADR Plant

13.7

2.3

11.4

Power Station

5.3

1.5

3.8

Process Plant Auxiliary Facilities

6.0

2.1

3.9

Commissioning

1.4

-

1.4

General and Administration

14.0

7.2

6.8

Contingency

14.2

3.6

10.6

Total Phase 1

166.3

42.3

124.0


Phase 2 Development of Kyzyltash

Drilling + Studies

30.0

15.0

15.0





Total Phase 1 & 2

196.3

57.3

139.0

Phase 1 Development of Tulkubash

Silvercorp is committed to finance and advance the construction of Tulkubash as a 4 million tonnes of oxidized ore per year open-pit mine/heap leach operation. The Tulkubash project design is based on the Bankable Feasibility Studies completed by Tetra Tech (Joint Ore Reserves Committee ("JORC") Code standard) in 2018, expertized and localized for Kyrgyzstan by Ken Too (Bishkek) in 2020, and further improved (JORC Code standard) in 2021 by LogiProc, a South African firm, with support from Ausenco's Canadian branch. Silvercorp also expects to publish an updated feasibility study, currently in progress by LogiProc, and expected to be completed by July 2026.

The Phase 1 Operation Process Flowsheet is a standard heap leach flow sheet, and consists of: 1) ore mined from the open pit is sent to the crushing plant, lower grade ore is sent to the LG Ore Stockpile and waste rock is sent to the Waste Rock Storage; 2) ore is crushed to a target size of P80 of 12.5 mm; 3) crushed ore is trucked and stacked on the Heap Leach Pad; 4) heap leaching comprises a barren solution dripping and a pregnant solution collection system; and 5) carbon absorption, desorption and recovery (ADR plant) and gold refinery building will produce gold doré bars.

Open Pit Mining, Stripping, and Waste Storage

The construction contract for the open pit and waste storage work will be based on fixed "unit cost" criteria for each cubic metre of rock removed. To date, five mining contractors, four of them with operations in Kyrgyzstan, have visited the site and have provided initial quotes for the open pit mining, stripping, and waste handling. From these quotes, an estimated bill of quantity ("BoQ") was prepared, along with a budget of $51.5 million based on the quote provided by one of the most experienced contractors.

Mine Auxiliary Facilities

The Company plans to set up a temporary camp, a powder magazine and carry out road upgrades in 2026, with an estimated cost of US$2.1 million. In 2027, construction of a mine truck maintenance workshop, detonators storage, temporary ore stockpile and other facilities is scheduled, with an estimated cost of US$5.9 million.

Heap Leach System

The heap leach facility involves the construction of a Crusher, Heap Leach Pad and an ADR Plant at a total capital cost of US$75.6 million. The cost estimates for earthworks are based on the initial, non-binding bidding quotes from Mining Contractors, material cost is based on recent market enquiries in China. Major equipment costs for the crusher are based on vendor quotes. The ADR plant cost estimate is based on the 2021 LogiProc study. Currently, BGRIMM of Beijing has been awarded a contract to redesign the Crusher and ADR plant to the Kyrgyzstan standard, therefore the final budget may be subject to adjustment under the new design. The design work is expected to be completed in stages, with final completion in March 2027.

Phase 2 Development of Kyzyltash (2028-2031):

Silvercorp and ZAAV will invest in the development of the Kyzyltash sulfide deposit as a 3 to 4 million tonnes per year open pit/underground mine, plus flotation, bacterial oxidization ("BIOX") and carbon in leach ("CIL"). To advance development of Kyzyltash, ZAAV will carry out in-fill drilling to convert inferred resources into higher categories, and complete a series of studies, including a Preliminary Economic Assessment (PEA), a Feasibility Study and Detailed Engineering Design.

During 2026, ZAAV plans to conduct a 50,000 to 60,000 metre drilling program, including both in-fill and step-out drilling to convert inferred resource into measured & indicated categories, and to make discoveries to expand the resource base. Currently, three contractors with 12 drill rigs are drilling at the Kyzyltash sulfide zone, including the Contact Zone (CZ) and the Main Zone (MZ). Drilling is generally conducted on spacing grids ranging from 80m×40m to 40m×40m.

In addition to geological drilling, geotechnical and hydrological, metallurgical and environmental studies will also be carried out, with a total budget of $15 million in 2026. The budget is based on actual quotes from drilling contracts.

In 2027, ZAAV plans to complete a PEA and undertake a further 60,000 m of drilling to support a Pre-Feasibility study (PFS), with the objective of submitting the study to the government for review and permitting. The total budget for the year is $15 million.

In 2028, ZAAV plans to complete a Feasibility Study and detailed engineering design for construction, and to commence construction.

About Silvercorp

Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.

For further information

Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com 

CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS

This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding the construction schedule, duration, and costs for the development of the Tulkubash/Kyzyltash gold projects, ore tonnage in 2026 and subsequent three year production, and striping ratio etc. By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including fluctuating commodity prices; recent market events and condition; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in China; regulatory environment and political climate in Bolivia and Ecuador; integration and operations of Adventus; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; public health crises; the Company's investment in New Pacific Metals Corp. and Tincorp Metals Inc.; and the other risk factors described in the Company's Annual Information Form and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.

A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports and filings which are available under its profile at www.sedarplus.ca.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-announces-the-construction-plan-and-schedule-for-the-development-of-the-chaarat-zaav-project-302806000.html

SOURCE Silvercorp Metals Inc.

FAQ

What did Silvercorp (SVM) announce about the Chaarat ZAAV project budget in June 2026?

Silvercorp announced a US$196.3 million budget for the Chaarat ZAAV project, covering Tulkubash Phase 1 and Kyzyltash Phase 2. According to Silvercorp, planned spending is US$57.3 million in 2026 and US$139.0 million in 2027 for construction and studies.

How much will Silvercorp (SVM) invest in developing the Tulkubash gold project?

Silvercorp plans to invest US$166.3 million to develop the Tulkubash heap leach gold project in Phase 1. According to Silvercorp, this includes mining, heap leach pad, crusher, ADR plant, power station, auxiliary facilities, commissioning, G&A and contingency over 2026–2027.

What is the development plan and schedule for Kyzyltash Phase 2 in the Silvercorp (SVM) ZAAV project?

Kyzyltash Phase 2 will be advanced through drilling and studies from 2026 to 2028, with construction targeted afterward. According to Silvercorp, ZAAV budgets US$30 million in 2026–2027 for 110,000–120,000 m of drilling, PEA, PFS, feasibility study and detailed engineering.

What drilling programs are planned at Kyzyltash in 2026 and 2027 under Silvercorp (SVM)?

Kyzyltash will see 50,000–60,000 m of drilling in 2026 and a further 60,000 m in 2027. According to Silvercorp, these in-fill and step-out programs, supported by three contractors with 12 rigs, aim to upgrade resources and support economic studies.

When will Silvercorp (SVM) complete the updated Tulkubash feasibility study?

Silvercorp expects to complete an updated feasibility study for Tulkubash by July 2026. According to Silvercorp, engineering firm LogiProc is preparing the study to refine the 4 million tonnes per year open-pit heap leach mine design within the approved Phase 1 budget.

How is the Silvercorp (SVM) and Kyrgyzaltyn joint venture structured for the ZAAV project?

ZAAV is a joint venture where Silvercorp holds 70% and acts as operator, while Kyrgyzaltyn holds a 30% free-carried interest. According to Silvercorp, ZAAV owns 100% of the mining license and surrounding exploration licenses for Tulkubash and Kyzyltash.