STOCK TITAN

Fortuna Mining clears Diamba Sud permit review

The Ministry has completed its application-document review, while permit issuance, the investment decision and construction remain subject to further approvals.

Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates
(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
6-K

Rhea-AI Filing Summary

Fortuna Mining Corp. received Senegal’s Notice of Admissibility for its Diamba Sud Exploitation Permit application on November 2, 2026, after the process began in February 2026. The notice confirms the Ministry completed its document review and found the application compliant with regulatory requirements, marking a final step toward the permit. Fortuna expects the Government’s internal approval process to conclude in the fourth quarter of 2026 and anticipates a formal final investment decision upon receipt of the permit, subject to Board approval and other required authorizations.

Full-scale construction remains subject to the permit, Board approval of the final investment decision and local customary construction approvals. Fortuna is advancing early works, with first gold targeted for mid-2028. Diamba Sud and the 30% Séguéla plant expansion together underpin a target of approximately 60% growth in annual gold production to an annualized rate of 500,000 ounces from mid-2028. Mining Convention negotiations with Senegal are advanced, based on the 2016 Mining Code with additional provisions intended to establish a ten-year fiscal stability framework; the Convention remains subject to finalization and Government approvals. The cited feasibility study reported a 60% after-tax IRR and NPV5% of US$1 billion using US$3,500 per ounce gold.

Annualized gold production target 500,000 ounces Target from mid-2028
Target growth in annual gold production Approximately 60% Target from mid-2028, supported by Diamba Sud and the Séguéla plant expansion
After-tax IRR 60% Diamba Sud feasibility study
NPV5% US$1 billion Diamba Sud feasibility study
Gold price used in feasibility study US$3,500 per ounce Diamba Sud feasibility study
Fiscal stability framework Ten-year period Additional provisions under negotiation for the Diamba Sud Mining Convention
Notice of Admissibility regulatory
"received the Notice of Admissibility"
Exploitation Permit regulatory
"Diamba Sud Exploitation Permit application"
An exploitation permit is an official government license that allows a company to extract and sell natural resources or operate a production activity in a specific area, similar to a landlord’s permission to use a plot of land. It matters to investors because the permit is often the legal gateway to generate revenue from a project; losing, failing to obtain, or facing restrictions on the permit can stop production, delay cash flow, or add costly compliance requirements.
Mining Convention regulatory
"advanced stage of negotiations on a new Mining Convention"
final investment decision technical
"formal final investment decision upon receipt of the Exploitation Permit"
A final investment decision is the point at which a person or organization chooses to move forward with a particular project or purchase after reviewing all the necessary information and options. It is like deciding to buy a house after considering all the costs, benefits, and alternatives. This decision is important because it determines whether and when the investment will be made, impacting future financial plans and outcomes.
IRR financial
"After-tax IRR of 60%"
IRR (Internal Rate of Return) is the annualized percentage return an investment is expected to produce based on its projected series of cash outflows and inflows; mathematically, it’s the rate that makes the present value of those cash flows balance to zero. Investors use IRR to compare and rank projects or investments—similar to comparing the interest rates on savings accounts—to judge which offers the best return for the time and risk involved.
NPV5% financial
"NPV5% of US$1 billion"
Net present value at a 5% discount rate (NPV 5%) measures the current worth of a sequence of expected future cash flows after shrinking them by 5% per year, like comparing getting money now versus in the future with a 5% annual “cost” for waiting. Investors use NPV 5% to judge whether an investment or project creates value: a positive number suggests the returns exceed that 5% benchmark, while a negative number implies the money would be better used elsewhere.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What economics does FSM cite for Diamba Sud?

The cited feasibility study reports an after-tax internal rate of return of 60% and NPV5% of US$1 billion, using a gold price of US$3,500 per ounce. Fortuna said the study was announced June 29, 2026.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

Form 6-K

 

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

 

For the month of November 2026

 

Commission File Number 001-35297

 

Fortuna Mining Corp.

(Translation of registrant’s name into English)

 

1111 Melville Street, Suite 820, Vancouver, British Columbia, Canada V6E 3V6

(Address of principal executive office)

 

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

FORM 20-F   ¨ FORM 40-F  þ

 

 

SIGNATURES

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. 

 

    Fortuna Mining Corp.
Date:  November 2, 2026   (Registrant)
       
    By: /s/  "Jorge Ganoza Durant"
      Jorge Ganoza Durant
      Chief Executive Officer

  

Exhibits:

 

  99.1 News Release dated November 2, 2026

  

 

 

 

 

Exhibit 99.1

 

 

Fortuna Advances Diamba Sud Gold Project Permitting in Senegal

 

Vancouver, British Columbia, November 2, 2026: Fortuna Mining Corp. (NYSE: FSM | TSX: FVI) is pleased to provide an update on its progress at the Diamba Sud gold project, Senegal.

 

Jorge A. Ganoza, CEO and Director of Fortuna, commented, “Following our July final investment decision on the 30% plant expansion at our flagship Séguéla mine, and with Diamba Sud advancing through the final stages of permitting, we are progressing along a clear growth path. Together, these projects underpin our target of approximately 60% growth in annual gold production to an annualized rate of 500,000 ounces from mid-2028.”

 

Permits

 

Fortuna is pleased to report that it received the Notice of Admissibility for its Diamba Sud Exploitation Permit application from Senegal’s Ministry of Mines and Geology on November 2, 2026, following initiation of the application process in February 2026. The notice confirms that the Ministry has completed the review of the application documentation, and the file complies with all regulatory requirements, marking an important final step toward the granting of the Exploitation Permit. The Company and the Ministry have worked constructively to advance the application to this stage. With this milestone completed, the Company now expects the Government´s internal approval process for the final Exploitation Permit to be completed during the fourth quarter of 2026.

 

The project has already received the environmental decree from Senegal’s Ministry of Environment and Ecological Transition approving its Environmental and Social Impact Assessment, as announced on June 15, 2026. Fortuna is advancing early works and committing capital to protect the project schedule and its target of first gold in mid-2028. The Company anticipates making a formal final investment decision (“FID”) upon receipt of the Exploitation Permit.

 

Mining Convention

 

Fortuna is at an advanced stage of negotiations with the State of Senegal on a new Mining Convention for the Diamba Sud project based on Senegal’s 2016 Mining Code, together with additional provisions intended to establish a fiscal stability framework for a ten-year period. The Convention remains subject to finalization and the required Government approvals.

 

Construction Planning and Early Works Advancing

 

Full-scale construction of the mine remains subject to receipt of the Exploitation Permit, Board approval of the FID and some local level customary construction approvals. The results of the positive feasibility study (“FS”) announced on June 29, 2026 demonstrated the project’s technical and economic viability (refer to Fortuna news release dated June 29, 2026, “Fortuna delivers robust Feasibility Study for the Diamba Sud Gold Project in Senegal: After-tax IRR of 60% and NPV5% of US$1 billion using US$3,500/oz”).

 

 -1- 

 

 

 

 

 

Early works completed or underway to support the project schedule include:

 

·Assembly of the owner’s construction team, with a core of professionals largely drawn from the team that successfully delivered Fortuna´s flagship Séguéla mine in Cote d’Ivoire
·Selection of SENET, a leading African project management and engineering company, as the project’s engineering, procurement and construction management contractor, and award of a limited order to proceed to advance early works
·Completion of front-end engineering and design
·15% progress on detailed engineering for the processing plant
·Purchase orders placed and down payments for critical long-lead equipment, including the semi-autogenous grinding (“SAG”) mill, primary crusher, and carbon-in-leach tank plate work
·Manufacturing of the power station's heavy fuel oil (“HFO”) and light fuel oil (“LFO”) generators with the LFO generators passing factory acceptance testing and shipped
·Tendering and award of key construction packages, including, bulk earthworks for process plant, water storage facility, tailings storage facility, power station, and fuel storage facilities
·New accommodation camp earthworks 80% complete, civil works 40% complete and buried services nearing completion
·Land compensation and clearing for major infrastructure footprints

  

Subject to receiving the Exploitation Permit and approval of the FID in 2026, the planned key project milestones are summarized below:

 

Timing Milestone
Q4 2026 FID, commencement of critical-path construction activities, including earthworks for the process plant and power station, and placement of all long-lead equipment orders
Q1 2027 Completion of the 329-person accommodation camp and delivery of the LFO generators
Q2 2027 Award of the mining contract, completion of the water storage dam and water harvest dam, and first concrete placed for the process plant
Q3 2027 Mobilization and site establishment of the mining contractor and arrival of the HFO generators
Q4 2027 Commencement of pre-production mining and arrival and installation of the SAG mill
Q1 2028 Commissioning of the power station, availability of power for process plant commissioning and start-up, and completion of the TSF
Q2/Q3 2028 Process plant commissioning, first gold pour and ramp-up to nameplate plant throughput

 

 -2- 

 

 

 

  

 

Qualified Person

 

Eric Chapman, Senior Vice President of Technical Services for Fortuna Mining Corp., is a Professional Geoscientist registered with Engineers and Geoscientists British Columbia (Registration No. 36328), and a Qualified Person as defined by National Instrument 43-101- Standards of Disclosure for Mineral Projects. Mr. Chapman has reviewed and approved the scientific and technical information contained in this news release and has verified the underlying data.

 


About Fortuna Mining Corp.

 

Fortuna Mining Corp. is a Canadian precious metals mining company with three operating mines in Argentina, Côte d’Ivoire, and Peru, and the feasibility -stage Diamba Sud Gold Project in Senegal. Our exploration portfolio spans our operating jurisdictions as well as Guinea and Guyana. Sustainability is at the core of our operations and stakeholder relationships. We produce gold and silver while creating long-term shared value through efficient production, environmental stewardship, and social responsibility. For more information, please visit our website at www.fortunamining.com

 

 

ON BEHALF OF THE BOARD

 

Jorge A. Ganoza

CEO and Director

Fortuna Mining Corp.

 

 

Investor Relations:

 

Carlos Baca | info@fmcmail.com | fortunamining.com | X | LinkedIn | YouTube | Instagram | TikTok

 

 -3- 

 

 

 

  

 

Cautionary Note Regarding Forward-Looking Statements

 

This news release contains forward-looking statements which constitute “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward-looking Statements”). All statements included herein, other than statements of historical fact, are Forward-looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward-looking Statements. Forward-looking Statements contained in this news release include, without limitation, statements with respect to: the Company’s target of approximately 500,000 GEO of annualized production from mid- 2028 and the contribution of Diamba Sud and the Séguéla plant expansion to that target; the projected economics of the Diamba Sud Project, including the net present value (NPV) of the Project and the internal rate of return (IRR) on the Project; the plans for completing the early works program; the project development timeline to production, including first gold pour in mid-2028; completion of the Ministry’s internal approval process for the Exploitation Permit and the completion of the negotiation and finalization of the Mining Convention both expected during the fourth quarter of 2026; a formal FID in the fourth quarter of 2026 upon receipt of the Exploitation Permit, subject to Board approval and receipt of other required authorizations; the estimated timing of the development, construction, commissioning and production at the Project; the timing of and future prospects for exploration and any expansion of the Project.

 

These statements are based on information currently available to the Company, and the Company provides no assurance that actual results will meet management's expectations. In certain cases, Forward-looking Statements may be identified by such terms as "anticipates", "believes", "could", "estimates", "expects", "may", "shall", "will", or "would". Forward-looking Statements contained in this news release are based on certain factors and assumptions regarding, among other things, the FS, the estimation of Mineral Resources and Mineral Reserves and any potential upgrades thereof, gold metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labor and operating costs, the availability of necessary financing and materials to continue to explore and develop the Company’s properties in the short and long-term, the progress of exploration and development activities, and the receipt of necessary regulatory approvals, the timing of the approval of the Exploitation Permit and the finalization of the Mining Convention. Other assumptions relate to currency fluctuations, environmental risks, title disputes or claims, and similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

 

Although the Company believes the expectations expressed in such Forward-looking Statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the Forward-looking Statements. Factors that could cause actual results to differ materially from those in Forward-looking Statements include: changes in market conditions, unsuccessful exploration results, possibility of project cost overruns or unanticipated costs and expenses, changes in the costs and timing of the development of new deposits, inaccurate Mineral Resources and Mineral Reserves estimates, changes in the price of gold, unanticipated changes in key management personnel and general economic conditions; the duration and impacts of geo-political uncertainties on the Company’s production, workforce, business, operations and financial condition; the expected trends in mineral prices, inflation and currency exchange rates; that all required approvals and permits will be obtained for the Company’s business and operations on acceptable terms; that there will be no significant disruptions affecting the Company’s operations; delays in obtaining the Exploitation Permit or Cabinet approval of the finalized Mining Convention; and changes to the negotiated fiscal terms during the approval process. Mining exploration and development is an inherently risky business. Accordingly, actual events may differ materially from those projected in the Forward-looking Statements. This list is not exhaustive of the factors that may affect any of the Company's Forward-looking Statements, including the factors included in the Company’s annual information form for the year ended December 31, 2025. These and other factors should be considered carefully, and readers should not place undue reliance on the Company's Forward-looking Statements. Forward-looking Statements are made as of the date hereof, and the Company disclaims any obligation to update any Forward-looking Statements, whether as a result of new information, future events, or results or otherwise, except as required by law. There can be no assurance that these Forward-looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

 

 -4- 

 

 

 

 

 

Cautionary Note to United States Investors Concerning Mineral Resources and Mineral Reserves

 

Technical disclosure regarding the Company’s properties included herein has been prepared in accordance with National Instrument 43-101, Standards of Disclosure for Mineral Projects ("NI 43-101") and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. Canadian standards, including NI 43-101, differ from the requirements of the Securities and Exchange Commission, and information included herein may not be comparable to similar information disclosed by U.S. companies.

  

 -5- 

 

Filing Exhibits & Attachments

1 document

Keep reading