Azure, Microsoft’s cloud, grew 48% in constant currency from July to September, beating Microsoft’s own forecast of 44% to 45% for at least the fifth quarter running by our count. In fiscal 2027’s first quarter, capex was $45.2 billion, Microsoft’s spending on data centers and equipment with leased sites booked like purchases, below an outlook of over $50 billion.

The short answer. Azure grew faster than Microsoft itself had forecast, for at least the fifth quarter running by our count. Capex was $45.2 billion, counting data center sites leased on terms booked like a purchase, below the over $50 billion Microsoft forecast. That forecast already allowed for more new leases being booked as rent. Azure rents out computing for AI and other work, so its growth indicates how much businesses want cloud computing, AI included.

Microsoft fiscal first quarter 2027, July to September 2026

Azure growth, constant currency
48%
Microsoft’s forecast for Azure as redefined in September: 44% to 45%
Capex, data centers and equipment
$45.2 billion
Counts leased sites booked like purchases, not those booked as rent; July outlook: over $50 billion
Azure revenue
$33.2 billion
Azure as redefined in September; $22.4 billion a year earlier on that basis
Azure grew 48% in constant currency, above Microsoft’s own forecast of 44% to 45%, while capex reached $45.2 billion. Figures from Microsoft results release, quarter ended September 30, 2026, as of October 28, 2026; Microsoft financial summary slides, quarter ended September 30, 2026, as of October 28, 2026; Microsoft FY27 Segments and Investor Metrics, September 2, 2026, as of September 2, 2026.

Microsoft earnings report: Azure growth against the forecast

Azure, the service businesses rent for computing and AI, grew 48% in constant currency. That beats Microsoft’s own forecast, as Azure has in every quarter of the past year.

Microsoft gives one Azure forecast a quarter, on its results call, and states it in constant currency, which leaves out the effect of exchange rates. On July 29 chief financial officer Amy Hood said: “In Azure, we expect revenue growth of approximately 45% in constant currency.”

On September 2 Microsoft narrowed what Azure covers, moving GitHub’s cloud services and Security Copilot into Microsoft 365 and its healthcare cloud into a new Industry solutions line. It restated the forecast for the narrower Azure as “Growth of 44% to 45% in constant currency,” the like-for-like benchmark for this quarter.

The release puts Azure’s revenue at $33.2 billion, up 48% as reported and 48% in constant currency. It is the first results release to give Azure in dollars, after the September restatement put the same three months of 2025 at $22.4 billion.

By our count, Azure finished above the forecast Microsoft gave three months before in each of the five quarters to September 2026. In the four quarters to June 2026 each result landed at least a point above the top of the range. This quarter’s gap of 3 points over the top of the range ties the widest of those five quarters. That was April to June 2026, when Azure grew 43% against a forecast of 39% to 40%.

Azure growth against the top of Microsoft’s own forecast, constant currency. Azure grew faster than the top of Microsoft’s own forecast in each of the five quarters from July 2025 to September 2026, by 3 points in the latest, which ties the widest gap.
Azure growth against the top of Microsoft’s own forecast, constant currency Azure grew faster than the top of Microsoft’s own forecast in each of the five quarters from July 2025 to September 2026, by 3 points in the latest, which ties the widest gap. Figures from Microsoft fiscal Q4 2025 earnings call (forecast for July to September 2025), as of July 30, 2025; Microsoft fiscal Q1 2026 earnings call, as of October 29, 2025; Microsoft fiscal Q2 2026 earnings call, as of January 28, 2026; Microsoft fiscal Q3 2026 earnings call, as of April 29, 2026; Microsoft fiscal Q4 2026 results release, as of July 29, 2026; Microsoft results release, quarter ended September 30, 2026, as of October 28, 2026; Microsoft FY27 Segments and Investor Metrics, September 2, 2026, as of September 2, 2026.
Show the data
ItemMicrosoft forecast (top)Azure growthChange
Jul to Sep 202537%39%+2 pts
Oct to Dec 202537%38%+1 pts
Jan to Mar 202638%39%+1 pts
Apr to Jun 202640%43%+3 pts
Jul to Sep 2026, narrower Azure45%48%+3 pts
Show the data
Quarter (Microsoft fiscal)Azure forecast, constant currencyAzure growth, constant currency
July to September 2025 (Q1 FY26)Approximately 37%39%
October to December 2025 (Q2 FY26)Approximately 37%38%
January to March 2026 (Q3 FY26)37% to 38%39%
April to June 2026 (Q4 FY26)39% to 40%43%
July to September 2026 (Q1 FY27), narrower Azure44% to 45%48%

Source: forecasts from the outlook on the previous quarter’s results call, the last as restated on September 2, 2026; each result from Microsoft’s results release (Microsoft Investor Relations). Rows before July 2026 use the Azure definition of their time.

Hood also said in July that “customer demand continues to exceed supply.” In our reading, with demand above supply, Azure’s growth depends on the capacity Microsoft has built and switched on. That is why the spending figure in this release matters as much as the growth rate.

Microsoft’s backlog: how much revenue is already under contract?

Microsoft’s commercial remaining performance obligation, the revenue business customers have signed for that Microsoft has still to deliver, was $677 billion on September 30. That is 73% more than a year earlier, though about level with June 30, according to Microsoft’s results releases for the September and June quarters.

This is the backlog Microsoft reports for its business customers. Its quarterly report, filed with the SEC on October 28, says Microsoft expects about 30% of it to turn into revenue within 12 months, and the rest later.

The 73% rise compares with the end of September 2025. Against the end of June, when the June quarter release put it at $678 billion, the commercial backlog was about level. The total for all customers, which Microsoft calls remaining performance obligations, was also flat. Its annual report put it at $684 billion on June 30, and its quarterly report at $683 billion on September 30. In July Hood had warned that “the significant OpenAI contracts signed in the prior year will result in some quarterly volatility in both the bookings and RPO growth rates.”

The release does not say how much of the September total comes from OpenAI. For April to June, Microsoft said in July that the backlog grew 25% from a year earlier when OpenAI is excluded. It added that all of the increase from March to June came from customers other than frontier model companies, the AI labs such as OpenAI.

How much is Microsoft spending on AI data centers?

Microsoft’s capex was $45.2 billion in the three months to September, counting leased data center sites booked like purchases, below its outlook of over $50 billion. That outlook already counted the lease change explained below.

Capital expenditures, or capex, is what a company spends on buildings and equipment that last more than a year, and Microsoft’s figure includes assets acquired under finance leases. Cash paid for property and equipment was $39.4 billion, a separate measure that differs from capex in when goods are paid for and in leaving out finance leases. By our calculation, capex was 49% of revenue in the quarter, against 45% a year earlier, when more new leases were counted in capex.

Microsoft capex by quarter, counting leased sites booked like purchases, $ billions. Capex rose from $24.2 billion in April to June 2025 to $45.2 billion in July to September 2026, the first quarter in which more new data center leases were booked as rent, outside capex.
Microsoft capex by quarter, counting leased sites booked like purchases, $ billions Capex rose from $24.2 billion in April to June 2025 to $45.2 billion in July to September 2026, the first quarter in which more new data center leases were booked as rent, outside capex. Figures from Microsoft fiscal Q4 2026 financial summary slides, as of July 29, 2026; Microsoft financial summary slides, quarter ended September 30, 2026, as of October 28, 2026.
Show the data
CategoryValue
Apr to Jun '25$24.2B
Jul to Sep '25$34.9B
Oct to Dec '25$37.5B
Jan to Mar '26$31.9B
Apr to Jun '26$41.0B
Jul to Sep '26$45.2B

Capex was 30% higher than a year earlier, though the two quarters count leases differently, and up from the $41.0 billion of April to June. Since July, Microsoft treats its data center buildings as lasting 25 years instead of 15, and Hood said on July 29 that “more of our future datacenter leases will shift from finance leases to operating leases as a result of this update. Finance leases are included in capital expenditures while operating leases are not.”

A finance lease is booked as if Microsoft had bought the site, while an operating lease is booked as rent. So the building goes on while less of it shows up as capex. Azure beat its forecast in a quarter when capex fell short of the outlook, and the release gives no reason for the gap. Microsoft’s slides say roughly three-quarters of capex went to short-lived assets, primarily CPUs and GPUs, after about two-thirds in April to June.

Until June 2026From July 2026
Life of a data center building15 years25 years
How more new leases are bookedFinance leases, like a purchaseOperating leases, like rent
In Microsoft’s capex figureFinance leases are includedOperating leases are not included
How a new Microsoft data center lease is counted, before and after July 2026 With a 25-year building life, more new data center leases count as operating leases, which stay out of Microsoft’s capex figure. Figures from Microsoft fiscal Q4 2026 earnings call, July 29, 2026, as of July 29, 2026.

Hood put a number on it for calendar 2026. In April Microsoft expected “roughly $190 billion in capital expenditures.” In July she said the plan was otherwise unchanged and that “the shift from finance to operating leases adjusts our expectation to approximately $175 billion.” By our subtraction, the lease change alone takes about $15 billion of 2026 building out of the capex line.

Microsoft’s quarterly report shows the shift in the first quarter under the new treatment. New operating leases, the kind booked as rent, brought in $6.5 billion of leased assets, against $1.4 billion a year earlier, while new finance leases fell.

Show the data
Leased assets Microsoft took on, by kind of leaseJuly to September 2026July to September 2025
Operating leases, booked like rent$6.5 billion$1.4 billion
Finance leases, booked like a purchase$5.2 billion$9.1 billion

Source: Microsoft Form 10-Q for the quarter ended September 30, 2026, leases note, right-of-use assets obtained in exchange for lease obligations. This measure differs from the $7.4 billion of finance leases in Microsoft’s capex slides.

The same report lists $364.6 billion of further leases, mostly for data centers, signed but not yet started, some of them still subject to conditions. At the end of June, Microsoft’s annual report put it at $329.1 billion. Under the change Hood described in July, more of those leases will be booked as operating leases and so stay out of capex.

If Microsoft keeps its figure of approximately $175 billion, the three months to December would carry about $57 billion of capex by our calculation. That remainder holds only while the July figure stands. Some of the rise is price. In April, Microsoft said its 2026 spending included “approximately $25 billion from the impact of higher component pricing,” such as the memory chips whose cost SK hynix’s results showed climbing from the seller’s side.

Did Microsoft beat earnings?

Revenue was $92.3 billion, above the top of the range Microsoft forecast in July. Its July outlook gave revenue and cost ranges, and no earnings per share figure.

Revenue rose 19% from a year earlier and operating income, the profit from running the business before interest, investments and taxes, rose 21% to $45.9 billion.

Diluted earnings per share were $4.92 under GAAP, the standard accounting rules, and $4.89 on Microsoft’s non-GAAP basis, which leaves out the gains and losses from its investment in OpenAI.

In July Microsoft had forecast revenue of $89.85 billion to $90.95 billion, growth of 16% to 17%, with faster growth from business customers partly offset by weaker demand for PCs.

In after-hours trading Microsoft shares were at $552.55 at 4:14 p.m. ET, up 4.1% from the regular-session close of $531.01, according to StockTitan real-time Nasdaq data.

Microsoft’s new segments: Agents and Infra, Devices and Consumer

Agents and Infra, home of Azure and Microsoft 365, brought in $76.8 billion, above Microsoft’s forecast. Devices and Consumer brought in $15.5 billion, above its forecast.

Agents and Infra holds Azure, Microsoft 365 for businesses and consumers, industry clouds, server software and consulting, while Devices and Consumer holds Windows, Xbox and advertising. Microsoft Cloud, the cloud products from Azure to the online Office apps, brought in $63.9 billion, up 30%.

Show the data
SegmentRevenueChange from a year earlierMicrosoft’s forecast, as restated September 2
Agents and Infra (Azure, Microsoft 365, server software, industry clouds)$76.8 billion25%$75.15 billion to $75.75 billion
Devices and Consumer (Windows, Xbox, search and advertising)$15.5 billionminus 3%$14.7 billion to $15.2 billion
Total$92.3 billion19%$89.85 billion to $90.95 billion

Source: Microsoft results release, quarter ended September 30, 2026; forecasts from Microsoft’s September 2, 2026 presentation on Form 8-K (Microsoft Investor Relations, SEC).

Microsoft dividend, buybacks and debt

Microsoft returned $10.2 billion to shareholders through dividends and share buybacks in the quarter, and its board raised the quarterly dividend by 8% in September.

Microsoft’s slides split it into $7.3 billion of dividends and $2.9 billion of share repurchases. Diluted shares, the count that includes shares owed under employee stock awards, averaged 7.45 billion, against 7.47 billion a year earlier.

The next quarterly dividend is $0.98 a share, up from $0.91, as Microsoft announced on September 15. Its quarterly report lists it as payable on December 10, 2026 to shareholders of record on November 19.

The balance sheet shows long-term debt of $31.1 billion and $4.4 billion due within a year, against $64.5 billion of cash and short-term investments, more than its total debt.

Cash from the business covered both the building and the payouts. Cash from operations was $58.0 billion in the quarter, and $18.6 billion was left after paying for property and equipment, which Microsoft’s slides call free cash flow.

What Microsoft’s earnings say about Azure and AI spending

Azure again grew faster than Microsoft forecast, while capex came in below the outlook. More new data center leases are now booked as rent, outside that capex figure.

The three months to December would carry the rest of Microsoft’s 2026 capex figure, so its next report shows whether that figure holds.

What to watch

  • Whether Azure growth speeds up in the six months to December, as Microsoft said in July it expected: its fiscal second quarter release, expected in late January 2027.
  • Whether capex for October to December fits Microsoft’s calendar 2026 figure of approximately $175 billion: the same fiscal second quarter release and its financial summary slides.

Our numbers

  • Five beats in five quarters: the Azure forecast Microsoft gave on each results call against the constant currency growth in the next release, five quarters.
  • 49% of revenue: capex including finance leases divided by revenue for the quarter, both as Microsoft reports them.
  • About $15 billion: Microsoft’s calendar 2026 capex expectation of roughly $190 billion in April less approximately $175 billion in July, which Microsoft tied to the lease shift.
  • About $57 billion for October to December: approximately $175 billion less capex of $31.9 billion, $41.0 billion and $45.2 billion in the three quarters from January to September 2026.

Frequently asked questions

What time is the Microsoft earnings call?

Microsoft’s call starts at 2:30 p.m. Pacific Time, 5:30 p.m. Eastern, on October 28, 2026, with a live webcast on Microsoft’s investor relations site. The results release came out after the market closed, before the call.

What does Microsoft forecast for the December quarter?

Microsoft gives its forecast for the next quarter on the results call and in outlook slides it posts on its investor relations site during the call, not in the release. In July it said it expected Azure growth to keep accelerating through the six months to December and calendar 2026 capex of approximately $175 billion. The October 28 call may update that outlook.

How much revenue does Azure make?

Azure brought in $33.2 billion in the three months to September 2026, according to Microsoft’s results release, up 48% from a year earlier. On the narrower definition Microsoft adopted in September, Azure made $101.9 billion in the fiscal year to June 2026.

How much will Microsoft spend on data centers in 2026?

In July Microsoft said it expected approximately $175 billion of capital expenditures, its spending on cloud and AI infrastructure and other long-lived assets, in calendar 2026. That is down from roughly $190 billion in April, which Microsoft tied to more data center leases now counting as operating leases. Its capex of $31.9 billion, $41.0 billion and $45.2 billion in the three quarters to September leaves about $57 billion of that figure for October to December, by our calculation.

Does Microsoft pay dividends?

Yes. Microsoft pays a quarterly dividend of $0.98 a share, payable on December 10, 2026 to shareholders of record on November 19, after an 8% increase announced on September 15, 2026.

News Earnings Technology

About Stock Titan Editorial Team

The Stock Titan Editorial Team is a group of market analysts and data scientists who specialize in transforming complex financial data into actionable insights.

Our team continuously monitors and integrates data from official sources including SEC filings, stock exchanges, and verified financial data providers directly into the StockTitan platform.

We maintain a neutral, unbiased approach to market analysis. Our goal is to present verified data clearly and accurately, helping investors of all experience levels understand market trends, sector performance, and individual stock movements.

Every article undergoes multi-source verification to ensure data accuracy and reliability.

Our mission: Make complex financial data accessible to everyone through thorough research, verified sources, and clear explanations.

Read our editorial standards and AI policy

The information provided in this article is for educational and informational purposes only. It does not constitute financial advice, investment recommendation, or an endorsement of any particular investment strategy. Past performance does not guarantee future results. Investors should conduct their own research and consult with a qualified financial advisor before making investment decisions.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google