INTEGRA REPORTS RECORD MINING AND ORE-STACKING RATES AT FLORIDA CANYON, 30% INCREASE IN SECOND QUARTER GOLD PRODUCTION

(Moderate)
(Very Positive)
Tags

Integra Resources (TSXV: ITR, NYSE American: ITRG) reported a strong interim Q2 2026 operational update for the Florida Canyon Mine, with gold production of 16,379 oz, up 30% from Q1. The quarter saw record total material movement, including 4.4M tonnes of ore and 3.6M tonnes of waste mined at a strip ratio of 0.81, averaging 87,867 tpd.

Ore mined rose 47% and ore placed on heap leach pads increased 45% quarter-over-quarter, while processed grade improved 21%. Year-to-date gold production reached 29,014 oz. Integra maintains 2026 gold guidance of 70,000–75,000 oz, supported by higher mining and stacking rates and its N2 ore blending strategy. An updated Florida Canyon Technical Report outlines an 8-year mine life, a 74% increase in Proven and Probable Mineral Reserves, a 17% increase in expected annual gold production and projected after-tax free cash flow of $0.8B. Consolidated cash and cash equivalents were $111.1M at June 30, 2026. Q2 financials will be released on August 11, 2026, followed by a conference call on August 12, 2026.

Loading...
Loading translation...

Positive

  • Gold production +30% QoQ to 16,379 oz at Florida Canyon in Q2 2026
  • Ore mined +47% QoQ to 4.4M tonnes; ore to leach pads +45% to 4.2M tonnes
  • Record mining rate of 87,867 total tonnes per day, 16% higher than Q1 2026
  • Strip ratio reduced to 0.81, a 38% quarter-over-quarter decrease
  • Technical Report shows 74% increase in Proven & Probable Reserves and $0.8B after-tax free cash flow
  • Strong liquidity with $111.1M in cash and cash equivalents as of June 30, 2026

Negative

  • Gold recovery rate decreased from 59.9% in Q1 2026 to 57.8% in Q2 2026

News Explained

The reported US$111,132 thousand cash-and-cash-equivalents figure at June 30, 2026 is preliminary and may differ from final unaudited second-quarter results scheduled for August 11, 2026.

News Market Reaction – ITRG

+1.41%
3 alerts
+1.41% Session close to close
$433.93M Market Cap
0.4x Rel. Volume

In the Jul 24 session, ITRG gained 1.41%, reflecting a mild positive market reaction. Our momentum scanner triggered 3 alerts that day, indicating moderate trading interest and price volatility.

Data tracked by StockTitan Argus on the day of publication.

Market Context

Historical news_id 1074560 provides a -2.09% 24-hour comparator for Florida Canyon disclosures. For ...
Analysis

Historical news_id 1074560 provides a -2.09% 24-hour comparator for Florida Canyon disclosures. For this operational update, that record supports watching the final Q2 financial statements alongside production delivery; preliminary figures and guidance remain key risks.

Key Figures

Q2 gold production: 16,379 ounces Gold production increase: 30% Ore mined increase: 47% +5 more
8 metrics
Q2 gold production 16,379 ounces Florida Canyon, second quarter 2026
Gold production increase 30% Q2 2026 versus Q1 2026
Ore mined increase 47% Quarter-over-quarter
Ore placed increase 45% Ore placed on heap leach pads, quarter-over-quarter
Full-year gold guidance 70,000 to 75,000 ounces 2026 guidance maintained
Mine life 8 years Updated Florida Canyon Feasibility Study and Life of Mine Plan
Mineral reserve increase 74% Proven and Probable Mineral Reserve
After-tax free cash flow $0.8 billion Updated Florida Canyon Technical Report

Historical Context

5 past events · Latest: Jun 26 (Neutral)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jun 26 Annual meeting results Neutral -4.7% Shareholders approved director elections, auditor appointment, and a rolling equity incentive plan.
Jun 25 Feasibility study Positive -2.1% Updated study increased reserves, extended mine life, and outlined substantial after-tax free cash flow.
Jun 02 Engineering appointment Neutral -1.1% Ausenco was appointed to lead DeLamar detailed engineering through the permitting process.
May 29 Permitting milestone Positive +1.9% The BLM published a Notice of Intent, formally beginning the DeLamar environmental review.
May 26 Leadership appointments Neutral +2.9% Integra appointed three senior mining executives and granted related equity awards.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Recent positive Florida Canyon and permitting announcements produced divergent reactions of -2.09% and aligned reactions of +1.86%.

Key Terms

heap leach pads, strip ratio, processed grade, ni 43-101
4 terms
heap leach pads technical
"ore placed on the heap leach pads quarter-over-quarter"
A heap leach pad is an engineered, lined area where crushed ore is stacked like a large, drained sponge and a chemical solution is sprayed or dripped through it to pull out valuable metals such as gold, silver or copper. Investors care because this method is a low‑cost way to produce metal but brings operational variables (recovery rates, reagent costs, water use) and environmental/regulatory risks (permits, spills, closure liabilities) that affect profitability and project value.
strip ratio technical
"at a strip ratio of 0.81 at the Florida Canyon Mine"
Strip ratio measures how much non-valuable material (waste) must be removed to access a given amount of mineral-bearing rock (ore) at a surface mine, expressed as a simple ratio like 3:1 meaning three units of waste per one unit of ore. Investors care because a higher strip ratio typically means higher extraction costs, larger equipment and disposal needs, and lower profit margins—think of peeling more rind to get the same amount of fruit, which affects project economics and cash flow.
processed grade technical
"Processed grade | g/t Au | 0.19 | 0.23 | 0.22"
Processed grade identifies the quality level and characteristics of a commodity or material after it has been cleaned, refined, milled, or otherwise transformed from its raw form. It explains how the product was treated and which quality standards or grading rules it meets, which affects price, marketability, storage, and which buyers or channels will accept it. Think of it as a report card showing how usable and saleable a product is after processing.
ni 43-101 regulatory
"Qualified Person as defined in National Instrument 43-101"
A Canadian regulatory standard that sets the rules for how mining and exploration companies must report mineral resources and reserves, requiring technical reports prepared or signed off by an independent, certified expert. It matters to investors because it creates a consistent, transparent “inspection report” for mining projects, making it easier to compare prospects, judge the reliability of claims, and assess geological and financial risk before investing.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

TSXV: ITR; NYSE American: ITRG
www.integraresources.com

VANCOUVER, BC, July 23, 2026 /PRNewswire/ -- Integra Resources Corp. ("Integra" or the "Company") (TSXV: ITR) (NYSE American: ITRG) is pleased to provide an interim operational update for the second quarter ended June 30, 2026. Florida Canyon produced 16,379 ounces of gold during the quarter, a 30% increase from the first quarter of 2026. The increase in gold production was supported by record total material movement, including a 47% increase in ore mined and a 45% increase in ore placed on the heap leach pads quarter-over-quarter. With significantly more ore being placed on the heap leach pad in the second half of this year, the Company expects gold production to increase in the third and fourth quarters and is maintaining full-year gold production guidance of 70,000 to 75,000 ounces.

Integra Resources Logo

The Company plans to release its second quarter 2026 financial results after market close on Tuesday, August 11, 2026, followed by a conference call hosted by senior management on Wednesday, August 12, 2026 at 10:00 AM Eastern Time / 7:00 AM Pacific Time. 

(All amounts in United States ("U.S.") dollars as at June 30, 2026, unless otherwise stated.)

Q2 2026 Operational Highlights:

  • Key Operating Metric Improvements Quarter-over-Quarter1:
    • 30% increase in gold produced
    • 16% increase in total tonnes mined
    • 47% increase in ore mined
    • 45% increase in ore placed on heap leach pads
    • 21% increase in processed grade
    • 38% decrease in strip ratio
    • 8% decrease in waste mined
  • The Company mined 4.4 million ("M") tonnes of ore and 3.6 M tonnes of waste at a strip ratio of 0.81 at the Florida Canyon Mine ("Florida Canyon" or the "Mine"). As a result, mining rates averaged 87,867 total tonnes per day ("tpd"), representing a record rate of total material movement at the Mine.  
  • The Florida Canyon Mine produced 16,379 ounces of gold and sold 15,794 ounces of gold during the second quarter, a 30% increase in gold production quarter-over-quarter. Gold production is expected to continue increasing through the second half of 2026, supported by the implementation of the N2 ore blending strategy, higher mining rates and increased ore stacking rates on the heap leach pads.
  • Florida Canyon achieved record mining rates during the second quarter, with total tonnes mined increasing 16% from the first quarter. The higher mining rates reflect the successful integration of new mining equipment into the fleet, positioning the operation for stronger gold production in the second half of 2026.
  • The Company released an updated Feasibility Study and Life of Mine Plan (the "Technical Report") for Florida Canyon which highlighted a materially enhanced operation with an 8-year mine life, a 74% increase in Proven and Probable Mineral Reserve, a 17% increase in annual gold production and $0.8 billion ("B") in after-tax free cash flow2.

(1)

See first quarter and second quarter results below in the table titled: Second Quarter and Year-to-Date 2026 Florida Canyon Mine Operational Update.

(2)

See news release dated June 25, 2026. This is a non-GAAP financial measure, please refer to the "Cautionary Note Regarding Non-GAAP Measures" disclosure at the end of this news release for a description of this measure.

George Salamis, President, CEO and Director of Integra commented:

"Florida Canyon continued to build operational momentum during the second quarter, with gold production increasing 30% from the first quarter and both total material moved and ore placed on the heap leach pads reaching record levels. Approximately 4.2 million tonnes of ore were placed on the heap leach pads during the quarter, a 45% increase over the first quarter, creating a large inventory of recoverable gold ounces that is expected to support stronger gold production through the balance of this year.

Beyond 2026, work is underway for the long-term transformation of Florida Canyon. As outlined in the June 2026 Technical Report news release, beginning in 2027 the Company expects higher annual gold production, lower operating costs, and stronger cash flow from an 8-year mine life, creating a stable operation to support the continued advancement of the DeLamar and Nevada North Projects."

Second Quarter and Year-to-Date 2026 Florida Canyon Mine Operational Update



Three months ended

March 31,

Three months ended
June 30,

Six months ended
June 30,


Unit (1)

2026

2026

2026

Ore mined

kt

3,008

4,417

7,425

Waste mined

kt

3,902

3,579

7,481

Strip ratio

waste/ore

1.30

0.81

1.01

Ore direct to heap leach pads

kt

1,074

2,332

3,406

Ore crushed

kt

1,784

1,824

3,608

Total ore to heap leach pads

kt

2,858

4,156

7,014

Processed grade

g/t Au

0.19

0.23

0.22

Gold recovery rate

%

59.9 %

57.8 %

58.5 %

Gold produced

oz

12,635

16,379

29,014

Gold sold

oz

12,518

15,794

28,312

Silver produced

oz

11,622

12,392

24,014

Silver sold

oz

11,466

12,581

24,047

(1)

Unit abbreviations: kt = 1,000 metric tonnes, g/t = grams per tonne, Au = gold, oz = troy ounce

(2)

Ore crushed includes material from stockpiles and ore mined.

Florida Canyon produced 16,379 ounces of gold in the second quarter 2026, with 29,014 ounces of gold produced year-to-date. The blending strategy developed in the first quarter of 2026 for N2 ore continues to leach as expected.

Mining activity at Florida Canyon continued to accelerate during the second quarter, with approximately 8 M tonnes mined in total at an average mining rate of approximately 87,867 tpd. Record mining rates were achieved this quarter due to the integration of new mining equipment into the fleet over the last two quarters and shorter haul distances. Subsequent to quarter-end, ore stacking on the heap leach pads has exceeded expectations in July, positioning the operation for stronger gold production over the next two quarters. As a result of these mining rates, the Company maintains annual gold production guidance in 2026 of 70,000 to 75,000 ounces, with increased gold production expected over the balance of the year.

Second Quarter 2026 Consolidated Financial Position

Consolidated Financial Position

Unit (1)

June 30, 2026

Cash and cash equivalents

$000s

$111,132

(1)

Unit abbreviations: $000s = thousands of U.S. dollars

The financial information presented above is preliminary in nature and subject to completion of the Company's quarter-end financial reporting process. Final unaudited financial results may differ from these amounts and will be reported as part of the Company's quarter-end financial statements. Complete financial results for the second quarter 2026 will be reported and filed on Integra's profile on SEDAR+ at www.sedarplus.ca and EDGAR profile at www.sec.gov on Tuesday, August 11, 2026.

Second Quarter 2026 Conference Call

Integra will host a conference call and webcast on Wednesday, August 12, 2026, at 10:00 AM Eastern Time / 7:00 AM Pacific Time, to discuss the second quarter 2026 results. Details for the conference call and webcast are included below.

Dial-In Numbers / Webcast:

Conference ID: 4645464
Toll Free: (800) 715-9871
Toll: +1 (646) 307-1963
Webcast: https://events.q4inc.com/attendee/102640394

About Integra Resources Corp.

Integra is a growing precious metals producer in the Great Basin of the Western United States. Integra is focused on demonstrating profitability and operational excellence at its principal operating asset, the Florida Canyon Mine, located in Nevada. In addition, Integra is committed to advancing its flagship development-stage heap leach projects: the past producing DeLamar Project located in southwestern Idaho and the Nevada North Project located in western Nevada. Integra creates sustainable value for shareholders, stakeholders, and local communities through successful mining operations, efficient project development, disciplined capital allocation, and strategic M&A, while upholding the highest industry standards for environmental, social, and governance practices.

ON BEHALF OF THE BOARD OF DIRECTORS

George Salamis
President, CEO and Director

CONTACT INFORMATION
Corporate Inquiries: ir@integraresources.com
Company website: www.integraresources.com
Office phone: 1 (604) 416-0576

Qualified Person 

The scientific and technical information contained in this news release has been reviewed and approved by James Frost, P.Eng., Director, Technical Services of Integra, who is a "Qualified Person" as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101").

Forward Looking Statements

Certain information set forth in this news release contains "forward‐looking statements" and "forward‐looking information" within the meaning of applicable Canadian securities legislation and in applicable United States securities law (referred to herein as forward‐looking statements). Forward-looking statements are often identified by the use of words such as "may", "will", "could", "would", "anticipate", "believe", "expect", "intend", "potential", "estimate", "budget", "scheduled", "plans", "planned", "forecasts", "goals" and similar expressions. Except for statements of historical fact, certain information contained herein constitutes forward‐looking statements which includes, but is not limited to, statements with respect to: the future financial or operating performance of the Company and its mineral properties; the expected increase in gold production in the second half of 2026; the Company's 2026 guidance; the development, operational and economic results of the Technical Report for Florida Canyon, including cash flows, revenue potential, development, expenditures, and timing thereof, extraction rates, life-of-mine projections and cost estimates; the realization of the expected economics of Florida Canyon; future development plans; and the date and timing of the conference call and webcast to the second quarter 2026 results. Forward-looking statements are based on a number of factors and assumptions made by management and considered reasonable at the time such statement was made. Assumptions and factors include: the Company's ability to complete its planned exploration and development programs; the absence of adverse conditions at the Company's mineral properties; no unforeseen operational delays; no material delays in obtaining necessary permits; results of independent engineer technical reviews; the possibility of cost overruns and unanticipated costs and expenses; the price of gold remaining at levels that continue to render the Company's mineral properties economic; the Company's ability to continue raising necessary capital to finance operations; and the ability to realize on the mineral resource and reserve estimates. Forward‐looking statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance or result expressed or implied by such forward‐looking statements. These risks and uncertainties include, but are not limited to: general business, economic and competitive uncertainties; the actual results of current and future exploration activities; conclusions of economic evaluations; meeting various expected cost estimates; benefits of certain technology usage; changes in project parameters and/or economic assessments as plans continue to be refined; future prices of metals; possible variations of mineral grade or recovery rates; the risk that actual costs may exceed estimated costs; geological, mining and exploration technical problems; failure of plant, equipment or processes to operate as anticipated; accidents, labor disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; risks related to local communities; the speculative nature of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); title to properties; and other factors beyond the Company's control and as well as those factors included herein and elsewhere in the Company's public disclosure. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in the forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Readers are advised to study and consider risk factors disclosed in Integra's Annual Information Form dated March 24, 2026 for the fiscal year ended December 31, 2025, which is available on the SEDAR+ issuer profile for the Company at www.sedarplus.ca and available as Exhibit 99.1 to Integra's Form 40-F, which is available on the EDGAR profile for the Company at www.sec.gov.

Investors are cautioned not to put undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date of this news release and, accordingly, are subject to change after such date. The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws. Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed online under the Company's profile on SEDAR+ at www.sedarplus.ca.

Cautionary Note Regarding Non-GAAP Financial Measures

Alternative performance measures in this news release such as "free cash flow" are furnished to provide additional information. These non-GAAP performance measures are included in this news release because these statistics are used as key performance measures that management uses to monitor and assess performance of Florida Canyon, and to plan and assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a standardized meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with IFRS.

Free Cash Flow

Free cash flows are revenues net of operating costs, royalties, capital expenditures and cash taxes. The Company believes that this measure is useful to the external users in assessing the Company's ability to generate cash flows from the Project.

Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves

NI 43-101 is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource and reserve information contained in this news release may not be comparable to similar information disclosed by domestic United States companies subject to the SEC's reporting and disclosure requirements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Email: ir@integraresources.com 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/integra-reports-record-mining-and-ore-stacking-rates-at-florida-canyon-30-increase-in-second-quarter-gold-production-302833659.html

SOURCE Integra Resources Corp.

FAQ

How much gold did Integra Resources (ITRG) produce at Florida Canyon in Q2 2026?

Integra Resources produced 16,379 ounces of gold at Florida Canyon in Q2 2026. According to the company, this was a 30% increase over Q1 2026, supported by higher mining rates, more ore stacked on heap leach pads, and improved processed grades.

What is Integra Resources’ 2026 gold production guidance for Florida Canyon (ITRG)?

Integra Resources is maintaining 2026 gold production guidance of 70,000 to 75,000 ounces for Florida Canyon. According to the company, record mining and ore-stacking rates, plus the N2 ore blending strategy, are expected to support higher gold output in the second half of 2026.

What operational improvements did Integra Resources (ITRG) report quarter-over-quarter in Q2 2026?

Integra Resources reported a 47% increase in ore mined, a 45% increase in ore placed on heap leach pads, and a 21% rise in processed grade. According to the company, total tonnes mined grew 16%, while the strip ratio declined 38% to 0.81.

What does the updated Florida Canyon Technical Report mean for Integra Resources (ITRG)?

The updated Technical Report outlines an 8-year mine life and a 74% increase in Proven and Probable Reserves at Florida Canyon. According to Integra Resources, it also indicates a 17% rise in expected annual gold production and projected after-tax free cash flow of $0.8 billion.

What was Integra Resources’ cash position as of June 30, 2026 (ITRG)?

As of June 30, 2026, Integra Resources reported $111.1 million in cash and cash equivalents. According to the company, this preliminary figure will be finalized with full Q2 2026 financial results, expected to be filed on August 11, 2026.