Namib Minerals Completes Dewatering at Redwing Mine, Delivering the First Milestone of its Five-Step Restart Pathway Ahead of Schedule.
Dewatering at Redwing is finished early, keeping Namib Minerals’ five-step restart schedule and fully funded DFS programme on track.
Rhea-AI Summary
Namib Minerals (NAMM) has completed dewatering at its Redwing Mine in Zimbabwe, delivering Step 1 of its five-step restart pathway ahead of the original Q4 2026 target.
Completion restores safe underground access and allows mapping, sampling and geotechnical and hydrological work that feed the Definitive Feasibility Study (DFS). The DFS technical programme is fully funded and remains on track to conclude in early Q1 2027. Step 2 (DFS technical programme) is underway, while later stages, including an 8,750‑metre surface drilling campaign, construction and restart, are scheduled through Q4 2027 and beyond, with some steps dependent on future funding and a positive development decision.
Positive
- Step 1 dewatering completed ahead of Q4 2026 target at Redwing Mine
- DFS technical programme fully funded and on track to conclude in early Q1 2027
Negative
- Step 3 resource definition targeted for Q4 2027 and designated as the next funding stage
Key Figures
- Restart pathway
- 5 steps
- Redwing Mine restart plan
- Dewatering target
- Q4 2026
- Step 1 target, completed ahead of schedule
- DFS completion
- Early Q1 2027
- Technical programme remains fully funded and on schedule
- Resource definition drilling
- 8,750 metres
- Step 3 planned resource definition and bankability work
Historical Context
-
Company established a five-step Redwing restart pathway with dewatering targeted for Q4 2026
-
Dewatering lowered underground water levels while pumping capacity exceeded requirements
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
definitive feasibility study technical
geotechnical technical
hydrological technical
AI-generated analysis. How Rhea-AI works. Not financial advice.
New York, Sept. 21, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib Minerals" or "the Company") (Nasdaq: NAMM), an established African gold producer with a portfolio of mining assets in Zimbabwe, today announced the completion of the dewatering programme at Redwing Mine, the first of the five steps in the restart pathway the Company set out on July 20, 2026.
On July 20, 2026, Namib Minerals published a defined five-step pathway and targeted milestone schedule for the restart of Redwing Mine, with dewatering as Step 1 and completion targeted for Q4 2026. That step is now complete, ahead of the targeted schedule.
Completion of dewatering restores safe access to the underground workings, enabling underground mapping, sampling and the geotechnical and hydrological work programmes that feed the technical programme of the Definitive Feasibility Study ("DFS"). The DFS technical programme remains fully funded through to completion and on track to conclude in early Q1 2027, unchanged from the schedule published in July.
Tulani Sikwila, Chief Executive Officer and Chairman of Namib Minerals, commented: "Dewatering was the gateway to everything that follows at Redwing, and we have delivered it ahead of the schedule we published. We set out a five-step pathway in July precisely so that our shareholders could measure us against it. Step one is done, step two is funded and underway, and we intend to keep reporting against that same map."
Redwing Restart Pathway
| Step | Scope | Target | Status |
| 1 – Dewatering | Staged pumping to safely access underground workings | Q4 2026 | Completed |
| 2 – DFS technical programme | Engineering, metallurgical, geotechnical, hydrological, environmental and financial workstreams; fully funded | Early Q1 2027 | Underway |
| 3 – Resource definition and bankability | 8,750-metre surface exploration drilling and associated work | Q4 2027 | Next funding stage |
| 4 – Construction | Staged restart capital mobilisation and construction on a positive decision | Upon DFS completion | — |
| 5 – Restart | Commissioning and phased return to production | Following construction | — |
About Namib Minerals
Namib Minerals (NASDAQ: NAMM) is a gold producer, developer and explorer with operations focused in Zimbabwe. Currently Namib Minerals operates the How Mine, an underground gold mine in Zimbabwe, and aims to restart two assets in Zimbabwe. For additional information, please visit namibminerals.com.
Forward-Looking Statements
This press release may include forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Any statements that refer to restarts of mines, future financing or other future events or circumstances, including any underlying assumptions, are also forward-looking statements. Forward-looking statements include, without limitation, statements regarding the Company’s governance and leadership structure, its financing programme and the planned restart of the Redwing Mine. Forward-looking statements are based on current expectations, are inherently subject to uncertainties and changes in circumstance, and speak only as of the date of such statement. There can be no assurance that future developments will be those that have been anticipated. These statements involve a number of risks and uncertainties described in the filings we make with the Securities and Exchange Commission, and you should carefully consider those factors. We caution you against placing undue reliance on forward-looking statements, which reflect current beliefs and are based on information currently available as of the date a forward-looking statement is made.
Contact:
Investor Relations:
Investor.relations@namibminerals.com
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
What are the five steps in Namib Minerals’ Redwing Mine restart pathway and their current status?
The restart pathway has five steps: 1) Dewatering – staged pumping to safely access underground workings, targeted for Q4 2026 and now completed; 2) DFS technical programme – engineering, metallurgical, geotechnical, hydrological, environmental and financial workstreams, fully funded, targeted for early Q1 2027 and underway; 3) Resource definition and bankability – 8,750-metre surface exploration drilling and associated work, targeted for Q4 2027 and marked as the next funding stage; 4) Construction – staged restart capital mobilisation and construction on a positive decision, planned upon DFS completion; and 5) Restart – commissioning and phased return to production following construction.
How does completing dewatering affect the Definitive Feasibility Study at Redwing Mine?
Completion of dewatering restores safe access to underground workings, allowing underground mapping, sampling and geotechnical and hydrological work programmes. These work programmes feed into the technical programme of the Definitive Feasibility Study, which remains fully funded and scheduled to conclude in early Q1 2027.