Energy Fuels Announces Q1-2025 Results
- Strong financial position with $214.61M working capital and zero debt
- 22% increase in uranium mining production guidance for 2025
- 193% increase in finished goods inventory guidance
- Record monthly mining production of 160,000 pounds U3O8 in April 2025
- Discovery of additional high-grade zones at Pinyon Plain mine
- Strategic partnerships with POSCO International and Chemours Company
- Substantial inventory position: 1.31M pounds of U3O8, 905K pounds V2O5, and rare earth elements
- Q1 2025 net loss of $26.32 million ($0.13 per share)
- No uranium sales during Q1 2025
- Higher operating expenses due to increased headcount
- Lower grade HMS production impacting costs
Insights
Energy Fuels reports Q1 loss but increases uranium production guidance by 22%, maintains strong cash position, and advances rare earth strategy.
Energy Fuels has implemented a counter-cyclical strategy in Q1-2025, deliberately withholding uranium sales while significantly ramping up production. Despite posting a
The standout operational highlight comes from the Pinyon Plain mine, which achieved exceptional uranium grades of 1.64% U₃O₈ in April - remarkably high by U.S. standards where grades typically run below 0.5%. This high-grade ore allowed extraction of 151,400 pounds of uranium from just 4,604 tons of material in a single month. The company now expects to produce up to 1 million pounds of finished U₃O₈ in 2025, substantially higher than previous guidance.
Energy Fuels maintains a rock-solid balance sheet with
Beyond uranium, the company's diversification strategy is advancing through strategic partnerships with POSCO International and The Chemours Company, positioning Energy Fuels in the non-Chinese rare earth element supply chain. Their heavy mineral sands segment generated
With operations at additional mines being prepared for production, Energy Fuels projects potential output of approximately 2 million pounds annually by 2026, with longer-term potential to reach 5 million pounds as larger projects come online. This scalability provides significant optionality as nuclear power growth accelerates globally.
Energy Fuels significantly increases 2025 uranium production and finished goods inventory guidance by
"Our team continues to build Energy Fuels into a leading critical minerals company in
"Energy Fuels elected not to make any uranium sales during the first quarter, due to no scheduled contract deliveries, relatively weak uranium prices, and our strong belief that spot and long-term prices will be higher in the future. However, our uranium mining operations are ramping up extremely well, with uranium grades at our Pinyon Plain mine significantly exceeding expectations, resulting in significant increases in our 2025 Production and Inventory Guidance, including a
"I should also add that after the end of Q1, combined ore production from our Pinyon Plain,
"We are also advancing our rare earth capabilities. As previously announced, we have entered into a strategic collaboration with
"With appropriate government and/or market support, Energy Fuels is prepared to make hundreds of millions of dollars of investments in
Q1-2025 Highlights
Unless noted otherwise, all dollar amounts are in
- Robust Balance Sheet with Over
of Liquidity and No Debt: As of March 31, 2025, the Company had$210 million of working capital including$214.61 million of cash and cash equivalents,$73.00 million of marketable securities (interest-bearing securities and uranium stocks),$89.64 million of trade and other receivables,$20.37 million of inventory, and no debt, which puts the Company in a strong position as it advances its various projects.$67.68 million - Over
of Additional Liquidity from Market Value of Inventory: At May 2, 2025 commodity prices, the Company's product inventory has a market value of approximately$11 Million , while the balance sheet reflects product inventory carried at cost of$46.39 million .$34.51 million - Incurred Net Loss of
Million: During the quarter ended March 31, 2025, the Company incurred a net loss of$26 , or$26.32 million per common share, on$0.13 of revenue. The loss was due to the Company's ramping up of mining at its Pinyon Plain,$16.90 million La Sal and Pandora Mines and the election not to sell any of its 595,000 pounds of finished goods (U3O8) inventories during the quarter, retaining such inventories for sales at higher prices under the Company's long-term contracts and expected higher uranium prices in the future, combined with recurring operating expenses, including additional operating expenses associated with the increased headcount of retained Base Resources employees (currently in the process of being reduced) and Kwale mine reclamation costs and higher costs applicable to heavy mineral sand ("HMS") revenues from the lower grade HMS produced at the end of the Kwale mine life. - Heavy Mineral Sands Revenue: During the three months ended March 31, 2025, the Company sold 6,836 tonnes of rutile, 12,852 tonnes of ilmenite, both used for the production of titanium products, and 1,429 tonnes of zircon, used for the production of zirconium, for total HMS revenues of
.$15.54 million - Well-Stocked to Capture Market Opportunities and meet Long-term Contract Obligations: As of March 31, 2025, the Company held a total of 1,310,000 pounds of U3O8 in inventory, including 595,000 pounds of finished U3O8, 605,000 pounds of U3O8 in ore and raw materials, and 110,000 pounds of work-in-progress U3O8. Inventory increased from last quarter due to Pinyon Plain,
La Sal and Pandora mine ore production, the purchase of 50,000 pounds of U3O8 on the spot market, and additional alternate feed materials received. The Company expects these uranium inventories to continue increasing, as we continue to mine additional ore and potentially purchase ore from third parties. The Company also held 905,000 pounds of finished vanadium ("V2O5"), 37,000 kilograms ("kg") of finished separated neodymium praseodymium ("NdPr") and 9,000 kg of finished high purity, partially separated mixed "heavy" samarium-plus ("Sm+") rare earth carbonate ("RE Carbonate") in inventory. Having stockpiled mined ore available at the Mill, which can be processed into finished U3O8 product on relatively short notice, and other inventories, gives the Company more flexibility in securing long-term sales contracts on the most favorable terms when needed, rather than merely accepting contracts at current prices when fundamentals suggest higher prices may be expected in the future. - Samples of NdPr Actively Being Qualified by Potential Customers: NdPr produced at the Mill is currently in the process of being qualified with permanent magnet manufacturers and other potential customers which, upon successful qualification, would set the stage for potential future offtakes.
- Strategic Announcements on Creating
U.S. and Non-China Critical Mineral Supply Chains: Two announcements this quarter showcase Energy Fuels' progress on creating a domestic rare earth oxide supply chain. Energy Fuels announced an alliance with The Chemours Company to expand the domestic supply chain for critical minerals and raw materials, including monazite for processing into rare earth oxides at Energy Fuels' White Mesa Mill inUtah , and a Memorandum of Understanding with POSCO International to validate Energy Fuels' NdPr oxide for permanent magnets for use in EV and Hybrid EV drivetrains, which could be available toU.S. , European, and allied Asian OEM customers as soon as later this year. - Landmark Agreement with the Navajo Nation: Energy Fuels signed a landmark agreement with the Navajo Nation, the largest and most populous indigenous tribe in
the United States , establishing additional requirements, over and above already highly protective federal regulations, to assure the Nation that uranium ore transport from the Pinyon Plain mine to the White Mesa Mill is performed safely and responsibly to the highest standards. Additionally, Energy Fuels agreed to accept (for free) 10,000 tons of uranium-bearing materials from historic abandoned uranium mines on the Navajo Nation, which are a relic ofU.S. government Cold War-era uranium programs.
Uranium Milestones:
- The Company produced a total of 150,000 pounds of finished U3O8 during the three months ended March 31, 2025 from stockpiled alternate feed materials and newly mined ore.
- The Company invested in 50,000 pounds of U3O8, at a price of
per pound, as the Company believes prices are likely to increase in the future.$64.75 - During April 2025, the Company mined 4,604 tons of ore, containing roughly 151,400 pounds of uranium with an average grade of
1.64% U3O8 at the Pinyon Plain mine, which the Company believes is one of the highest-grade uranium mines inU.S. history. Production rates at the mine have steadily increased over the past several months, with April's results representing the largest monthly production rate since mining began last year. - The Company currently expects to process approximately 700,000 pounds of U3O8 in Q4 2025 from stockpiled ore mined from its Pinyon Plain,
La Sal and Pandora mines, with the remainder of the mined ore and Alternate Feed Materials retained in stockpile at the mines or Mill for processing during 2026 or 2027, subject to market conditions, contract requirements, and the Mill's schedule. This is expected to result in the production of an additional 700,000 pounds of finished U3O8 in Q4 2025 from stockpiled and mined ore from the Company's Pinyon Plain,La Sal and Pandora mines, which when added to the Company's expected production of approximately 300,000 pounds of finished U3O8 through the first half of 2025 from existing conventional ore inventories and Alternate Feed Materials, would result in the production of up to 1,000,000 pounds of finished U3O8 product in 2025. - As a result of these developments, the Company is pleased to provide its updated production, sales and inventory guidance for 2025 as follows:
Previous Guidance | Revised Guidance | Change in | |||||
Low | High | Low | High | Midpoint (%) | |||
Mined (contained pounds of U3O8) | 730,000 | 1,170,000 | 875,000 | 1,435,000 | 22 % | ||
Alternate Feed Materials and other (contained pounds of U3O8)(1) | 160,000 | 200,000 | 160,000 | 200,000 | — % | ||
Processed (pounds of U3O8) | 200,000 | 250,000 | 700,000 | 1,000,000 | 278 % | ||
Sales (pounds of U3O8)(2) | 200,000 | 300,000 | 220,000 | 220,000 | (12) % | ||
Finished goods (pounds of U3O8) | 290,000 | 445,000 | 925,000 | 1,225,000 | 193 % | ||
Total inventories (contained pounds of U3O8) | 1,655,000 | 2,340,000 | 1,985,000 | 2,585,000 | 14 % |
(1) "Other" includes ore purchases from 3rd party miners and potential cleanup from historic abandoned uranium mines.
(2) The Company has not elected to sell inventory into the spot market at this time, but may do so subject to market conditions.
- The Company continues to mine and stockpile ore from its Pinyon Plain,
La Sal and Pandora mines, which is expected to total approximately 875,000 to 1,435,000 pounds of U3O8 contained in approximately 55,000 to 80,000 tons of ore from these mines during 2025, subject to market conditions, mining rates and other factors. This is an increase in previously reported guidance of approximately22% . The Company also expects to purchase uranium ore from third-party miners in the region, and there is the potential to receive additional Alternate Feed Materials and mine cleanup materials, expected to add a total of approximately 160,000 to 200,000 pounds of additional contained uranium to ore inventories, all of which will be processed as market conditions, Mill schedules, and contract requirements may warrant. - The Company expects to sell 220,000 pounds of uranium during 2025, under the Company's existing long-term contracts with utilities. As a result of these sales, plus planned 2025 mine production, at the end of 2025, the Company expects to hold a total of 1,985,000 to 2,585,000 pounds of U3O8 in ore inventories plus finished product, including approximately 925,000 to 1,225,000 pounds of finished U3O8 inventory. This expected finished goods uranium inventory would be sufficient to satisfy the Company's 2025, 2026 and a large portion of the Company's 2027 delivery requirements, at higher margins than would be expected compared to spot sales at this time.
- The Company has been performing underground drilling in the "Juniper Zone" of the Pinyon Plain mine, with exceptional drill results from its 2024 – 2025 underground drill program showing high-grade intercepts within the previously defined Mineral Resource as well as above the existing mineralized zone, which exceed previous expectations (linked here). The Company is in the process of completing a
U.S. Subpart 1300 of Regulation S-K ("S-K 1300") and Canadian National Instrument 43-101 ("NI 43-101") compliant technical report, which is expected to significantly add to the uranium resources. - The Company continues to observe positive results from ongoing drilling at its Nichols Ranch in-situ recovery ("ISR") Project in
Wyoming . Both the Nichols Ranch Project and Whirlwind Mine inColorado are being prepared for production, as market conditions warrant. Production from these mines, when combined with production from Pinyon Plain,La Sal and Pandora, alternate feed materials, uranium from monazite, and third-party uranium ore purchases, would be expected to increase the Company's production run-rate to roughly two million pounds per year by as early as 2026. - The Company continued advancing permitting and other pre-development activities on its large-scale Roca Honda and Bullfrog uranium projects during the three months ended March 31, 2025, which together with its Sheep Mountain Project, have the potential to expand the Company's uranium production to a run-rate of up to five million pounds of U3O8 per year in the coming years.
- As of May 2, 2025, the spot price of U3O8 was
per pound and the long-term price of U3O8 was$70.00 per pound, according to data from TradeTech.$80.00 - The Company's Roca Honda Project in
New Mexico was included on theU.S. Federal Infrastructure Projects, Permitting Dashboard list of FAST-41 Transparency Projects, which according to the White House, "makes the environmental review and authorizations schedule for these vital mineral production projects publicly available and allows all of these projects to benefit from increased transparency. The public nature of the dashboard ensures that all stakeholders, from project sponsors and community members to federal agency leaders have up-to-date accounting of where each project stands in the review process. This transparency leads to greater accountability, ensuring a more efficient process."
Rare Earth Element Milestones:
- The Company held about 37,000 kg of separated NdPr from its newly commissioned Phase 1 REE separation circuit at the Mill, along with 9,000 kg of finished high purity, partially separated mixed "heavy" Sm+ RE Carbonate.
- Samples of the Company's NdPr product have been sent to permanent magnet and other companies around the world for product qualification, including POSCO International. Initial testing responses have been positive.
- On April 17, 2025, Energy Fuels announced that it had successfully developed the technical ability it believes is required to commercially produce samarium, gadolinium, dysprosium, terbium, lutetium, yttrium, and other oxides, at scale through expansion of its existing REE production capability in
Utah . On April 4, 2025, the Chinese government announced export restrictions on these REEs, which are needed for key defense technologies. - The Company continues the process of updating the White Mesa Mill's AACE International ("AACE") Class 4 Pre-Feasibility Study (not a Pre-Feasibility Study subject to or intended to be compliant with NI 43-101 or S-K 1300), originally released in Q2-2024 to increase throughput to a total of 50,000 tpa of monazite, producing roughly 5,000 tpa of NdPr, 150 to 225 tpa of Dy, and 50 to 75 tpa of Tb. The Mill PFS referenced above can be viewed on the Company's website, www.energyfuels.com.
Heavy Mineral Sands:
- On November 28, 2024, the Government of
Madagascar lifted the suspension on the development of the Toliara Project, and on December 5, 2024, the Company entered into a Memorandum of Understanding (the "MOU") with the Government ofMadagascar setting forth certain key terms applicable to the Toliara Project along with mechanisms to achieve long-term fiscal stability for the Project. Now that the Government ofMadagascar has lifted the suspension, the Company has re-commenced development and investment in the Project, is re-establishing community and social programs, and is advancing the technical, environmental and social activities necessary to achieve a final investment decision ("FID"), which the Company expects to make in Q2-2026. While the Company is progressing towards an FID, the Company will continue working with the Government ofMadagascar to formalize the terms and conditions set out in the MOU to achieve long-term fiscal stability for the Project, which currently includes promulgation of revisions to the existing Malagasy law establishing a special regime for large scale investments in the Malagasy mining sector, and certification of the Project under the revised law (with an investment agreement, as needed) after it is approved by the Malagasy Parliament. - The Company continued to advance the Donald Project (the "Donald Project"), a large monazite-rich HMS project in
Australia , pursuant to its joint venture with Astron Corporation limited. The Company expects that an FID could be made on the Donald Project as early as the latter half of 2025. - During the three months ended March 31, 2025, the Company also continued to advance its wholly owned Bahia HMS project in
Brazil (the "Bahia Project") with its Phase 2 drilling campaign, which is expected to continue during 2025. Additionally, the Company completed bulk test work on a 2.5 tonne sample in March 2024, and recently shipped a larger 15 tonne sample to theU.S. for additional process test work. Subject to permitting, finalization of surface access arrangements, and completion of additional drilling, the Company expects to complete an S-K 1300 and NI 43-101 compliant mineral resource estimate on the Bahia Project in late 2025 or early 2026.
Medical Isotope Highlights:
- During Q1-2025, the Company continued to utilize its research and development ("R&D") license for the potential recovery of R&D quantities of Ra-226 at the Mill. During the remainder of 2025, Energy Fuels plans to complete its process development engineering and, upon successful completion of such engineering, expects to set up the first stages of the pilot facility and produce R&D quantities of Ra-226 for testing by end-users of the product. Upon successful production of R&D quantities of Ra-226, Energy Fuels plans to develop capabilities at the Mill for the commercial-scale production of Ra-226 in 2027-2028, conditional on completion of engineering design, securing sufficient offtake agreements for final radium production, and receipt of all required regulatory approvals and project financing. At the same time, parallel with its Ra-226 process development activities, the Company has applied for a license to concentrate R&D quantities of Ra-228 at the Mill and is currently performing engineering on its process development and R&D pilot facility for Ra-228 production.
Vanadium:
- The Company chose not to execute any vanadium sales during the three months ended March 31, 2025 and holds about 905,000 pounds of V2O5 in inventory.
- As of May 2, 2025, the spot price of V2O5 was
per pound, according to data from Fastmarkets.$5.24
Mr. Chalmers continued:
"We invite all stakeholders to join us in our upcoming May 8, 2025, earnings call, details of which are below, to learn more about our exciting achievements."
Conference Call and Webcast at 9:00 AM MT (11:00 AM ET) on May 8, 2025:
Conference call access with the ability to ask questions:
To instantly join the conference call by phone, please use the following link to easily register your name and phone number. After registering, you will receive a call immediately and be placed into the conference call.
- Rapid Connect URL: https://emportal.ink/4jvBbbx
or
Alternatively, you may dial in to the conference call where you will be connected to the call by an Operator.
- North American Toll Free: 1-888-510-2154
To view the webcast online:
Audience URL: https://app.webinar.net/nagk7YnBLW9
Conference Replay
- Conference Replay Toronto: 1-289-819-1450
- Conference Replay North American Toll Free: 1-888-660-6345
- Conference Replay Entry Code: 59363 #
- Conference Replay Expiration Date: 05/15/2025
The Company's Quarterly Report on Form 10-Q has been filed with the
Selected Summary Financial Information:
Three Months Ended March 31, | |||
(In thousands, except per share data) | 2025 | 2024 | |
Results of Operations: | |||
Uranium concentrates revenues | $ — | $ 25,314 | |
Heavy mineral sands revenues | 15,543 | — | |
Total revenues | 16,898 | 25,426 | |
Operating income (loss) | (26,193) | 2,021 | |
Net income (loss) attributable to Energy Fuels Inc. | (26,297) | 3,639 | |
Basic net income (loss) per common share | $ (0.13) | $ 0.02 | |
Diluted net income (loss) per common share | $ (0.13) | $ 0.02 |
(In thousands) | March 31, 2025 | December 31, 2024 | Percent Change | ||
Financial Position: | |||||
Working capital | $ 214,608 | $ 170,898 | 26 % | ||
Property, plant and equipment, net | 57,031 | 55,187 | 3 % | ||
Mineral properties, net | 283,375 | 278,330 | 2 % | ||
Current assets | 256,880 | 230,187 | 12 % | ||
Total assets | 650,792 | 611,969 | 6 % | ||
Current liabilities | 42,272 | 59,289 | (29) % | ||
Total liabilities | 65,363 | 80,292 | (19) % |
ABOUT ENERGY FUELS
Energy Fuels is a leading US-based critical minerals company, focused on uranium, REEs, HMS, vanadium and medical isotopes. The Company has been the leading
Cautionary Note Regarding Forward-Looking Statements: This news release contains certain "Forward Looking Information" and "Forward Looking Statements" within the meaning of applicable
View original content to download multimedia:https://www.prnewswire.com/news-releases/energy-fuels-announces-q1-2025-results-302449361.html
SOURCE Energy Fuels Inc.